COMPETENCYDEMONSTRATION REPORTCareer Episode 3ELZUBAIR RODWAN ABDELMAJID
Competency Demonstration Report - Heating, Ventilation and Air Conditioning (HVAC) System_1
CE 3.1 Project InformationName of the project: Heating, Ventilation and Air Conditioning (HVAC) SystemInvestigationLocation of the project: DubaiProject Duration: September, 2015 to CurrentOrganization: Dunham-Bush (DB-MENA)Role and Designation during the time: Application engineerCE 3.2 Project BackgroundCE 3.2.1 Characteristics of the projectThe company Dunham-Bush has been considered to be one of the top most commercialair conditioning manufacturers with an operating experience of more than 100 years. Theyspecialize in the field of heating, ventilation, air, conditioning and refrigeration. The companyhad a wide range of HVAC/R products for their clients. The company work in the production oflarge sized chillers, thermal storage for energy, packaged units, airside systems and unitary forthe residential users. They are also used by the commercial buildings and large industrialfacilities. I had worked at this facility to learn about their working procedure for the developmentof these equipment. I had provided the business partners with the efficient amount of trainingbased on the technical theory.
Competency Demonstration Report - Heating, Ventilation and Air Conditioning (HVAC) System_2
CE 3.2.2 Objectives developed for the projectBased on the requirements of the project, I had laid out the following list of objectives tobe considered for the completion of the project:To provide the right amount of technical training of HVAC products for the Dunham-Bushbusiness partners.To manage the relationships and assigned business partners To coordinate with the factory for the understanding of the process of development of theequipment’s. To analyse the final technical and commercial bids for the project. To coordinate the respective factory production process and status for the development of theequipment and the logistics of the related matter. To ensure that all the working services are resolved with in time. CE 3.2.3 My area of workFor the completion of the project I had worked for providing the technical training to theindividuals of the Dunham-Bush business partners for the HVAC products being developed bythe company. I had helped in the management of the relationship of the assigned businesspartners of the company to ensure that they are able to meet all the contractual terms of theproject in terms of revenue and margin. I had analysed the project preparation process for thewriting of the final technical bids. I had also coordinated the logistics for ensuring the timelydelivery of the products. I had also taken care for the preparation of the reports for themanagement of the open jobs on a weekly basis.
Competency Demonstration Report - Heating, Ventilation and Air Conditioning (HVAC) System_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Introduction to Professional Engineering
|13
|2918
|194

Competency Demonstration Report- PDF
|8
|1635
|152

ITC 493 - Competency Demonstration Report - Multiple Machinery Operations
|8
|1633
|210

WOOMESH RAMAN KAHER.
|3
|562
|599

Upgrading Boiler Capacity and Fuel System at Cheema Boilers Ltd
|32
|10974
|354

Mechanical Engineer Resume - Kulwinder Singh
|6
|1099
|223