Schedule Management
Schedule Management
Story Points
User Story/Technical Store Number Story Points
User Story #1 2
User Story #2 3
User Story #3 4
User Story #4 2
User Story #1 – Technical Store #1 2
User Story #1 – Technical Store #2 2
User Story #2 – Technical Store #1 3
User Story #2 – Technical Store #2 3
User Story #2 – Technical Store #3 3
User Story #3 and #4 – Technical Store #1 4
User Story #3 and #4 – Technical Store #2 2
MVP Schedule
Task Name Duration Start Finish Predecessors
MVP Schedule 40 days Mon 14
Oct '19
Fri 06 Dec
'19
E-list for emergency records 18 days Mon 14
Oct '19
Wed 06
Nov '19
Analysis and planning 2 days Mon 14
Oct '19
Tue 15 Oct
'19
Design & Development - Parallel
testing 8 days Wed 16
Oct '19
Fri 25 Oct
'19 3
Testing, UAT, and improvements 8 days Mon 28
Oct '19
Wed 06
Nov '19 4
Milestone 1: E-list for emergency
records module 0 days Fri 25 Oct
'19
Fri 25 Oct
'19 4
Alarm and notification 10 days Mon 28
Oct '19
Fri 08 Nov
'19 6
Analysis and planning 2 days Mon 28 Tue 29 Oct 6
1
Schedule Management for Desklib - MVP Schedule, WBS & Gantt Chart_1

Schedule Management
Oct '19 '19
Design & Development - Parallel
testing 8 days Wed 30
Oct '19
Fri 08 Nov
'19 8
Testing, UAT, and improvements 8 days Wed 30
Oct '19
Fri 08 Nov
'19 8
Milestone 2: Alarm & Notification 0 days Fri 08 Nov
'19
Fri 08 Nov
'19 10
Select Health Items 10 days Mon 11
Nov '19
Fri 22 Nov
'19
Analysis and planning 2 days Mon 11
Nov '19
Tue 12
Nov '19 11
Design & Development - Parallel
testing 8 days Wed 13
Nov '19
Fri 22 Nov
'19 13
Testing, UAT, and improvements 8 days Wed 13
Nov '19
Fri 22 Nov
'19 13
Milestone 3: Select health items 0 days Fri 22 Nov
'19
Fri 22 Nov
'19 15
Register & Login 10 days Mon 25
Nov '19
Fri 06 Dec
'19
Analysis and planning 2 days Mon 25
Nov '19
Tue 26
Nov '19 16
Design & Development - Parallel
testing 8 days Wed 27
Nov '19
Fri 06 Dec
'19 18
Testing, UAT, and improvements 8 days Wed 27
Nov '19
Fri 06 Dec
'19 18
Milestone 4: Register/login module 0 days Fri 06 Dec
'19
Fri 06 Dec
'19 20
Changes to MVP Schedule
The duration that is estimated for the MVP is 40 days which is equivalent to 8 weeks. The
estimation is done as there will be four sprints of two weeks each that will be executed to
accomplish the task (Juricek, 2014).
2
Schedule Management for Desklib - MVP Schedule, WBS & Gantt Chart_2

Schedule Management
There are changes that can be made to the MVP schedule by running any two of these sprints
in parallel and carrying out the resource distribution accordingly. This will bring down the
duration from 8 weeks to 6 weeks.
Best Estimate of Schedule
The best estimate of the schedule is illustrated in the table above. In this schedule, the sprint 3
and the sprint 4 as select health items and register & login are being carried out in parallel
with each other. This has led to the reduction of the overall schedule by 10 days and the total
duration has come down to 6 weeks (Serrador and Pinto, 2015).
WBS & Gantt chart
The work breakdown structure for the activities under MVP is shown below.
WBS Task Name
1 MVP Schedule
1.1 E-list for emergency records
1.1.1 Analysis and planning
1.1.2 Design & Development - Parallel testing
1.1.3 Testing, UAT, and improvements
1.1.4 Milestone 1: E-list for emergency records module
3
Schedule Management for Desklib - MVP Schedule, WBS & Gantt Chart_3