logo

Scope and Time Management Plan

   

Added on  2023-01-16

11 Pages1660 Words69 Views
 | 
 | 
 | 
Running head: SCOPE AND TIME MANAGEMENT PLAN
Scope and Time Management Plan: The Bungalow Project
Name of the student:
Name of the University:
Scope and Time Management Plan_1

1SCOPE AND TIME MANAGEMENT PLAN
1. Project goal and objectives
1.1 Goal
The goal of the project is to construct a Bunglow within estimated time period and
allotted project budget considering the demand of the consumers and other specifications. It is
the role of the project manager to accomplish the Bunglow project by managing time and scope
statement. The Bunglow will be constructed on the strip footings. The prepared blueprint of the
Bunglow project implies that, it will be comprises of 6 rooms including kitchen, lounge, dining,
main bedroom, second bedroom, a guest room and a laundry with an internal plaster finishing,
timber trussed rafters and double brick veneer external walls. The construction project associates
will be paid on weekly basis. Based on complexity of their activities each of the project team
members will be paid hourly basis. As per the best case scenario duration for each activity is
needed to be increased by 50 percent to complete the project 20 percent faster than the
preliminary settings. Units for each of the activities are also chosen along with the plant cost and
material cost.
1.2 Objectives
The objectives for this specific project are as follows:
To inspect the location or site accurately before initiating the work
To accomplish the project within estimated time and assigned budget (as the work
is financed with bank loan therefore, the time mist not exceed the primary
estimation)
Scope and Time Management Plan_2

2SCOPE AND TIME MANAGEMENT PLAN
To accomplish the task faster than preliminary estimation by increasing the
duration for making it much faster
2. Project scope statement
The scope of the project is to accomplish construction of a Bunglow on strip footing
within assigned time and budget with best quality raw materials and architect for its interior and
exterior design. In order to avoid over allocation of resources, cost and budget the complete
project is subdivided into four different segments such as design, site preparation, building (to
lock up) and building (to hand over). Each of these work packages are required to be completed
within the assigned project budget and timeline. The design, site preparation, building (to lock up
and hand over) phases are needed to be completed respectively by project team engagement,
pour footing and mortgage inspections. Each of these aspects needs to be successfully followed
by the contractors, sub contractors, civil engineer and architects.
Scope and Time Management Plan_3

3SCOPE AND TIME MANAGEMENT PLAN
3. Work Breakdown Structure
Developig schedule for
the Bunglow project
Project preliminary phase
Design structure
Appointing project
manager
Modify changes
Conducting soil
testing
Receiving approval
from the clients
Drawing plan and
schedule
Attain engineer
certifications
Submitting plans to
the local council
Preparing and
submitting QBCC
applications
Selection of insurance
packages
Engage the project
management team
Site inspection phase
Erecting temporary
fencing
Installation of
portaloo to the site
Installation of
temporary power
pole
Installation of water
point
Cost estimation for
power and water
construction
Clear ground
Set out of the
dwelling
Dig foundations
Foundation of
inspection
Installation of trench
mesh
Pour footing
Project building (to lock
up) phase
Erect the double
brick external wall
system
Framing doors and
windows
Glazing
Installation of floor
joists
Erect internal timber
frame, floors and
walls
Install roof trusses
and battens
Installation roof rail
Ceiling joists
Fit T and G strip
flooring
Installation of
guttering
Fit roof tiles
Rough in electrical
Rough in plumbing
Project building
(handover) phase
Insulation installing
Plaster ceiling
Plaster walls
Crane lift shell into
place
Install and connect
swimming pool shell
or pump
Conducting second
fix (architraves and
fitting activities)
Tiles
Wall paining and
ceiling
Fit off electrical
points and
appliances
Fit off plumbing
points
Install downpipes
and connect to
storm water
Landscape the site
Connecting to sewer
connecting to water
supply
Connection to the
water supply
Connection to the
power supply
Clean site
Handover to client
Mortgage holder
inspections
Figure 1: Work Breakdown Structure for the Bunglow project
(Source: Created by Author)
Scope and Time Management Plan_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management: Bungalow Project
|10
|1468
|61

Construction and Installation Sequence for Building a Double Brickwall and Ground Slab
|4
|626
|292

Scope Management Plan for Bungalow Project
|13
|1841
|77

Project Management: Bungalow Project
|12
|1563
|215

Project Management: The Bungalow Project
|15
|2274
|100

Bungalow Construction Project Management
|15
|3189
|300