Running head: SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Smart Money Bank ABM Infrastructure Upgrade
Name of the Student
Name of the University
Author Note
Smart Money Bank ABM Infrastructure Upgrade
Name of the Student
Name of the University
Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Table of Contents
Scope Statement.........................................................................................................................2
Problem statement..................................................................................................................2
Description of the product:.....................................................................................................2
Objectives of the project........................................................................................................2
Assumptions...........................................................................................................................3
Constraints..............................................................................................................................4
Deliverable.............................................................................................................................4
Work Breakdown Structure........................................................................................................5
Plan.............................................................................................................................................5
Bibliography...............................................................................................................................6
Table of Contents
Scope Statement.........................................................................................................................2
Problem statement..................................................................................................................2
Description of the product:.....................................................................................................2
Objectives of the project........................................................................................................2
Assumptions...........................................................................................................................3
Constraints..............................................................................................................................4
Deliverable.............................................................................................................................4
Work Breakdown Structure........................................................................................................5
Plan.............................................................................................................................................5
Bibliography...............................................................................................................................6
2SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Scope Statement
It is defined as the type of statement which contains the deliverables of a project, this
statement is very much required to understand the objectives of a project. The success criteria
of a project can be understood in the first place using a scope statement. This statement is
written by the project manager before writing the statement of work. The entire life cycle of
the products can be understood using the scope statement as well.
Problem statement
There are downtime issues associated with the current core system of Smart Money
Bank; as a result, this banking organization is facing a huge challenge to retain their loyal
consumers. Thus, the existing system needs to be upgraded so that the net revenue of this
business starts increasing.
Description of the product:
The core system of Smart Money Bank shall be upgraded to the latest version of the
ABM software. The new system shall have new features both for the consumers and for the
employees working in the bank. The software can be very much useful to communicate the
service providers of this bank as well such as the external contractors.
Objectives of the project
The objectives of this project are as followings:
Improve the uptime of the ABMs throughout the bank’s network
Acquire new version of ABM software
Develop a schedule for a phased implementation of the project
Arrange for technical and user acceptance testing of the new software
Engage a focus customer focus group to assess the new features being offered
Scope Statement
It is defined as the type of statement which contains the deliverables of a project, this
statement is very much required to understand the objectives of a project. The success criteria
of a project can be understood in the first place using a scope statement. This statement is
written by the project manager before writing the statement of work. The entire life cycle of
the products can be understood using the scope statement as well.
Problem statement
There are downtime issues associated with the current core system of Smart Money
Bank; as a result, this banking organization is facing a huge challenge to retain their loyal
consumers. Thus, the existing system needs to be upgraded so that the net revenue of this
business starts increasing.
Description of the product:
The core system of Smart Money Bank shall be upgraded to the latest version of the
ABM software. The new system shall have new features both for the consumers and for the
employees working in the bank. The software can be very much useful to communicate the
service providers of this bank as well such as the external contractors.
Objectives of the project
The objectives of this project are as followings:
Improve the uptime of the ABMs throughout the bank’s network
Acquire new version of ABM software
Develop a schedule for a phased implementation of the project
Arrange for technical and user acceptance testing of the new software
Engage a focus customer focus group to assess the new features being offered
3SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
There are two categories of scope statement which usually considered by the project
managers, such as the in-scopee which includes all the inclusions of a project and out scope,
which shall include the exclusions of the project.
In-scope: Documentations shall be provided to the investors of this project who will
be funding the financial resource required in this project. The other inclusion of this project
shall be a user manual, as the new version of the software shall have numerous new features
which will be a little bit challenging for its new users. Each of these shall be there when the
project gets completed.
Out scope: On the other hand, there will be few exclusions as well in this project. The
main reason behind the presence of the out scope constraints related to this project which
shall be described in the following segment of this paper. Based on the total budget which is
allocated for this project, the two most significant thing which shall not be provided after the
successful completion of this project are is maintenance and training sessions. Training
sessions shall be requiring additional investments; hence it is considered in this category.
Maintenance cost of this project is very much dynamic and depends upon the local marketing
conditions of Trinidad.
Assumptions
There are numerous assumptions related to this project such as the availability of
resources required in the project. The new version of the software shall be running on the
ABM machines, it can be assumed that experienced designers, programmers, database
experts shall be easily obtained for this project with the cost which is allocated for the
external stakeholders of this project. The older version of the software will not be supported
by the vendors starting January 1, 2021. The other assumption of this project is that some
cross-section of the customers can play their role in the testing of the new product. It can also
There are two categories of scope statement which usually considered by the project
managers, such as the in-scopee which includes all the inclusions of a project and out scope,
which shall include the exclusions of the project.
In-scope: Documentations shall be provided to the investors of this project who will
be funding the financial resource required in this project. The other inclusion of this project
shall be a user manual, as the new version of the software shall have numerous new features
which will be a little bit challenging for its new users. Each of these shall be there when the
project gets completed.
Out scope: On the other hand, there will be few exclusions as well in this project. The
main reason behind the presence of the out scope constraints related to this project which
shall be described in the following segment of this paper. Based on the total budget which is
allocated for this project, the two most significant thing which shall not be provided after the
successful completion of this project are is maintenance and training sessions. Training
sessions shall be requiring additional investments; hence it is considered in this category.
Maintenance cost of this project is very much dynamic and depends upon the local marketing
conditions of Trinidad.
Assumptions
There are numerous assumptions related to this project such as the availability of
resources required in the project. The new version of the software shall be running on the
ABM machines, it can be assumed that experienced designers, programmers, database
experts shall be easily obtained for this project with the cost which is allocated for the
external stakeholders of this project. The older version of the software will not be supported
by the vendors starting January 1, 2021. The other assumption of this project is that some
cross-section of the customers can play their role in the testing of the new product. It can also
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
be assumed rat the local banks of Trinidad can authorize the credit card transactions using
web interface. The other assumption of this project is that the local populace can help to
reduce traffic within the tax offices.
Constraints
This software up-gradation projects shall have two constraints, each of them can have
a devastating effect on the successful completion of this project. One of these constraints is
the total budget related to this project which is US$450,000. Additional budget was required
to provide training sessions to the employees who are working in this business organization.
The maintenance of this project could have been conducted by the project if there was an
adequate financial resource. The other constraint related to this project is the limited time
which is there to conduct this project due to a limitation of the software, which is six months
and it has to be completed within 31st December. The availability of more time in the project
could have added new models and stages in the project to increase the success rate of the
project.
Deliverable
The deliverable of this project shall include the System Requirement Specification
sheet which will be showing the non-functional and functional requirements of the upgraded
software. The entire plan of the project, software and hardware required for the developers
and the programmers and the contracts of each external stakeholder working in this project
are the key deliverables of this project. The upgraded core system is the most significant
deliverable of this project which shall be provided after the completion of the project.
be assumed rat the local banks of Trinidad can authorize the credit card transactions using
web interface. The other assumption of this project is that the local populace can help to
reduce traffic within the tax offices.
Constraints
This software up-gradation projects shall have two constraints, each of them can have
a devastating effect on the successful completion of this project. One of these constraints is
the total budget related to this project which is US$450,000. Additional budget was required
to provide training sessions to the employees who are working in this business organization.
The maintenance of this project could have been conducted by the project if there was an
adequate financial resource. The other constraint related to this project is the limited time
which is there to conduct this project due to a limitation of the software, which is six months
and it has to be completed within 31st December. The availability of more time in the project
could have added new models and stages in the project to increase the success rate of the
project.
Deliverable
The deliverable of this project shall include the System Requirement Specification
sheet which will be showing the non-functional and functional requirements of the upgraded
software. The entire plan of the project, software and hardware required for the developers
and the programmers and the contracts of each external stakeholder working in this project
are the key deliverables of this project. The upgraded core system is the most significant
deliverable of this project which shall be provided after the completion of the project.
5SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Work Breakdown Structure
Figure 1: WBS
(Source: Created by author)
Plan
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
1 Upgradation of the core system
in Smart Money Bank
121 days Wed 7/15/20 Wed
12/30/20
$344,960.00
2 Phase 1: Requirement analysis
Data backup
21 days Wed 7/15/20 Wed 8/12/20 $36,160.00
3 Understanding the issues 5 days Wed 7/15/20 Tue 7/21/20 CIO of Smart Money Bank,Project manager$8,800.00
4 Documentation 5 days Wed 7/22/20 Tue 7/28/20 3 Project manager $4,800.00
5 Data backup 10 days Wed 7/29/20 Tue 8/11/20 4 Network manager,Project manager$21,600.00
6 Milestone 1 1 day Wed 8/12/20 Wed 8/12/20 5 Project manager $960.00
7 Phase 2: Resource
identification and plan
25 days Thu 8/13/20 Wed 9/16/20 $44,000.00
8 Identification of resources 5 days Thu 8/13/20 Wed 8/19/20 6 Project manager $4,800.00
9 Scheduling the activities of
the resource
10 days Thu 8/20/20 Wed 9/2/20 8 CIO of Smart
Money
Bank,Project
$29,600.00
10 Creation of the project plan 10 days Thu 9/3/20 Wed 9/16/20 9 Project manager $9,600.00
11 Milestone 2 0 days Wed 9/16/20 Wed 9/16/20 10 Project manager $0.00
12 Phase 3: Execution 30 days Thu 9/17/20 Wed 10/28/20 $72,000.00
13 Restructuring the core
system
5 days Thu 9/17/20 Wed 9/23/20 11 Designer,Developers $5,600.00
14 Designing 10 days Thu 9/24/20 Wed 10/7/20 13 Designer,Developers,Network manager$23,200.00
15 Upgradation procedure 10 days Thu 10/8/20 Wed 10/21/2014 Designer,Developers,Network manager,Server team,Software engineer$41,200.00
16 Update the organizational
database
5 days Thu 10/22/20 Wed
10/28/20
15 Designer $2,000.00
17 Milestone 3 0 days Wed 10/28/20 Wed 10/28/2016 Project manager $0.00
18 Phase 4: Testing 5 days Thu 10/29/20 Wed 11/4/20 $2,000.00
19 Black box testing 5 days Thu 10/29/20 Wed 11/4/20 17 Customers $2,000.00
20 Milestone 4 0 days Wed 11/4/20 Wed 11/4/20 19 Project manager $0.00
21 Phase 5: Implementation 40 days Thu 11/5/20 Wed 12/30/20 $190,800.00
22 Documentation after testing 5 days Thu 11/5/20 Wed 11/11/2020 Project manager $4,800.00
23 Quality check 5 days Thu 11/12/20 Wed 11/18/2022 CIO of Smart Money Bank,Network manager,Project manager,Customers$16,800.00
24 Implementation 30 days Thu 11/19/20 Wed 12/30/2023 Designer,Developers,Network manager,Project manager,Server team,Software engineer,Vendors$169,200.00
25 Milestone 5: Project closure 0 days Wed 12/30/20 Wed 12/30/2024 Project manager $0.00
CIO of Smart Money Bank,Project manager
Project manager
Network manager,Project manager
Project manager
Project manager
CIO of Smart Money Bank,Project ma
Project manager
9/16
Designer,De
Designer
T S W S T M F T S W S T M F
Jul 12, '20 Jul 26, '20 Aug 9, '20 Aug 23, '20 Sep 6, '20
Figure 2: Project plan
(Source: Created by author)
Work Breakdown Structure
Figure 1: WBS
(Source: Created by author)
Plan
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
1 Upgradation of the core system
in Smart Money Bank
121 days Wed 7/15/20 Wed
12/30/20
$344,960.00
2 Phase 1: Requirement analysis
Data backup
21 days Wed 7/15/20 Wed 8/12/20 $36,160.00
3 Understanding the issues 5 days Wed 7/15/20 Tue 7/21/20 CIO of Smart Money Bank,Project manager$8,800.00
4 Documentation 5 days Wed 7/22/20 Tue 7/28/20 3 Project manager $4,800.00
5 Data backup 10 days Wed 7/29/20 Tue 8/11/20 4 Network manager,Project manager$21,600.00
6 Milestone 1 1 day Wed 8/12/20 Wed 8/12/20 5 Project manager $960.00
7 Phase 2: Resource
identification and plan
25 days Thu 8/13/20 Wed 9/16/20 $44,000.00
8 Identification of resources 5 days Thu 8/13/20 Wed 8/19/20 6 Project manager $4,800.00
9 Scheduling the activities of
the resource
10 days Thu 8/20/20 Wed 9/2/20 8 CIO of Smart
Money
Bank,Project
$29,600.00
10 Creation of the project plan 10 days Thu 9/3/20 Wed 9/16/20 9 Project manager $9,600.00
11 Milestone 2 0 days Wed 9/16/20 Wed 9/16/20 10 Project manager $0.00
12 Phase 3: Execution 30 days Thu 9/17/20 Wed 10/28/20 $72,000.00
13 Restructuring the core
system
5 days Thu 9/17/20 Wed 9/23/20 11 Designer,Developers $5,600.00
14 Designing 10 days Thu 9/24/20 Wed 10/7/20 13 Designer,Developers,Network manager$23,200.00
15 Upgradation procedure 10 days Thu 10/8/20 Wed 10/21/2014 Designer,Developers,Network manager,Server team,Software engineer$41,200.00
16 Update the organizational
database
5 days Thu 10/22/20 Wed
10/28/20
15 Designer $2,000.00
17 Milestone 3 0 days Wed 10/28/20 Wed 10/28/2016 Project manager $0.00
18 Phase 4: Testing 5 days Thu 10/29/20 Wed 11/4/20 $2,000.00
19 Black box testing 5 days Thu 10/29/20 Wed 11/4/20 17 Customers $2,000.00
20 Milestone 4 0 days Wed 11/4/20 Wed 11/4/20 19 Project manager $0.00
21 Phase 5: Implementation 40 days Thu 11/5/20 Wed 12/30/20 $190,800.00
22 Documentation after testing 5 days Thu 11/5/20 Wed 11/11/2020 Project manager $4,800.00
23 Quality check 5 days Thu 11/12/20 Wed 11/18/2022 CIO of Smart Money Bank,Network manager,Project manager,Customers$16,800.00
24 Implementation 30 days Thu 11/19/20 Wed 12/30/2023 Designer,Developers,Network manager,Project manager,Server team,Software engineer,Vendors$169,200.00
25 Milestone 5: Project closure 0 days Wed 12/30/20 Wed 12/30/2024 Project manager $0.00
CIO of Smart Money Bank,Project manager
Project manager
Network manager,Project manager
Project manager
Project manager
CIO of Smart Money Bank,Project ma
Project manager
9/16
Designer,De
Designer
T S W S T M F T S W S T M F
Jul 12, '20 Jul 26, '20 Aug 9, '20 Aug 23, '20 Sep 6, '20
Figure 2: Project plan
(Source: Created by author)
6SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Bibliography
Ali, N. and Lai, R., 2018. Requirements Engineering in Global Software Development: A
Survey Study from the Perspectives of Stakeholders. JSW, 13(10), pp.520-532.
Buffardi, K., Robb, C. and Rahn, D., 2017. Tech startups: realistic software engineering
projects with interdisciplinary collaboration. Journal of Computing Sciences in Colleges,
32(4), pp.93-98.
Hujainah, F., Bakar, R.B.A., Abdulgabber, M.A. and Zamli, K.Z., 2018. Software
requirements prioritisation: a systematic literature review on significance, stakeholders,
techniques and challenges. IEEE Access, 6, pp.71497-71523.
Kamalirad, S., Kermanshachi, S., Shane, J. and Anderson, S., 2017, May. Assessment of
construction projects’ impact on internal communication of primary stakeholders in complex
projects. In Proceedings for the 6th CSCE International Construction Specialty Conference.
Palma, F.E., Fantinato, M., Rafferty, L. and Hung, P.C., 2019. Managing Scope, Stakeholders
and Human Resources in Cyber-Physical System Development.
Pheng, L.S., 2018. Project Scope Management. In Project Management for the Built
Environment (pp. 63-77). Springer, Singapore.
Scandaroli, A., Leite, R., Kiosia, A.H. and Coelho, S.A., 2019, May. Behavior-driven
development as an approach to improve software quality and communication across remote
business stakeholders, developers and QA: two case studies. In 2019 ACM/IEEE 14th
International Conference on Global Software Engineering (ICGSE) (pp. 105-110). IEEE.
Simeone, O., 2018. Problem statement. IEEE SIgnal ProcESSIng MagazInE, 1053(5888/18).
Sritharan, S., 2019. Problem Statement. The Bridge, 515, pp.294-8103.
Bibliography
Ali, N. and Lai, R., 2018. Requirements Engineering in Global Software Development: A
Survey Study from the Perspectives of Stakeholders. JSW, 13(10), pp.520-532.
Buffardi, K., Robb, C. and Rahn, D., 2017. Tech startups: realistic software engineering
projects with interdisciplinary collaboration. Journal of Computing Sciences in Colleges,
32(4), pp.93-98.
Hujainah, F., Bakar, R.B.A., Abdulgabber, M.A. and Zamli, K.Z., 2018. Software
requirements prioritisation: a systematic literature review on significance, stakeholders,
techniques and challenges. IEEE Access, 6, pp.71497-71523.
Kamalirad, S., Kermanshachi, S., Shane, J. and Anderson, S., 2017, May. Assessment of
construction projects’ impact on internal communication of primary stakeholders in complex
projects. In Proceedings for the 6th CSCE International Construction Specialty Conference.
Palma, F.E., Fantinato, M., Rafferty, L. and Hung, P.C., 2019. Managing Scope, Stakeholders
and Human Resources in Cyber-Physical System Development.
Pheng, L.S., 2018. Project Scope Management. In Project Management for the Built
Environment (pp. 63-77). Springer, Singapore.
Scandaroli, A., Leite, R., Kiosia, A.H. and Coelho, S.A., 2019, May. Behavior-driven
development as an approach to improve software quality and communication across remote
business stakeholders, developers and QA: two case studies. In 2019 ACM/IEEE 14th
International Conference on Global Software Engineering (ICGSE) (pp. 105-110). IEEE.
Simeone, O., 2018. Problem statement. IEEE SIgnal ProcESSIng MagazInE, 1053(5888/18).
Sritharan, S., 2019. Problem Statement. The Bridge, 515, pp.294-8103.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7SMART MONEY BANK ABM INFRASTRUCTURE UPGRADE
Tipi, L. and Matthias, O., 2019. Towards A Framework For Categorisation Of Project
Stakeholders.
Tipi, L. and Matthias, O., 2019. Towards A Framework For Categorisation Of Project
Stakeholders.
1 out of 8
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.