TASK 2.3. STATUS REPORT. Project Status Summary. Percen
Verified
Added on  2023/04/20
|3
|448
|92
AI Summary
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
TASK 2.3STATUS REPORT Project Status SummaryPercent Complete of total project: 87% The status date for the project status report is 4/30/19 and the work completed is 87% till date. All the major project works has been completed till date and only the closure phase is left for achievement. The Initialization Phase, Planning Phase, and Renovation Phase has been completed 100% and the closure phase is 46% for completion. The project status report would imply the formation of the innovative analysis of the project. Deliverables and Milestones DeliverableWBS #Planned Date Actual Date Status Letters1.31/28/191/28/19Completed Cost Estimation2.21/0/191/0/19Completed Renovation works3.02/1/192/1/19Completed Integration4.25/13/19-Yet to start MilestoneWBS #Planned Date Actual Date Status Project kick off1.41/31/191/31/19Completed Approval of the plan2.41/30/191/30/19Completed Completion of the renovation3.104/12/194/12/19Completed Closed4.35/20/19-Yet to start BSBPMG522_AT2_Task2.3_StatusReport
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Budget Status Budget Status Approved BudgetPlanned Expenditures to Date Actual Expenditures to Date Variance (planned – actual) $60000.00$55000.00$56000.00-$1000.00 Planned Remaining Budget Actual Remaining Budget Variance (planned – actual) $5000.00$4000.00$1000.00 Additional $ needed (if required)$1000.00 Work Completed During Last Period WBSTask Name% Complete 0Renovation of head office of Superior Implements (SIM Co.)87% 1Initialization Phase100% 1.1Analysis of the requirements100% 1.2Finalizing the works required in the Head Office100% 1.3Letter to sponsor for approval100% 1.4Project kick off100% 2Planning Phase100% 2.1Selection of Plan methodology100% 2.2Schedule development and Cost estimation100% 2.3Developing plan for the project100% 2.4Approval of the plan100% 3Renovation Phase100% 3.1Clearing of the Kitchen and Bathroom100% 3.2Fixing of the flooring100% 3.3Washing the house100% 3.4Bathroom Fixation100% 3.5Installing wash basin100% 3.6Painting the Head Office100% 3.7Installing new equipment100% 3.8Furniture fixation100% 3.9Change of drapes and curtains100% 3.10Completion of the renovation100% 4Closure46% 4.1Evaluation of the implementation60% BSBPMG522_AT2_Task2.3_StatusReport
Work Planned For Next Period WBSTask Name% Complete 4Closure46% 4.1Evaluation of the implementation60% 4.2Integration Management0% 4.3Closed0% Project Manager’s Name:____________________________________ Date:// 20 BSBPMG522_AT2_Task2.3_StatusReport