STATUS REPORT
PROJECT: Yes Chemist Pty Ltd
Date: 29th Sep, 2018.
Produced by: Project Manager
Reporting period: 28th May, 2019.
Project summary
Yes Chemist is the group of the independent Pharmacies which is expanding their
business in Australia. The company is provided health as well as beauty needs of
the customers related to the Pharmaceutical operations. The store is maintaining a
larger stock of the products at competitive prices. Due to operational weakness of
the company and lack of technical solutions, the business is required to improve its
Pharmaceutical operations. It is decided that they should replace its existing
accounting, inventory as well as HR management system by SAP S/4HANA for SAP
Business All-in-One. In order to strengthen its sales, services as well as marketing
modules, the company has implemented core on premise SAP Customer
Relationship Management (CRM) solution.
Completed tasks
WBS Task Name % Complete
1 Project Initiation Phase 100%
1.8 Milestone 1: Completion of project initiation phase 100%
2 Project Planning Phase 100%
2.5 Milestone 2: Completion of project planning phase 100%
3.14 Milestone 3: Server Installation Phase 100%
Project Status Report on Yes Chemist Pty Ltd_2
Budget Report
WBS Task Name Duration Start Finish Planned
cost Actual Cost
0
Implementation of SAP
system for Yes Chemist Pty
Ltd
404.25
days
Tue
7/25/17
Mon
2/11/19 $913,750.00 $645,800.00
1 Project Initiation Phase 20 days Tue
7/25/17
Mon
8/21/17 $44,640.00 $44,640.00
2 Project Planning Phase 11 days Tue
8/22/17
Tue
9/5/17 $25,680.00 $25,680.00
3 Server Installation Phase 225.25
days
Wed
9/6/17
Wed
7/18/18 $484,350.00 $484,350.00
4 System implementation
phase 115 days Wed
7/18/18
Wed
12/26/18 $254,800.00 $91,130.00
5 Project closure phase 33 days Wed
12/26/18
Mon
2/11/19 $104,280.00 $0.00
Pending tasks
WBS Task Name % Complete
4 System implementation phase 35%
4.6 Milestone 4: Completion of system implementation phase 0%
5 Project closure phase 0%
5.7 Milestone 5:completion of training and sign-off 0%
Risk and Issues
Type of risk Risk Details Mitigation strategy
Failure in case of
design the
business
processes for
fitting the software
It is difficult for Yes Chemist to change
its existing processes as well as
customize SAP system to fit with its
current processes.
The programmer, technical
coder as well as project
manager should design the
proposed system by
considering all the project
requirements and objectives.
There is proper server and
Project Status Report on Yes Chemist Pty Ltd_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BCO6656 - SAP Implementation for Yes Chemist Pty Ltd
|5
|1266
|45

Implementation of SAP System for Yes Chemist Pty Ltd. - Project Plan
|10
|1744
|91

Implementation of SAP for Yes Chemist Pty Ltd.
|4
|1195
|88

Yes Chemist Pty Ltd. - SAP Implementation Project Status Report
|9
|2417
|82

Information Technology Project Management: Project Status Report
|11
|1493
|422

SAP Implementation for Yes Chemist Pty Ltd - Status Report
|7
|1549
|455