Uninterrupted Power
Supply (UPS) Frame
Work
PROJECT MANAGEMENT CAPSTONE C
(PROJ6016)
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Overview of the Organisation
The assignment represents identification as well as
planning for procurement of the Uninterrupted Power
Supply system.
Company chosen is As-Sabuur Nigeria Limited.
The objective is to install generators in organisations and
various houses.
Document Page
Overview of the Organisation
Houses in Nigeria face numerous issues in relation to
power outages.
Project plan is designed by the project manager.
Installation of generator systems in houses would prove
highly beneficial because the organization would be able
to get more financial returns.
It would allow the company to pay the labours with their
desired wages.
Document Page
Identification of a Problem and
Suggested Solutions
Chosen place does not cover under 24 hours electric
supply range.
The place faced issues due to various power outages.
People face numerous issues in their regular work.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Identification of a Problem and
Suggested Solutions
Help them in installing the two units of generator sets in
the house.
Viable solution would be helpful for the house owner in
solving the issues.
Nigeria Limited to help them in installing the generators
Document Page
Identification of a Problem and
Suggested Solutions
Stakeholders within the project are the project manager,
house owner, and site project lead.
Project manager designs the project schedule.
Design the plan for installing work on the generator,
prepare a financial plan.
Document Page
Project Plan and Budget
Incur various processes that would be important for the
success of the project.
The project would need the project manager who is responsible
for knowing the requirements.
The project will be initiated by performing a particular
negotiation work
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Plan and Budget
Signing of documents by both parties will provide an
assurance that would be initiated by the project.
After that the procurement of the generators would be
done.
After the installation phase is done, monitoring as well as
control is done.
Document Page
The Gantt chart of the Project
(Fig 1: The Gantt chart for the Project)
(Source: Created by author)
Document Page
The Work Breakdown Structure
Uninterrupted Power Supply
(UPS) Frame Work
Start of Project Initiation of Project Design
Negotiation with the client
Signing of document
Procurement of generator
and accessories
Installation of cables
Completion of the Initiation
phase
Planning for the
Installation
Procurement of 2
generators
Planning design for
installation
Test running of generators
Completion of planning
phase
Executing the project
Installation of Generators
Test running of generators
Completion of installation
phase
Monitoring and Controlling
Cost Variance
Schedule Variance
Scope Variance
Completion of phase
Project Closing
Payment to contractors
Payment to staffs
Project records into OPA's
Signing off of project
Lessons learnt in to OPA's
Completion of Project
Closure phase
End Project
(Fig 2: The WBS for the Project)
(Source: Created by author)
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The Milestones of the Project
1. Completion of Initiation Phase of Project
2. Completion of planning phase of project
3. Completion of execution phase of project
4. Completing the monitoring and controlling of
installation of generator.
5. Completion of project closure phase.
Document Page
The Budget of the Project
Initiation of Project Design 19600
Planning for the Installation 4720
Executing the project 7200
Monitoring and Controlling 4800
Project Closing 3200
Total Cost for the project 39520
Total Cost for the project
(Fig 2: The Budget for the
Project)
Document Page
The Risks and Mitigation
Documents might not be prepared within the needed time.
There might be some defects detected after installation.
The plan must be designed within exact time.
Generator must be tested before it is installed.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Current Skills to be tested
Strong form of mechanical and electrical aptitude skills.
Good form of leadership and communication skills.
Project manager must be able to carry out duties along
with a sense of urgency.
Ability to work in a paced and dynamic environment
Document Page
Current Skills to be tested
Technical knowledge on diesel engine, electric power
generation, distribution of power which has the sets of
engine generation, installation, assembly, repair,
commissioning, system integration design, paralleling,
operation, transfer and switch gear switches.
One more part of the knowledge that would be required is
based on fuel systems, enclosures, exhaust systems and
ancillary equipment.
Document Page
Current Skills to be tested
Project manager must have the ability to interpret various
forms of instructions.
Understand specifications that would include blueprints.
Negotiation skills and organizational skills would be
highly needed
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Bibliography
Bukhari, S. S. H., Lipo, T. A., & Kwon, B. I. (2017). An online UPS system that eliminates the inrush current
phenomenon while feeding multiple load transformers. IEEE Transactions on Industry Applications, 53(2),
1149-1156.
Gironès, V. C., Moret, S., Maréchal, F., & Favrat, D. (2015). Strategic energy planning for large-scale energy
systems: A modelling framework to aid decision-making. Energy, 90, 173-186.
Larsen, E. R., Osorio, S., & van Ackere, A. (2017). A framework to evaluate security of supply in the
electricity sector. Renewable and Sustainable Energy Reviews, 79, 646-655.
Oluoti, K., Megwai, G., Pettersson, A., & Richards, T. (2014). Nigerian wood waste: A dependable and
renewable fuel option for power production. World Journal of Engineering and Technology, 2, 234-248.
Puka, L., & Szulecki, K. (2014). The politics and economics of cross-border electricity infrastructure: A
framework for analysis. Energy Research & Social Science, 4, 124-134.
Saponara, S., Fanucci, L., Bernardo, F., & Falciani, A. (2016). Predictive diagnosis of high-power
transformer faults by networking vibration measuring nodes with integrated signal processing. IEEE
Transactions on Instrumentation and Measurement, 65(8), 1749-1760.
Document Page
chevron_up_icon
1 out of 18
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]