VUIS CONSULTING PTY LTD. PROJECT PLAN [V1.1.1] [Implementation of SAP System for Yes Chemist Pty Ltd] [28thMay, 2019] [INSERT AUTHOR NAME HERE] [INSERT AUTHOR JOB TITLE HERE] [INSERT AUTHOR EMAIL HERE] The following template is for educational purposes only.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
CONTENTS Glossary.............................................................................................................................3 Introduction.........................................................................................................................4 Project scope......................................................................................................................4 Business case.....................................................................................................................5 Project Schedule and Approach (Rollout strategy)..............................................................7 Resources..........................................................................................................................8 Budget................................................................................................................................9 Risk...................................................................................................................................10 Communication.................................................................................................................11 Summary..........................................................................................................................12 Bibliography......................................................................................................................13 VUIS Consulting Project PlanPage2 [Insert Author name here]
Glossary TermDefinition SAPSystems Application and Products in Data Processing SDLCSystem Development Life Cycle VUIS Consulting Project PlanPage3 [Insert Author name here]
Introduction The project plan is being accessible with a point to detail the necessities of the project client “Yes Chemist Pty Ltd”. The task is based on implementation of SAP for the client organization so that they can control and monitor over providing healthy as well as beauty requirements of the customers based on their pharmaceutical operations. The project plan is included schedule of the project, budget plan, resources, communication as well as risks which are identified at the instance of implementation of SAP system. In order to develop the development plan, certain project statements are taken from the plan charter. The plan schedule, extent as well as project cost are making changes which are considered over the project implementation plan. Project scope The aim of this project plan is based on improving the business operations of the customer organization Yes Chemist Pty Ltd. The objectives of this project are: To provide with technical solutions by implementing SAP S/4HANA Business All-in- one To provide with core on principle SAP Customer Relationship Management (CRM) To ensure that there is ease of implementation as well as maintenance To ensure that all interfaces are being robust plus secured To follow SAP recommendations for the accomplishment of the system The major project deliverables and quality standards for the project are listed below: Project Deliverables i. Installation of the hardware for SAP system implementation Destruction of existing server room Reconstruction of the server room ii. Installation of the software for SAP system implementation Getting license free for around 300 users Setting of SDLC environment for cloud hosting Installation of SAP S/4HANA Business All-in-one Project quality standards i. System requirements Identifying the functional needs of the designing of SAP system Identifying the non-functional necessities of the designing of SAP system ii. Data conversion Understanding legacy data structure VUIS Consulting Project PlanPage4 [Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Placing the information extractor script expansion Post analysis of information migration as well as manual rectification of information Metrics techniques Evaluate the project status Foreseeing the plan risks Assess the productivity of the plan team Check quality of the work Business case Yes Chemist is the autonomous pharmacies with its stores are extended within various stores of Australia. The head workplace of the business is in Southern Melbourne, Victoria. The stores are ensured that through their services, their customers can get caring experienced at the time of shopping and they can maintain a larger stock of their products. The company is determined to restore its accessible accounting along with inventory management system with SAP system. The settlement of SAP system implementation in Yes Chemist are: a.Keeping the pharmaceutical data safe as well as regulated with protection b.Elimination of redundant processes along with tasks throughout automation c.Automating the pharmaceutical operations of the company d.All the data of the customers as well as financial data are housed into one location e.Faster as well as accurate access to the information of the customers and history of the customers f.Centralized data will able to bolster the collaboration among the client organization and customers DeliverablesSystem implementation of application modules for SAP system Development of business process for optimization of system functionality Conducting acceptance testing of system upgradation On-going training program of new system users Benefits and benefit realization Support the growth of the pharmaceutical businesses Adoption of best project management practices Elimination of duplication of the data entry Capturing of business transactions within one location Review the inventory and customer’s activities VUIS Consulting Project PlanPage5 [Insert Author name here]
Standardization of the materials code Reduction of the operating cost MeasuresAlignment of the customer’s expectations with the identified project scope Empowering the organization to make project related decisions Accurate plus timely data migration Apart from the benefits, there are some dis-benefits of the implementation of SAP system into the business organization such as: Higher cost of the purchasing as well as implementing the program Complexity to built the software for SAP system implementation VUIS Consulting Project PlanPage6 [Insert Author name here]
VUIS Consulting Project PlanPage7 [Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Schedule and Approach (Rollout strategy) Figure 1: Gantt chart (Source: Created by author) From the above Gantt chart, it is shown that the total duration of the project plan is 109 days. Following table shows the total project phases with its respective start and end date. Task NameDurationStartFinish SAP System Implementation in Yes Chemist109.25 daysTue 7/25/17Mon 12/25/17 Initiation Phase34 daysTue 7/25/17Fri 9/8/17 Planning phase100.25 daysMon 8/7/17Mon 12/25/17 Server installation phase72 daysMon 8/7/17Tue 11/14/17 System installation phase50 daysTue 10/3/17Tue 12/12/17 Implementation Phase49 daysTue 10/17/17Mon 12/25/17 Integration and testing phase13 daysMon 10/30/17Thu 11/16/17 Closure phase34 daysWed 11/1/17Tue 12/19/17 Resources Responsibilities Project Manager Project Sponsor Administrat ive Staff Programme rs Testers Business Analyst Technical Support Technical Writer End user trainers Resource planningRICIII--- Organizing of the project teamRARCI---- Estimation of the project cost and budget development RAIIII--- Analyze and manage the project risks ARAAI---- Monitor the project progressRAACIII__ Collect fund for the projectRRARAAI-- Ensure the project risks are managed ARCIACIII VUIS Consulting Project PlanPage8 [Insert Author name here]
Hardware and software installation RARRCIRRI Approve the key project deliverables IIIIARCIA Manage and distribute information in office RIAICII-- Create and maintain file systems RAIIIRRRR Schedule appointmentsRAIIRR--- Test the systemRAIRIRRII Analyze the business requirements AIIIRAIII Determine the technical requirements of the system IIIIARCIA Write the technical codesIRAIIICRA Providing training to the usersAIIIAIIIR Budget NameCost Initiation Phase$24,600.00 Planning phase$181,000.00 Server installation phase$58,470.00 System installation phase$97,600.00 Implementation Phase$87,720.00 Integration and testing phase $40,040.00 Closure phase$66,000.00 Risk Type of riskRisk detailsLikelihoodImpactRisk level Mitigation strategies Unclear projectThe project goals behindUnlikelyModerateMediumThe project charter VUIS Consulting Project PlanPage9 [Insert Author name here]
goals and objectives implementation of SAP system implementation is not properly mentioned in the development charter. should require mentioning a defined project objectives as well as goals. Ineffective communication There is no proper communication among the project manager as well as project team associates to discuss the project progress. ModerateModerateMediumA communication plan is required in this case so that there should be proper interaction as well as communication among the project team members. Insufficient training among end users The employees have lack of technical skills to handle the system, and in this case training is not provided to them. LikelyMajorHighTraining program is required in this case so that all the employees can conduct their system implementation work. Poor integration of the SAP system SAP system implementation is not integrated based on the project requirements. ModerateModerateMediumThere is required to implement the SAP system based on the functional requirements of the system. Ineffective project cost The cost of the project is not estimated properly, therefore there is high risk of project failures. ModerateModerateMediumCost management plan is required to be prepared by adding all project expenses and resources. Communication Communication type Purpose of communication AudiencesFrequencyMethod of communication Responsible person Project charterDefining the project scope and project approach Project Team Members At the project initiation phase Presentation and Email Project Manager Project status meetings Tracking the progress of the development plan, formulate the decisions when needed Project Team Members MonthlyPresentation, Memos and Face-to-face meetings Project Manager VUIS Consulting Project PlanPage10 [Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Issue log and documentation Maintain as well as update status of the development issues Project Team Members WeeklyFace-to-face meetings Project Manager Change requestsTrack the project changes affect scope and budget Project Team Members WeeklyPresentation and Email Project Manager Project decision requests Tracking the project issues which provide impact on project completion date Project Team Members WeeklyFace-to-face meetings Project Manager Sponsorship communications Scope as well as goals of the development stakeholders Project Team Members WeeklyFace-to-face meetings Project Manager VUIS Consulting Project PlanPage11 [Insert Author name here]
Summary It is concluded that YesChemist can maintain a larger stock their medical products at a price so that they can make a competitive advantage. Due to implementation of SAP into the business organization ofYesChemist, it can make improvement into the business productivity, increase into the business efficiencies as well as decrease into the operational cost. It is found that theYesChemist can streamline their business processes. VUIS Consulting Project PlanPage12 [Insert Author name here]
Bibliography Binder, J., 2016.Global project management: communication, collaboration and management across borders. Routledge. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Heagney, J., 2016.Fundamentals of project management. Amacom. Heldman, K., 2018.PMP: project management professional exam study guide. John Wiley & Sons. Heldman, K., 2018.Project management jumpstart. John Wiley & Sons. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kerzner, H., 2018.Project management best practices: Achieving global excellence. John Wiley & Sons. Kerzner, H., 2019.Using the project management maturity model: strategic planning for project management. Wiley. Larson, E.W. and Gray, C.F., 2017.Project management: The managerial process. McGraw-Hill Education. Milosevic, D.Z. and Martinelli, R.J., 2016.Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons. Turner, R., 2016.Gower handbook of project management. Routledge. Verzuh, E., 2015.The fast forward MBA in project management. John Wiley & Sons. VUIS Consulting Project PlanPage13 [Insert Author name here]