VUIS CONSULTING PTY LTD. PROJECT PLAN [version: 1] [Implementation of SAP in Yes Chemist Pty Ltd] [INSERT DATE HERE] [INSERT AUTHOR NAME HERE] [INSERT AUTHOR JOB TITLE HERE] [INSERT AUTHOR EMAIL HERE] The following template is for educational purposes only.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
CONTENTS Table of Contents Glossary.............................................................................................................................3 Introduction.........................................................................................................................4 Project scope......................................................................................................................4 Business case.....................................................................................................................6 Project Schedule and Approach (Rollout strategy)..............................................................7 Resources........................................................................................................................11 Budget..............................................................................................................................12 Risk...................................................................................................................................15 Communication.................................................................................................................16 Summary..........................................................................................................................17 References.......................................................................................................................18 VUIS Consulting Project PlanPage2 [Insert Author name here]
Glossary TermDefinition Business Case Proper reasoning for project start and execution Project Management The process of identifying the major project goals, scope and schedule ScopeIt is a part of project planning that involves goals, deliverables and features VUIS Consulting Project PlanPage3 [Insert Author name here]
Introduction A project plan is to be prepared for yes chemist that manages a group of independent Pharmacies with a shared value and common philosophy. The business of yes Chemist Pty Ltd had started as a family venture in late 2010s, which has gradually expanded stores in all the major cities of Australia, which includes Sydney, Brisbane Adelaide, Perth and Melbourne. The business of Yes Chemist has been doing well for quite a sometime and therefore, the organization has decided to implement SAP for integrating all the major business operations of the organization. The need of a new accounting, HR and inventory management system is essential as an operational review that was conducted resulted unveiled the weaknesses in the existing system (Schwalbe 2015). The Victoria University Information Systems Consulting mainly secured the contract for implementing the SA S/4HANA for SAP Business All in one. The main purpose of this project plan is to define the scope of the project including the major project deliverables associated with the project and project quality standards. The quality standards requirement for the project will be discussed as well (Leach 2014). The project Plan outlines the business case for the project that justifies the need of the project. The project schedule and the approach of implementing the project are discussed in the project plan. The project plan further covers the resources, budget and risks associated with a project. A communication matrix is also prepared that includes different communication activities associated with the project. This project plan is prepared to get an overview of the different project activities, schedule and the deliverables. Project scope The aim of the project is to implement SAP S/4HANA for SAP Business All in one for Yes chemist Pvt Ltd. The system development life cycle of the project mainly consists of the development, testing and the user acceptance testing as well. The system will be set up on cloud considering the fact that server room refurbishment will take almost three months to complete (Kerzner and Kerzner 2017). The project would be a success only if the hardware and the software installation are complete. The data conversion, which is an important project deliverable should be completed successfully. With the implementation of a new system, it is very essential to train the existing users of the organization about the use of the software in the organization (Harrison and Lock 2017). This process is followed by the user acceptance testing. The objective of the project is to deliver the identified deliverables of the project on time. The project will be a success only if the major deliverables of the project manages to achieve the desired quality standards for the project. The deliverables and the quality standards required for the acceptance of each deliverables is represented in the following table (Burke 2013). DeliverablesAcceptance Criteria of Quality Standards Development of Infrastructure and EquipmentThe work should be completed within 15 days as quoted by the contractor started from 3rdof June Collection of the functional requirements of theThe requirement fetching should incorporate the VUIS Consulting Project PlanPage4 [Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
new system design associated with the projectall the functional requirements of the project. Data Conversion is another major deliverable of the project. Since the company is integrating all their business processes in a new SAP instance, data extraction, conversion, validation and transitioning is essential. This data conversion will take at least 3 weeks. The acceptance criteria of this deliverable will be conversion of data according to legacy data structure and proper identification and rectification of the defect in data conversion (if any). Integration and Testing- Integration and testing is one of the most important deliverables of the project as the success of the project largely depends on the proper integration of the new SAP system will the e-gate feature for corporate banking associated with the organization. The deliverable will be accepted only after a comprehensive end to end testing within All in one finance module. This should incorporate testing with a live e ate instance and postings in journal ledger. Documentation of the project workThis deliverable will only be accepted if the documentation process is completed by a technical writer of VUISC. The documentation process should include review standard SAO business All in one end user manuals. Training the usersSince VUISC is implementing the project, it is essential that the training is imparted by VUISC trainer only as this trainer will have a proper knowledge about the working process of the software. MaintenanceThe acceptance criterion is that a regular maintenance is ensured. The assumptions are- 1. A realistic schedule is set 2. The budget allocation is appropriate The Constrains are as follows- 1. Maintenance does not include disaster or data recovery and it is the responsibility of the client. 2. The budget may not incorporate hike in the wages of the workers. Business case The business needs that the project is expected to address (Heagney 2016)- 1. The Sap system will provide a solution to replace the legacy accounting, HR and inventory management system. 2. The new SAP system is expected to mitigate the operational weaknesses associated with Yes Chemist. VUIS Consulting Project PlanPage5 [Insert Author name here]
3. The process of data storage will be automated that will help in easier data extraction The project is justified as with the increase in the business units of Yes Chemist, it is essential to upgrade the existing system to make the process of information storage and retrieval easier. The expected benefits of the project is represented in the following table- BenefitsBenefit Measures Significant Cost savingsThe SAP software is capable of tracking the company’s data and generates the reports thus reducing the need of human labor. Consistent OperationsThe progress report shows consistent improvement management of the operation Flexibility in designing the processWith the use of Sap, the employees of the organization are able to design the business processes in an innovative manner Customizing the solution to suit the business process of Yes Chemist Customization of the business process becomes easier Reduction in sales and order processing costThe regular progress reports showing reduction in order processing cost. Reduced the order delivery timeCustomers are getting faster delivery. However, there are certain dis –benefit of the new system, which are as follows- 1. In the initial months after the implementation of the project, the productivity might reduce as the employees will need time to understand the working principle of the new system. 2. The initial cost of development and installation is huge 3. The hardware design flow of SAP Hana follows a very specific guideline and therefore, it is essential to train the employees in a proper way. 4. Point in time recovery feature is absent in SAP HANA. Project Schedule and Approach (Rollout strategy) The project will include a number of phases. At first, it is very essential to do a proper research on the feasibility of the project. The project will include the different phases of project management which are requirement analysis, implementation, testing and maintenance. The details about the different phases of the project and the time allocated for each phase is represented in the following table- Task NameDurationStartFinish VUIS Consulting Project PlanPage6 [Insert Author name here]
SAP Implementation Project in Yes Chemist251 days Fri 01- 06-18 Fri 17- 05-19 Project starts1 dayFri 01-06- 18 Fri 01-06- 18 Feasibility Study8 daysMon 04- 06-18 Wed 13- 06-18 Operational Feasibility5 daysMon 04- 06-18 Fri 08-06- 18 Technical Feasibility6 daysMon 04- 06-18 Mon 11- 06-18 Documenting the report1 dayTue 12- 06-18 Tue 12-06- 18 Drafting the report1 dayWed 13- 06-18 Wed 13- 06-18 Requirement Analysis14 daysMon 04- 06-18 Thu 21- 06-18 Understanding the resource requirements5 daysMon 04- 06-18 Fri 08-06- 18 Preparation of the project plan3 daysMon 11- 06-18 Wed 13- 06-18 Obtaining Functional Requirements4 daysMon 11- 06-18 Thu 14-06- 18 M1: Collection of the functional requirements of the new system design associated with the project0 daysThu 14- 06-18 Thu 14-06- 18 Preparation of project schedule3 daysFri 15-06- 18 Tue 19-06- 18 Documenting the reports2 daysWed 20- 06-18 Thu 21-06- 18 Implementation102 daysMon 04- 06-18 Tue 23- 10-18 Server room demolition15 daysMon 04- 06-18 Fri 22-06- 18 Permission for cloud hosting10 daysMon 25- 06-18 Fri 06-07- 18 M2: Development of Infrastructure and Equipment0 daysFri 06-07- 18 Fri 06-07- 18 Designing the interface15 daysMon 09- 07-18 Fri 27-07- 18 Coding the software30 daysMon 30- 07-18 Fri 07-09- 18 Coding database30 daysMon 10- 09-18 Fri 19-10- 18 linking the data base with the software2 daysMon 22- 10-18 Tue 23-10- 18 connection of new servers with the existing network10 hrsMon 25- 06-18 Tue 26-06- 18 Data Conversion22 daysWed 24- 10-18 Thu 22- 11-18 Understanding the legacy of data structures3 daysWed 24- 10-18 Fri 26-10- 18 VUIS Consulting Project PlanPage7 [Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Setting up the data extractor and script development2 daysMon 29- 10-18 Tue 30-10- 18 Data validation and cleansing3 daysWed 31- 10-18 Fri 02-11- 18 Development of the automated script for loading data into B1 instance2 daysMon 05- 11-18 Tue 06-11- 18 Testing in real time instance3 daysWed 07- 11-18 Fri 09-11- 18 Defect rectification2 daysMon 12- 11-18 Tue 13-11- 18 Post data migration analysis4 daysWed 14- 11-18 Mon 19- 11-18 Manual data rectification by client3 daysTue 20- 11-18 Thu 22-11- 18 M3: Successful Data Conversion0 daysThu 22- 11-18 Thu 22-11- 18 Integration and Testing35 daysFri 23-11- 18 Thu 10- 01-19 Integration of new SAP system with e-gate feature for corporate banking5 daysFri 23-11- 18 Thu 29-11- 18 Testing30 daysFri 30-11- 18 Thu 10- 01-19 unit testing5 daysFri 30-11- 18 Thu 06-12- 18 system testing6 daysFri 07-12- 18 Fri 14-12- 18 black box testing5 daysFri 07-12- 18 Thu 13-12- 18 alpha testing5 daysFri 14-12- 18 Thu 20-12- 18 end to end testing with live e-gate instance10 daysFri 21-12- 18 Thu 03-01- 19 System integration Testing5 daysFri 04-01- 19 Thu 10-01- 19 M4: Completion of Integration and testing of SAP0 daysThu 10- 01-19 Thu 10-01- 19 Documentation and training61 daysFri 04-01- 19 Fri 29-03- 19 Documenting the project progress and project reports7 daysFri 04-01- 19 Mon 14- 01-19 Development of functionality manuals10 daysFri 04-01- 19 Thu 17-01- 19 Reviewing the standard of SAP business All in one end user manuals20 daysFri 18-01- 19 Thu 14-02- 19 Customization of the manuals based on client's delivery requirements10 daysFri 15-02- 19 Thu 28-02- 19 Training by VUISC trainer to the staffs of Yes Chemist21 daysFri 01-03- 19 Fri 29-03- 19 M5: Completion of Documentation and training Phase0 daysFri 29-03- 19 Fri 29-03- 19 Acceptance Testing and Client Sign off15 daysMon 01-Fri 19-04- VUIS Consulting Project PlanPage8 [Insert Author name here]
04-1919 Performing acceptance testing on the application developed10 daysMon 01- 04-19 Fri 12-04- 19 Sign Off5 daysMon 15- 04-19 Fri 19-04- 19 Completion of hardware and software installation2 daysMon 15- 04-19 Tue 16-04- 19 Checking whether data conversion and training is successfully completed2 daysMon 15- 04-19 Tue 16-04- 19 Documenting the report5 daysMon 15- 04-19 Fri 19-04- 19 M6: Completion of Acceptance Testing and successful client sign off0 daysFri 19-04- 19 Fri 19-04- 19 Application go live20 daysMon 22- 04-19 Fri 17-05- 19 server equipments tested by VUISC technical staff before SAP installation2 daysMon 22- 04-19 Tue 23-04- 19 Installation by Frontline Engineer2 daysWed 24- 04-19 Thu 25-04- 19 go live1 dayFri 26-04- 19 Fri 26-04- 19 Maintenance post go live3 wksMon 29- 04-19 Fri 17-05- 19 Project Ends0 daysFri 17-05- 19 Fri 17-05- 19 The Gantt of the project is represented below- VUIS Consulting Project PlanPage9 [Insert Author name here]
VUIS Consulting Project PlanPage10 [Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Figure 1: Representing the Gantt chart of the shifting project (Source: Generated by Author using MS project) The work activities marked in red in the Gantt chart above depict the critical path of the project (Larson and Gray 2013) Resources The human resources associated with this project is represented below- Resource NameStd. RateCost/Use IT Project Manager VUISC$75.00/hr$0.00 VUISC Programmers$30.00/hr$0.00 VUISC Testers$35.00/hr$0.00 VUISC business Analyst$50.00/hr$0.00 VUISC Technical writers$30.00/hr$0.00 VUISC End user trainers$25.00/hr$0.00 Jacob and Sons Pty Ltd subcontracting staffs$0.00/hr$15,000.00 Peter Cables Pty Ltd$60.00/hr$0.00 Frontline Engineer$30.00/hr$0.00 VUISC technical staffs$20.00/hr$0.00 The resource report is represented below- VUIS Consulting Project PlanPage11 [Insert Author name here]
The above report gives an overview of the resources associated with the project and the responsibilities of each resource. Budget The cost estimated for the project is represented in the following table – WBSTask NameDurationCost 0SAP Implementation Project in Yes Chemist251 days$109,845.00 1Project starts1 day$600.00 2Feasibility Study8 days$7,000.00 2.1Operational Feasibility5 days$2,800.00 2.2Technical Feasibility6 days$3,360.00 2.3Documenting the report1 day$240.00 2.4Drafting the report1 day$600.00 3Requirement Analysis14 days$9,480.00 3.1Understanding the resource requirements5 days$3,000.00 3.2Preparation of the project plan3 days$1,800.00 3.3Obtaining Functional Requirements4 days$2,400.00 3.4M1: Collection of the functional requirements of the new0 days$0.00 VUIS Consulting Project PlanPage12 [Insert Author name here] RESOURCE OVERVIEW RESOURCE STATSWORK STATUS RESOURCE STATUS Work status for all work resources. Remaing work for all work resources. % work done by all the work resources.
system design associated with the project 3.5Preparation of project schedule3 days$1,800.00 3.6Documenting the reports2 days$480.00 4Implementation102 days$40,305.00 4.1Server room demolition15 days$15,000.00 4.2Permission for cloud hosting10 days$6,000.00 4.3M2: Development of Infrastructure and Equipment0 days$0.00 4.4Designing the interface15 days$3,600.00 4.5Coding the software30 days$7,200.00 4.6Coding database30 days$7,200.00 4.7linking the data base with the software2 days$480.00 4.8connection of new servers with the existing network10 hrs$825.00 5Data Conversion22 days$4,760.00 5.1Understanding the legacy of data structures3 days$480.00 5.2Setting up the data extractor and script development2 days$320.00 5.3Data validation and cleansing3 days$480.00 5.4Development of the automated script for loading data into B1 instance2 days$320.00 5.5Testing in real time instance3 days$1,320.00 5.6Defect rectification2 days$480.00 5.7Post data migration analysis4 days$640.00 5.8Manual data rectification by client3 days$720.00 6M3: Successful Data Conversion0 days$0.00 7Integration and Testing35 days$11,480.00 7.1Integration of new SAP system with e-gate feature for corporate banking5 days$800.00 7.2Testing30 days$10,680.00 7.2.1unit testing5 days$1,400.00 7.2.2system testing6 days$1,680.00 7.2.3black box testing5 days$1,400.00 7.2.4alpha testing5 days$1,400.00 7.2.5end to end testing with live e-gate instance10 days$2,800.00 7.2.6System integration Testing5 days$2,000.00 7.3M4: Completion of Integration and testing of SAP0 days$0.00 8Documentation and training61 days$18,620.00 8.1Documenting the project progress and project reports7 days$1,120.00 8.2Development of functionality manuals10 days$2,400.00 8.3Reviewing the standard of SAP business All in one end user manuals20 days$8,000.00 8.4Customization of the manuals based on client's delivery requirements10 days$2,400.00 8.5Training by VUISC trainer to the staffs of Yes Chemist21 days$4,700.00 9M5: Completion of Documentation and training Phase0 days$0.00 10Acceptance Testing and Client Sign off15 days$4,640.00 10.1Performing acceptance testing on the application developed10 days$2,800.00 10.2Sign Off5 days$1,840.00 VUIS Consulting Project PlanPage13 [Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10.2.1Completion of hardware and software installation2 days$320.00 10.2.2Checking whether data conversion and training is successfully completed2 days$320.00 10.2.3Documenting the report5 days$1,200.00 11M6: Completion of Acceptance Testing and successful client sign off0 days$0.00 12Application go live20 days$12,960.00 12.1server equipments tested by VUISC technical staff before SAP installation2 days$320.00 12.2Installation by Frontline Engineer2 days$480.00 12.3go live1 day$760.00 12.4Maintenance post go live3 wks$11,400.00 13Project Ends0 days$0.00 The following report gives an overview of the resource cost overview associated with the project- The cost of work is huge since the schedule of the project is long and the project work is quite complex. VUIS Consulting Project PlanPage14 [Insert Author name here] RESOURCE COST OVERVIEW COST STATUSCOST DISTRIBUTION COST DETAILS Cost status for work resources.How costs are spread out amongst different resource types. Cost details for all work resources.
Risk Every project is associated with a certain amount of risk that needs to be properly managed in order to eliminate the chances of project failure (McNeil, Frey and Embrechts 2015). A risk register is prepared for documenting the different risks that is associated with the SAP implementation project in Yes Chemist. A risk register is a master document that is created in the early stages of the project and is therefore an important part of Risk management plan (Alhawari, S., Karadsheh, Talet and Mansour 2012). A risk register helps in addressing the different risks and problems as they arise. The risks associated with the SAP implementation are as follows (Galliers and Leidner 2014) – S.NoSecurity Threat/Risk Description Likelihood Impact PriorityPreventive Actions 1.Any problem in data conversion and data transfer might result in the permanent data loss MediumHighHighAs a preventive action, the data conversion and transfer which is a significant project deliverable should be completed in a controlled environment 2.Technical risk in testing of the developed modules MediumHighHighAs a mitigation approach, the testing phase is allocated with a considerable times 3.Schedule risk due to delay in the resources availability LowMediumMediumAs a risk mitigation approach, the daily progress of the project is needed to be tracked 4.Operational Risk due to inexperienced employees HighHighHighThe training should be imparted to the maximum number of employees 5.The SAP system is not providing the expected output LowHighHighAs a risk mitigation approach, proper requirement analysis and research about SAP HANA is to be made prior to its implementation. 6.Project Experiencing frequent delays and slippage in deadline MediumMediumMediumThe project manager should have a clear visibility of the project progress and timely completion of the VUIS Consulting Project PlanPage15 [Insert Author name here]
deliverable. Communication Proper communication flow among the team members is essential in measuring the success of the project (Binder 2016). A communication matrix is a tool that is designed to get an overview on how an individual in communicating. The communication matrix for this project in represented in the following table (Martinelli and Milosevic 2016)- Communication activities Target Audience Description/PurposeFrequencyDistribution Vehicle Weekly status report Project TeamCommunicate updated project status Weeklyemail Project Progress Report Project Team along with project manager Communicate the project progress In every two weeksEmail, face to face communication Delivery or communication of key messages The project team Any recent development in the project needs to be communicated RegularlyPhone calls Impact assessment report Project team and stakeholders Communicating the impact assessment report Bi-weeklyEmail Updated schedule Project team members Communicating any update in schedule As requiredEmail Summary The project plan demonstrates the different phases and activities associated with the project of Yes Chemist. A SAP application will be implemented for integrating all the business processes associated with the organization. The project plan gives an overview of the project scope, business case, schedule, resources and budget, associated risks and the project communication plan. VUIS Consulting Project PlanPage16 [Insert Author name here]