Running head: PROJECT REPORT Project Report Wonboyn River Bridge Project Name of the Student: Student ID: Name of the University:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT REPORT Executive Summary The following assignment had been made on the concept of developing the planning the execution of the activities and aligning the significant management of the operations. The project of Wonboyn River Bridge had been developed for widening of the existing highway bridge over the river. The Welbilt Pty Ltd had been planning for forming the construction of the bridge and improving the travelling at the locations. The people had been able to improve their conveyance with the help of the increased area for travelling. The report would include the work breakdown structure construction of the project and identifying the probable construction of the highway bridge. The network diagram had been developed using Ms-Project software and the report had been developed on the proper management of the operations for the project.
2PROJECT REPORT Table of Contents Introduction......................................................................................................................................3 Reflective Comments on Team Performance..................................................................................3 Identification and description of project activities..........................................................................4 Network Diagram..........................................................................................................................11 Analysis of Network......................................................................................................................12 Comments on Relevance of work..................................................................................................12 Suitability of network....................................................................................................................14 Conclusion.....................................................................................................................................14 Bibliography..................................................................................................................................16
3PROJECT REPORT Introduction The specific project alignment would be effectively managed with the formation and deployment for the alignment and influence management (Kerzner and Kerzner 2017). The construction management includes the successful integration and implication and listing probable information management. The project plan development had been successfully implied with the continuation of the successful project execution. The management of the construction projects had been implied with the management of the probable information management for developing the construction project execution (Raj and Wadsamudrakar 2018). The improvement of the highway construction would be effectively managed with the consideration and utilization of the successive project plan development. The following assignment is effectively developed for considering the utilization of the effective implication management. The improved functional development can be implied with the consideration and utilization management. The improvement of the information analysis is implied with the consideration of the factors and alignment of the activities. The report is implied for taking care of the construction management and information development of activities of Wonboyn River Bridge Project. The discussion of the network diagram would include the probable identification of the work packages and forming proper project plan development. The narrative analysis of the team performance would be done for taking care of the information management for the construction project. Reflective Comments on Team Performance The reflective review of the project operations had been helpful for implying the management of the activities. I was the project manager with the responsibilities of managing
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT REPORT and executing the project operations. I had to make sure that the project work was divided to specific persons for executing the project activities. We were also responsible for analysing and planning the completion of the activities and listing the compact analysis of the project completion.Myteamcomprisedofexternalcontractorforresourceaccumulationand development of effective alignment model. The project team had the responsibility of developing successive completion of the project. Being a manager I was responsible for the completion of the projectactivities.The plannerwasinvolvedfor developingthe projectplanfor the completion of the effective project completion. The management of the successful project activities completion had been developed confiding the management of the operations. The implication of the factors of development was highly implied with the formation of the successive project completion and development management. The alignment model is implied with the continuation and deployment model for the utilization management. Identification and description of project activities The Wonboyn River Bridge Project had been developed for widening of the existing highway bridge over the river. The Welbilt Pty Ltd had been planning for forming the construction of the bridge and improving the travelling at the locations. The following is the list of project activities, WBSTask Name 0WONBOYN RIVER BRIDGE PROJECT 1Start, Administration 2Initial Site Establishment 2.1Initial Surveying
5PROJECT REPORT 2.2Site Clearance 2.3Signage and Protection 2.4Drainage system 2.5Security and guard outposts 2.6Site Office 2.7Staff Area/ Parking 2.8Site Induction 2.9Traffic Signage 2.10Accessing Roads 2.11Temporary Services 2.12Notify and receive Casting Steel (PSC) 2.13Construct Casting Bay 3Surveying 3.1Set out for Pre-existing bridge 3.2Set out for Pier Piles 3.3Set out for pier Piles 4Demolition 4.1Railing/End post Demolish 4.2Partially demolish deck/wing wall 5De watering/Drainage of creek 5.1Establish Site boundaries 5.2Embankment 5.3Place Sheet Pile to create Coffer Dam 5.4Drain water 6Manufacture PSC Planks
6PROJECT REPORT 6.1Order/Receive Steel Fibres 6.2Determine plank size/dimensions 6.3Place pre stressed fibres 6.4Pour Concrete 6.5Steam cure concrete, demold 7Excavation 7.1Excavate for Abutment Pile A 7.2Excavate for Abutment Pile B 7.3Excavate for Pier Pile A 7.4Excavate for Pier Pile B 8Construct Abutment Piles 8.1Establish Site 8.2Place Steel cases into soil and boring 8.3Place Steel Reinforcement 8.4Pour Concrete 8.5Remove Casing 8.6Cure Concrete 9Construct Pier Piles 9.1Place Steel cases into soil and boring 9.2Place Steel Reinforcement 9.3Pour Concrete 9.4Remove Casing 9.5Cure Concrete 10Construct Columns 10.1Place Steel Reinforcement
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT REPORT 10.2Put formwork in place 10.3Pour concrete 10.4Cure Concrete 10.5Remove Formwork 11Construct Headstock 11.1Place Steel Reinforcement 11.2Put formwork in place 11.3Pour concrete 11.4Cure Concrete 11.5Remove Formwork 12Construct Abutments 12.1Place order for Elastomeric strips 12.2Erect Scaffolding 12.3Formwork & Reinforcement 12.4Pour and Compact/Vibrate Concrete 12.5Cure Concrete 12.6Remove Formwork 12.7Install elastomeric bearings/ motor pads/ dowel Pedestals 13Place PSC 13.1Order Crane 13.2Move PSC planks to site 13.3Order Protection Angle 13.4Set out position 13.5Put PSC Planks in place 13.6Fix Protection Angle
8PROJECT REPORT 14Approaching Slab 14.1Set out Position 14.2Put Reinforcement in place 14.3Place formwork 14.4Pour concrete 14.5Cure and harden concrete 14.6Remove Formwork 15Parapet 15.1Core 15.2Put Dowel Reinforcement in place 15.3Epoxy Mortar (Fill Reo) 15.4Set out positions 15.5Put Reinforcement in place 15.6Place formwork 15.7Pour Concrete 15.8Cure/ Harden concrete 15.9Remove formwork 16Construct Main Deck 16.1Set Out Positions 16.2Put formwork in place for Scutter 16.3Pour Asphalt concrete 16.4Cure/ Harden Concrete 16.5Remove Formwork 17Wing walls 17.1Place reinforcement in place
9PROJECT REPORT 17.2Put formwork in place 17.3Pour concrete 17.4Cure/Harden Concrete 17.5Remove formwork 18Railings 18.1Place order for Barrier Railings 18.2Railing Set out 18.3Cast Posts 18.4Use Protective Coating 18.5Weld 18.6Construct Panels 19Site Closure 19.1Cleanup 19.2Remove site services, amenities, power… 20Project Completion Explanation of the project activities:The Wonboyn River Bridge Project is developed for constructing the bridge with a wider width and it would be implied with the management of the successful implementation model. The project is initialized with the operations of Start, Administration process where all the information collection is done. The first phase of the project includes initial site establishment comprising of the activities of initial surveying, site clearance, signage and protection, drainage system, security and guard outposts, site office, staff area/ parking, site induction, traffic signage, accessing roads, temporary services, notify and receive casting steel (PSC), and construct casting bay.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT REPORT The second phase of the project surveying involves set out for pre-existing bridge, set out for pier piles, and set out for pier piles. The next phase Demolition includes the activities of railing/end post demolishes and partially demolishes deck/wing wall de watering/drainage of creek. The next phase, establish site boundaries includes the activities of embankment, place sheet pile to create coffer dam, and drain water. The next phase, manufacture PSC planks includes the activities of order/receive steel fibres, determine plank size/dimensions, place pre stressed fibres, pour concrete, and steam cure concrete, demold. The next phase excavation includes the activities of excavate for abutment pile A, excavate for abutment pile B, excavate for pier pile A, and excavate for pier pile B. The next phase, construct abutment piles includes the activities of establish site, place steel cases into soil and boring, place steel reinforcement, pour concrete, remove casing, and cure concrete. The next phase construct pier piles includes the activities of place steel cases into soil and boring, place steel reinforcement, pour concrete, remove casing, and cure concrete. The next phase construct columns includes the activities of place steel reinforcement, put formwork in place, pour concrete, cure concrete, and remove formwork. The next phase construct headstock includes the activities of place steel reinforcement, put formwork in place, pour concrete, cure concrete, and remove formwork. The next phase construct abutments includes the activities of place order for elastomeric strips, erect scaffolding, formwork & reinforcement, pour and compact/vibrate concrete, cure concrete, remove formwork, and install elastomeric bearings/ motor pads/ dowel pedestals. The next phase place PSC includes the activities of order crane, move PSC planks to site, order protection angle, set out position, put PSC planks in place, and fix protection angle. The next
11PROJECT REPORT phase Approaching Slab includes the activities of set out position, put reinforcement in place, place formwork, pour concrete, cure and harden concrete, and remove formwork. The next phase Parapet includes the activities of core, put dowel reinforcement in place, epoxy mortar (fill reo), set out positions, put reinforcement in place, place formwork, pour concrete, cure/ harden concrete, and remove formwork. The next phase construct main deck includes the activities of set out positions, put formwork in place for scutter, pour asphalt concrete, cure/ harden concrete, and remove formwork. The next phase wing walls include the activities of place reinforcement in place, put formwork in place, pour concrete, cure/harden concrete, and remove formwork. The next phase railings includes the activities of place order for barrier railings, railing set out, cast posts, use protective coating, weld, and construct panels. The next phase site closure includes the activities of cleanup and removes site services, amenities, power. The final milestone for the project is project completion. Network Diagram
12PROJECT REPORT 1 131718 212426293132 35 42 47 51 76 878891 9293 84 3 4 5 10 14 65 66 67 68 69 70 73 747778109 11196 8912 22 15 7 8375 2527 3037 94 41 48 45 116 114 112 113 615349 50 106 104 103101 99 97 55 33 54 44 43 38 40 36 5657 100 9089 110 105 6059 62 8081 82 85107 111 118117 71 6398 95 Figure 1: Network Diagram for the project (Source: Created by the author) Analysis of Network The project network diagram has been developed using the Ms-Project software and it would involve the activity id on the node for developing effective project progress. The network diagram would be developed for integrating the management of the factors and alignment of the successive information management. The critical activities of the project has been shown in the red blocks and the rest of the activities (non critical) have been shown in blue blocks. Comments on Relevance of work The project plan has been shown in the following Gantt chart,
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT REPORT IDTask Mode WBSTask NameDuration 00WONBOYN RIVER BRIDGE PROJECT191 days 11Start, Administration0 days 22Initial Site Establishment7 days 32.1Initial Surveying1 day 42.2Site Clearance1 day 52.3Signage and Protection1 day 62.4Drainage system2 days 72.5Security and guard outposts1 day 82.6Site Office1 day 92.7Staff Area/ Parking1 day 102.8Site Induction1 day 112.9Traffic Signage2 days 122.10Accessing Roads3 days 132.11Temporary Services1 day 142.12Notify and receive Casting Steel (PSC)1 day 152.13Construct Casting Bay3 days 163Surveying3 days 173.1Set out for Pre-existing bridge1 day 183.2Set out for Pier Piles1 day 193.3Set out for pier Piles1 day 204Demolition4 days 214.1Railing/End post Demolish3 days 224.2Partially demolish deck/wing wall3 days 235De watering/Drainage of creek14 days 245.1Establish Site boundaries6 days 255.2Embankment2 days 265.3Place Sheet Pile to create Coffer Dam6 days 275.4Drain water2 days 286Manufacture PSC Planks13 days 296.1Order/Receive Steel Fibers1 day 306.2Determine plank size/dimensions1 day 316.3Place pre stressed fibers1 day 326.4Pour Concrete1 day 336.5Steam cure concrete, demold12 days 347Excavation6 days 357.1Excavate for Abutment Pile A3 days 367.2Excavate for Abutment Pile B3 days 377.3Excavate for Pier Pile A3 days 387.4Excavate for Pier Pile B3 days 398Construct Abutment Piles12 days 408.1Establish Site12 days 418.2Place Steel cases into soil and boring2 days 428.3Place Steel Reinforcement2 days 438.4Pour Concrete2 days 448.5Remove Casing2 days 458.6Cure Concrete7 days 469Construct Pier Piles9 days 479.1Place Steel cases into soil and boring2 days 489.2Place Steel Reinforcement2 days 499.3Pour Concrete2 days 509.4Remove Casing2 days 519.5Cure Concrete7 days 5210Construct Columns14 days 5310.1Place Steel Reinforcement2 days 5410.2Put formwork in place3 days 5510.3Pour concrete2 days 5610.4Cure Concrete7 days 5710.5Remove Formwork2 days 5811Construct Headstock16 days 5911.1Place Steel Reinforcement2 days 6011.2Put formwork in place3 days 6111.3Pour concrete2 days 6211.4Cure Concrete7 days 6311.5Remove Formwork2 days 6412Construct Abutments67 days 6512.1Place order for Elastomeric strips42 days 6612.2Erect Scaffolding1 day 6712.3Formwork & Reinforcement1 day 6812.4Pour and Compact/Vibrate Concrete12 days 6912.5Cure Concrete1 day 7012.6Remove Formwork7 days 7112.7Install elastomeric bearings/ motor pads/ dowel Pedestals 3 days 7213Place PSC97 days 7313.1Order Crane6 days 7413.2Move PSC planks to site2 days 7513.3Order Protection Angle96 days 7613.4Set out position1 day 7713.5Put PSC Planks in place1 day 7813.6Fix Protection Angle10 days 7914Approaching Slab19 days 8014.1Set out Position1 day 8114.2Put Reinforcement in place4 days 8214.3Place formwork10 days 8314.4Pour concrete1 day 8414.5Cure and harden concrete7 days 8514.6Remove Formwork3 days 8615Parapet22 days 8715.1Core2 days 8815.2Put Dowel Reinforcement in place1 day 8915.3Epoxy Mortar (Fill Reo)1 day 9015.4Set out positions1 day 9115.5Put Reinforcement in place3 days 9215.6Place formwork3 days 9315.7Pour Concrete1 day 9415.8Cure/ Harden concrete7 days 9515.9Remove formwork3 days 9616Construct Main Deck22 days 9716.1Set Out Positions1 day 9816.2Put formwork in place for Scutter10 days 9916.3Pour Asphalt concrete1 day 10016.4Cure/ Harden Concrete7 days 10116.5Remove Formwork3 days 10217Wing walls24 days 10317.1Place reinforcement in place4 days 10417.2Put formwork in place9 days 10517.3Pour concrete1 day 10617.4Cure/Harden Concrete7 days 10717.5Remove formwork3 days 10818Railings96 days 10918.1Place order for Barrier Railings96 days 11018.2Railing Set out2 days 11118.3Cast Posts2 days 11218.4Use Protective Coating10 days 11318.5Weld2 days 11418.6Construct Panels2 days 11519Site Closure4 days 11619.1Cleanup2 days 11719.2Remove site services, amenities, power…2 days 11820Project Completion0 days 10/15 7/8 TSWSTMFTSWSTM Aug 26, '18Oct 21, '18Dec 16, '18Feb 10, '19Apr 7, '19Jun 2, '19Jul 28, '19 Figure 2: Project Gantt chart (Source: created by the author)
14PROJECT REPORT The project plan has been developed for integrating the management of the improved project plan development. The project plan has been developed considering the project activities aligned with the continuation of the improved functional development. The proper project plan development would be supported by the inclusion of the factors and development. The listing of the successful project activity alignment had been implied for taking care of the information management and inclusion of proper project development. Suitability of network The project network would be developed considering the method of effective and improved project plan development. The waterfall model would be developed considering the management of the successive implementation model. The network plan development of the project would be effectively managed with the implication and specific utilization of the project plan development. The project network plan was developed considering the alignment of the improved functional development and integrating the improved construction management. It is significantly managed with the utilization of the innovative construction works. The analysis had been helpful for taking care of the factors and integration of the innovative project completion. Conclusion It can be concluded that the identification of the network elements for the construction project activities had been implied with the continuation of the construction project management. The completion of the project had resulted in identifying the probable management of the information and listing the successful completion of the project. The major factor required for the analysis of the effective construction works had been considered for the construction of the project. The increment of the width of the highway had been done considering the principles of
15PROJECT REPORT the effective project management principles and management. It is important for aligning with the development of the successful project completion. The use of the work package identification had been done for making sure that the probable alignment activities had been formed with the consideration of the factors for aligning the implication management. The report had helped in documenting any change requirements or the progress highlights of the project. The future prospects had been considered for the completion of the effective project compliment. The network diagram had been developed using the project management software and it had implied with the usefulness of the successful project completion. The AON notation for the project activities had been developed considering the development of the activities.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16PROJECT REPORT Bibliography Alomari, K., Gambatese, J. and Olsen, M.J., 2016. Role of BIM and 3D laser scanning on job sitesfrom theperspectiveof constructionprojectmanagementpersonnel. InConstruction Research Congress 2016(pp. 2532-2541). Bascoul, A.M., Tommelein, I.D. and Tuholski, S.J., 2016, November. Construction Project ComplexityasAddressedinTraditionalversusLeanProjectManagementLiterature. InConstruction Research Congress 2018(pp. 282-293). Burtonshaw-Gunn, S.A., 2017.Risk and financial management in construction. Routledge. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Harrison, F. andLock,D., 2017.Advancedprojectmanagement:astructuredapproach. Routledge. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Lock, D., 2016.Project management in construction. Routledge. Lock, D., 2017.The essentials of project management. Routledge. Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalofproject management,32(2), pp.202-217.
17PROJECT REPORT Nicholas,J.M.andSteyn,H.,2017.Projectmanagementforengineering,businessand technology. Routledge. Oakland,J.andMarosszeky,M.,2017.Totalconstructionmanagement:Leanqualityin construction project delivery. Routledge. Raj,M.andWadsamudrakar,N.K.,2018.Riskmanagementinconstruction project.International Journal of Engineering and Management Research (IJEMR),8(3), pp.162- 167. Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015.Construction project management. John Wiley & Sons. Turner, R., 2016.Gower handbook of project management. Routledge. Walker, A., 2015.Project management in construction. John Wiley & Sons. Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), pp.1214-1225.