Project Management: Gantt Chart, Stakeholder Analysis, WBS, Risk Register

   

Added on  2022-12-15

14 Pages2133 Words403 Views
BM522 Project Management
Project Management: Gantt Chart, Stakeholder Analysis, WBS, Risk Register_1
TABLE OF CONTENTS
INTRODUCTION...........................................................................................................................2
TASK 1............................................................................................................................................2
Gantt chart...................................................................................................................................2
TASK 2............................................................................................................................................6
Stakeholder analysis....................................................................................................................6
TASK 3............................................................................................................................................7
WBS.............................................................................................................................................7
TASK 4............................................................................................................................................7
Risk register.................................................................................................................................7
TASK 5..........................................................................................................................................10
Different criteria to meet the project deadline...........................................................................10
TASK 6..........................................................................................................................................11
Methodology..............................................................................................................................11
CONCLUSION..............................................................................................................................11
REFERENCES..............................................................................................................................12
Project Management: Gantt Chart, Stakeholder Analysis, WBS, Risk Register_2
INTRODUCTION
Project management is a process of leading the work of team to attained goal and meet
the success criteria as well. The present study helps to attract the investors for the project and for
that network and gantt chart will be developed in order to determine the duration of a work.
Also, present stakeholder analysis and define the best project management methodology for the
project as well.
TASK 1
Gantt chart
Task
Mode Task Name Duratio
n Start Finish Predecessors Early
Start
Early
Finish
Late
Start
Late
Finish
1 Budget
Approval 1 day Mon
4/26/21
Mon
4/26/21
Mon
4/26/21
Mon
4/26/21
Mon
4/26/21
Mon
4/26/21
2 Hire Publicity
Director 14 days Tue
4/27/21
Fri
5/14/21 1 Tue
4/27/21
Fri
5/14/21
Tue
4/27/21
Fri
5/14/21
3 Hire Set
Designer 14 days Tue
4/27/21
Fri
5/14/21 1 Tue
4/27/21
Fri
5/14/21
Tue
6/15/21
Fri
7/2/21
4
Hire
Place For
Auditions
7 days Mon
5/17/21
Tue
5/25/21 2 Mon
5/17/21
Tue
5/25/21
Mon
5/17/21
Tue
5/25/21
5
Advertising
To Hire Crew
and Cast
7 days Mon
5/17/21
Tue
5/25/21 2 Mon
5/17/21
Tue
5/25/21
Mon
5/17/21
Tue
5/25/21
6
Hire Production
& Publicity
Crew
28 days Wed
5/26/21
Fri
7/2/21 4,5 Wed
5/26/21
Fri
7/2/21
Wed
5/26/21
Fri
7/2/21
7 Set Designed
and Built 35 days Mon
7/5/21
Fri
8/20/21 3,6 Mon
7/5/21
Fri
8/20/21
Mon
7/5/21
Fri
8/20/21
8 Train Production
Crew 12 days Mon
7/5/21
Tue
7/20/21 3,6 Mon
7/5/21
Tue
7/20/21
Thu
8/12/21
Fri
8/27/21
9 Auditions To
Hire Cast 2 days Wed
5/26/21
Thu
5/27/21 4,5 Wed
5/26/21
Thu
5/27/21
Wed
5/26/21
Thu
5/27/21
10 Cast Rehearsal 66 days Fri
5/28/21
Fri
8/27/21 9 Fri
5/28/21
Fri
8/27/21
Fri
5/28/21
Fri
8/27/21
11 Hire Orchestra 7 days Tue
4/27/21
Wed
5/5/21 1 Tue
4/27/21
Wed
5/5/21
Thu
6/24/21
Fri
7/2/21
Project Management: Gantt Chart, Stakeholder Analysis, WBS, Risk Register_3
12 Music 7 days Thu
5/6/21
Fri
5/14/21 11 Thu
5/6/21
Fri
5/14/21
Fri
8/13/21
Mon
8/23/21
13
Photograph Cast
And Crew &
Collect
Biographies
35 days Mon
7/5/21
Fri
8/20/21 6,9,11 Mon
7/5/21
Fri
8/20/21
Mon
7/5/21
Fri
8/20/21
14
Enter
Information Into
Computer
1 day Mon
8/23/21
Mon
8/23/21 13 Mon
8/23/21
Mon
8/23/21
Mon
8/23/21
Mon
8/23/21
15 Printing 5 days Tue
8/24/21
Mon
8/30/21 14 Tue
8/24/21
Mon
8/30/21
Tue
8/24/21
Mon
8/30/21
16
Develop an
Advertising
Plan
7 days Mon
7/5/21
Tue
7/13/21 6 Mon
7/5/21
Tue
7/13/21
Thu
7/22/21
Fri
7/30/21
17 Advertising
media 21 days Wed
7/14/21
Wed
8/11/21 16 Wed
7/14/21
Wed
8/11/21
Mon
8/2/21
Mon
8/30/21
18 Orchestral
Rehearsal 4 days Mon
5/17/21
Thu
5/20/21 12 Mon
5/17/21
Thu
5/20/21
Tue
8/24/21
Fri
8/27/21
19 Order Costumes 7 days Fri
5/28/21
Mon
6/7/21 9 Fri
5/28/21
Mon
6/7/21
Thu
8/12/21
Fri
8/20/21
20 Costume Parade
And Alterations 5 days Mon
8/23/21
Fri
8/27/21 7,19 Mon
8/23/21
Fri
8/27/21
Mon
8/23/21
Fri
8/27/21
21 Dress Rehearsal 1 day Mon
8/30/21
Mon
8/30/21 8,10,18,20 Mon
8/30/21
Mon
8/30/21
Mon
8/30/21
Mon
8/30/21
22 Performance 10 days Tue
8/31/21
Mon
9/13/21 15,17,21 Tue
8/31/21
Mon
9/13/21
Tue
8/31/21
Mon
9/13/21
Project Management: Gantt Chart, Stakeholder Analysis, WBS, Risk Register_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Music Event: Stakeholder Analysis, Risk Analysis, and Communication Strategies
|17
|2773
|60

Project Management for TFL's Bollo Lane Development
|12
|2087
|245

Desklib - Online Library for Study Material with Solved Assignments, Essays, Dissertation
|15
|2296
|392

Project Management Plan
|13
|1949
|31