1CONSTRUCTION PROJECT Table of Contents 1.Introduction..............................................................................................................................4 2.Literature Review....................................................................................................................5 2.1Project Cost Management.................................................................................................5 2.2Project Scope Management...............................................................................................9 2.3Project Risk Management...............................................................................................13 3.Case Study Review................................................................................................................15 3.1Case Study 1: Contextual analysis on a Lecture Project.................................................15 3.1.1. Introduction..................................................................................................................15 3.1.2. Problem Description....................................................................................................16 3.1.3. Research Methodology and Data Collection...............................................................17 3.1.4. Data Collection............................................................................................................17 3.1.5. Analysis.......................................................................................................................17 3.1.6. Findings.......................................................................................................................18 3.1.7. Recommendations........................................................................................................19 3.1.8. Conclusions..................................................................................................................19 3.2Case Study 2: Sydney Opera House...............................................................................19 3.2.1.Introduction..............................................................................................................19 3.2.2.Problem Description................................................................................................20
2CONSTRUCTION PROJECT 3.2.3.Research Methodology and Data Collection...........................................................21 3.2.4.Analysis...................................................................................................................22 3.2.5.Findings...................................................................................................................22 3.2.6.Recommendations....................................................................................................23 3.2.7.Conclusions..............................................................................................................23 3.3 Case Study 3:Severe Exploitation of Foreign Workers in Australia..................................23 3.3.1.Introduction..............................................................................................................23 3.3.2.Problem Description................................................................................................24 3.3.3.Research Methodology and Data Collection...........................................................25 3.3.4.Analysis...................................................................................................................25 3.3.5.Findings...................................................................................................................26 3.3.6.Recommendations....................................................................................................27 3.3.7.Conclusions..............................................................................................................28 4.Challenges..............................................................................................................................28 4.2.Cost Management challenges..........................................................................................28 4.3.Scope Management challenges.......................................................................................30 4.3Risk management Challenges...........................................................................................31 5.Strategies................................................................................................................................32 5.2.Cost Management Strategy.............................................................................................32 5.3.Scope Management Strategies........................................................................................33
3CONSTRUCTION PROJECT 5.4.Risk Management strategy..............................................................................................34 6.Conclusion and Recommendations........................................................................................34 7.Reference...............................................................................................................................36
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4CONSTRUCTION PROJECT 1.Introduction The process of implementing skills, process, experience, methods and in order to acquire the desired goals of an undertaken project within the constraints of the project is known as Project management. The output of a project is obtained within the assigned timeline and the budget made for the same. The management of the resources and knowing the scope of the project is most desirable to proceed with any project. The factors responsible for the success of a project and manage the project effectively are defines as the CSFs, that is critical success factors. The CFS are the important activities that are undertaken in any project so that the desired goal of the project is achieved. These factors are given special priorities so that the important activities of the project are completed as per the planning of the project. The CSF are differentiated into several categories such as cost, time, change, quality, organizations, and stakeholders. The CSFs that are mostly considered in the project are project goal clarity, communication of the stakeholders, effective planning of the project, team motivation, importance to project manager, project coordination, team member’s competence and support from higher management. All the project goes through the common phases of initiation, planning, execution, monitor and finally closure. The approaches to project management are definedinthePMBOKandthosecanbeappliedtotheengineering,softwareand construction related projects. The available knowledge areas according to POMBOK in the area of project management are vast and from that the most important three knowledge area are the scope, risk and cost management. These three areas are the most crucial areas to undertaken in project to achieve the desired success of the project. The success factors of project are briefly discussed in the literature review section. These success factors are closely related to the ways of the management of the project as well as the
5CONSTRUCTION PROJECT knowledge areas taken under consideration. The three related case studies will be explained with considering several aspect for each of them. This report will briefly discuss all the challenges that comes of the three knowledge areas of project management. The strategies to manage a project is also discussed below specifically for the knowledge areas. 2.Literature Review 2.1Project Cost Management According toBanihashemi, Hosseini, Golizadeh & Sankaran, 2017, the construction project are complex and dynamic in nature. The initiation of the project are mostly structured with the good idea, huge amount of investment from the shareholders and involvement of great team, however they fail to reach the desired success. The failure is observed due to the inability to understand the statistics of the project that is the cost, scope and time related to the project. The initiation phase of the project consist of the advantages, disadvantages, strategies and values. The success of the project is considers to be the research scope of the project that is dependent on the scope, quality and time of the project. Benchmarking is utilized by the project team members so that the project success can be defined well by distributing the meaning of the profit gained by the contactors of the project as well as the owner of the project. The quality cost of the project is described in the considered project, the proper monitoring and analysis of the quality cost related to the project is carried out so that technical performances can be judged well. It is expected that the quality cost plays a vital role in the success of project in the aspects of the cost of the project.
6CONSTRUCTION PROJECT The project cost preparation is an important section in the planning of the entire project, it involves control of time too and both are interdependent to each other. In the construction project of UK, some deficiencies of the same are identified as discussed by Olawale & Sun, 2015in their article. In order to understand the problems occurring in the field of construction project, a survey is conducted taking around 250 companies of UK. Then an interview was conducted with 15 practitioners of the same company so that the issues can be identified better and the experiences that the people have while face those issues. The details of the ways they have undertaken to mitigate those issues are also asked in the interview process. The authors have recommended around 65 ways that can be utilized to control the risks of project, those are reporting, analysis, monitoring and planning. These recommendations are proposed from the analysis of the answers obtained from the interview as well as some literature available. The Delphi mechanism is undertaken by the practitioner of the undertaken interview, to evaluate and analyse the recommendation made on the basis of the details mentioned above. For the industry of constructioninUKtherecommendationsaregivenspecialplacesothatthe improvements can be observed in the practices of project. The techniques used for controlling the cost and time of the project are effective by several groups. The planning of the project were conducted by the latest techniques sues as the use of critical path method or use of gantt chart alongside the tradition techniques. The software which are used for the same purposes in UK are MS Project and Asta Power project. In construction project the controlling of the cost in the project is the most crucial aspect of the project to achieve the desired success in the same field. In order to achieve success through this process the ultimate requirement is to have updated input of the data
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7CONSTRUCTION PROJECT in all the stages of the project. The contractors of small and medium size lack in providing the desired number of workers and investment which cause failure in tracking the cost related to the project. In construction, the documents of the buildings misplaces the actual amount of the project. The tasks can only be controlled by the exact details of the project to enhance the time and accuracy of the project to have positive impact on the overall project. One main reason in the occurrence of the issues related to the cost is in the collection of the original data. The procedure to mitigate the issues occurred in the project are suggested by the authors and that is the BCCS, which stands for Barcode based Cost control system, this is used on the software of spreadsheet, it will eventually conduct a comparison between cost accountant and the prepared budget that have been developed from the bills’ cost. The results obtained from undertaking the process to mitigate the issues have been useful to reduce the time and errors of the project. It has also stand out be effective for SMCs project cost controller. The approach is expected to be benefiting some future managements such as worker keeping, materials management and collaboration with others. In projects the aspect of cost management is identified with some challenges by Smith, 2014 in his article. The profession has some issues and those are directly related to the cost, quantity, project controls and project manager services. The recognition that cost management has is very much different to the other available professions, as this profession has a greater impact on the society in respect to creating awareness among all and this becomes somehow challenging for them. The article clearly states the issue that is common in the field of cost management, this is faced by the professionals involving the association of the international project management, quantity surveyors’ association,
8CONSTRUCTION PROJECT etc. The global standards are identified and programs of certification. A series of recommendation and strategies are also addressed by the authors on a global platform like United Nation, World Bank, International Management Fund and many other. The cost management is essential in every project as the most crucial portion of ant project is to manage the budget of the project so that the stability of the project is maintained by the project manager and conduct the project in an effective way. The main idea behind the conduction of cost management is that the budget of the business remains controllable and the accounting stay under the control. The expenditure of the business is always lowers and the success and process keep on successions. The cost management can be performed on a portion of a project or on the overall project. The cost differs on the expected by the planning team and the end of the completion of the project. This expected cost of the project is defined at the planning phase and approved by the seniors of the project department (Raman et al., 2019). At all the phases of the project the expenses of the project like the cost of raw materials, payment to the workers and every little sent is recorded so that the cost of the project can be controlled and monitoring is done to keep the projectunder the budget. At the closure phase of the project the standing cost of the project is compared with the cost that is assigned to the project team at the planning phase of the project. The difference between them will clearly show the amount that is required extra for the project or the project is conducted under the budget only (Meikandasivam, Vijayakumar & Priya, 2017). The analysis and the difference in the cost can be used as reference for the future conduction of the project budget and the monitoring process can also be improved based on that.
9CONSTRUCTION PROJECT Some organization or companies forms a proper structure of cost on the undertaken projects so that the budget can be controlled better. The budgeting is done and monitored for all the process of the project stating from the initiation phase till the closure phase. In the resource planning phase the cost assigned with all the resources are also assigned and distributed throughout. All the tools required as well as developments done are associated with some costing and therefore undertaken in the planning phase only (Ainslie et al., 2014). The next is the estimation of cost, quantifying the cost of the resources needed is done with all the available investment process available in the industry. The developed information of the project and the resources are designed and submitted to the finances. The process such as the schedule, cost control, analysis of the cost all are undertaken (Nayak, 2014). The process of cost estimation is done on all the phases whenever any modification, addition or cancellation of assets or resources are take place during the project. In this modern technological, the availability of tools and software are vast and those are used at larger scale. It also seen that the time required in the performing of the tasks of the project t is directly proportional to the cost of the project. Whenever, the time required for the activities increases the cost increases in the same manner. 2.2Project Scope Management The SMCEs are studies thoroughly byJavernick Will, La Ratta & Corvello, 2017, which plan, control and monitor the scope of project on daily basis. The features of the SMCEs are accurate performance and developing the routines of cost management. A survey is conducted in the article and that is totally based on questions and answers. And then those are made available to the SMECs. Regression analysis is done of the collected information from the survey. The processes of scope management on the daily basis and
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10CONSTRUCTION PROJECT performances are the overall uses of the process of the project scope management. Those appeared to be negative or positive that have performance impact on the SMCE’s. The managers of the SMECs have taken up the approaches of project scope management system that are practical as well as systematic, this eventually enhance the performance of the organization. The authors have mainly focused on the SMCEs that has project scope management. The boundaries of the project that hast the processes of the controlling, registering defined in PMBOK for the purpose of scope management is well defined by Atkinson, Crawford & Ward, 2006. The relevance that have been observed for the success of the project as well as the applications is the biggest challenge as the tools are not available by the project managers which will faster the processes undertaken the project. The tools are supposed to be supportingthemanagementprocesses.Theabsenceofcomprehensionaboutthe necessities of the task is another factor, which frustrates the execution of that specific territory in light of the fact that regularly the stakeholders don't have total information with respect to the requirements while starting the undertaking that additionally brings about changes all through whole other lifecycle that likewise expands the expenses and cutoff times. In this situation, the fundamental goal of the researcher is to present the combination about degree the executives by actualizing the methodology of designing for better recognizable proof of necessities with respect to the undertaking and furthermore for understanding that what requires to be done, which may have a huge commitment in the success of the task.
11CONSTRUCTION PROJECT For assessing every one of the outcomes got from this research, the requirement module of engineering has been set up and coordinated by utilizing tool of computation for the project management that likewise planned for helping the application to follow every one of the rules as well as practices, as stated in PMBOK. According toIfeanyi, 2019,the most part cantered the quantitative scope identified with the scope change of the project, basically in creating project. The primary goal in the research was to decide about the quantitative strategy be utilized for dealing with the varieties, especially for the structuring scope change. Survey strategy is undertaken by the researcher. Alongside this, the EVA was additionally used for assessing 10 number of projects.Asidefromthis,asurveyasadditionallybeenconductedtoaround52 respondents. PIM and graphic statistics were used in the analysis. The outcomes show the huge changes in the project that may happen for the most part at the execution phase. This research states that the application of the PMI for solving the issue identified with scope change of the project. The author stated that the usage of PIM in the management of scope change would facilitate the project scope change and classify them depending on the life cycle. The intension of project scope management is that the process ensuring in the project are carried out correctly and mapped into the project accurately. The benefit of project scope management is utilized by the project manager, it enables them to sort the activities and tasks of the project to the rightful person and obtain the desired out to reach the success of the project. The techniques of the scope management helps the project manager to allocate the activities as per the requirement and necessity of the project. This
12CONSTRUCTION PROJECT is an essential requirement of the scope management of the project. The set of deliverable oftheprojectthatareundertakenintheoverallprojectisunderstoodfromthe requirement of the project only. Some project managers define the scope manages is the process that need to be undertaken in order to deliver a successful project is the better ways to manage the scope first and then proceed with the rest of the activities of the project. The clear knowledge and identification of the activities undertaken by the project is to deliver the successful project to the stakeholders is defines ion the scope statement of the project. The responsibility of the project manager is that the scope of the project is on the focus and given priorities to. The boundaries of the project is defined in the documentation of the scope management with the proper sorting of the roles and responsibilities of each member of the team. The procedures of the tasks are also defined with the works, later these are compared with the assigned and the done work by the team members of the project. This is an official statement made by the project manager, it is also know by the names of work statement, reference of terms and scope statement (Girma, 2018). The designated steps followed in the management of the project scope are’ definition of the needs of the project- the timeline of the project is established with the resource allocation and setting of the objectives. The work then further process and the defining helps in smooth going of the processes with proper name, meaning and each definition having a particular scope. After this the members are assigned with the tasks and specific procedures that needed to be followed by the member to deliver the same. Then the next step is the understanding of the objective of the project- the definition of the scope will require the establishment of the project objectives. The incorporation of the new services, new
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13CONSTRUCTION PROJECT products and developing new strategies (WEKESA, 2016). The management team mainly the manager keeps the track that his team deliver the outcomes that were expected at the definition stage along with the functions and features of the project. The last one is the project scope definition- the work and resources that are the backbone of any project are the direct scope of the project. Hence, the objective or the goal of the project that the project team aims to achieve at the end of the project completion with satisfaction of all the members present is known as the scope of the project. 2.3Project Risk Management According toSols, 2018, a few distributions have managed different risks, which isn't done extensively. This article consists the methodologies that have been identified by the writer dependent on 25 years of experience, and these identifications had process basically for the dynamic risk management. The use of technique suggested in this paper can be utilized widely. By the utilization of several criteria the assessment is completed. Thecriteriaarethewarnings,immediacy,triggeringfactor,recoverabilityand aggregability factor. The research also consists of thorough assessment, the risks that are present in the assessment are found at the time of execution with agreeing with the project processes. The synthesis that was conducted in the research is the knowledge for pursuing practice by the variable managers of engineering in the project management process. The maturing of the management of risk in a project is essential for the effective implementation of the management tactics of risks so that the desired goals of the project are achieved.In order to provide successful project, the learning from the organization is important as it increases the experiences and knowledge of individual to perform better.
14CONSTRUCTION PROJECT The management of risk is shown critically in this research undertaken and the quality, time and cost related to the project undertaken in the organization is of construction which has a huge impact on them. The learning of the organization have been seen as the criteria of success in respect to cost and quality. It has been observed that the learning or organization is impacted by the presence of the success criteria and performance of project get better in the presence of the success criteria along sides the maturity of the risk management. The aspects of risk management as shown byDandage, Mantha, Rane & Bhoola, 2017, in his article that the project achieves its goal only after facing the challenges, worker’s attitude, culture of organization, methodologies of risk management, overcoming the barriers of risk management and finally incorporating the higher managements. The varied range of management of risks as well as risks are discussed in this paper that are observed to be domestic as well as international projects. This paper consists of several methods of modelling of the risk management, MICMAC analysis, ISM as these methods have been utilized for observing the relation of the priorities and barriers (Corvello, Javernick-Will & Ratta, 2017). The barriers that are considered in this paper are the differences in culture, inadequate formal training and unavailability of support from the higher management. The process of analyzing, responding an identifying the possible risks related to a project in the entire life cycle of the project. It is the most important part of the project that is mandatory to incorporate irrespective of the other available process of the project. As the risks of project makes the entire project most vulnerable and it can dis-balance every on-going process of the project (Ridwan & Poespowidjojo, 2017). The suitable
15CONSTRUCTION PROJECT time to involve the planning of the risk management techniques is in the planning phase. This is because predicting the risks at the initial stages will allow the better prevention and protection of the risks and all the possible arrangement can be undertaken by the project manager. The manager can chalk out the ways and present to the team members and ask for the suggestions to each department of the project. All the risks varies from department to department, therefor, giving individual priority to each type of risk is important as well as quite hard (Hamad et al., 2019). However, the risks can cause the scope change of the project, cost change of the project, increase the timeframe set to each activity. Therefore, to stop all the negative activities the strategies developed in the planning phase is defines as the risk management procedure. The present of project charter and maintenance of it can show the possibilities in the occurrence of the risks. A list is prepared with the help of the team members and possibilities are written down then thorough analysis is done to narrow it down to the most prone risks that the project may experience.The plan of risk management is prepared with the identification of the risks and possible way to diminish it before causing any harmful effect on the project (WEKESA, 2016). The regular monitoring of the risks are required hence, forming a group that only focuses on the risks and all the strategies to prevent them as well as stopping them from effecting the project. Risk register is another way to lay out the identified risks, the description of the risks, its likelihood and its intensity of impact on the project process. This register is then utilized to prepare the matrix of risk, the matrix consist of the likelihood of the risk with three parameter of high, medium and low (TOMAIZEH, 2016). The three parameter is then
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16CONSTRUCTION PROJECT represented by three different color to keep focus of the high risks which needed more attention during the conduction of the project. 3.Case Study Review 3.1Case Study 1: Contextual analysis on a Lecture Project 3.1.1. Introduction In the Australian University, addressing of the redesign research of the contextual analysis is carried out. In 2017, the project was initiated with the aim of enhancing the capturing of the lecture facility in the lecture campus inside the campus. 160 classrooms are present in the five available campuses. The staffs are happy in conducting their work. The members of the project must have the access of the lectures in the classroom of the University in order to complete the upgrade work in the assigned time. The important elements of the planning of the project are the risk, cost and scope. As stated byHuemann, 2016the deliverables of the project are defined by the scope of the project along with the requirements of the project, constraints, milestones of the project and assumptions of project. The elements of the project are associated with the risks with the impact on the objectives of the project. The element of cost is represented as the resource for money needed in the project (Lock2017). 3.1.2. Problem Description The problems that have arisen in the University due to the redesigning of the research plan in respect to lecture capture. i.Some of the devices do not provide any response against the upgrade code and result in the failure of the equipment and devices.
17CONSTRUCTION PROJECT ii.Unavailability of lecture rooms hence the upgrade is not possible to achieve. iii.The communication gap is seen with the security officer of the campus are unaware of the lecture going on the campus. iv.Paying a visit to the people of the talk ro0om so that arrangements of the gadgets are done correctly. v.The lecture rooms do not have the activities schedules, hence, the rooms are used by the staffs of the upgrade work. 3.1.3. Research Methodology and Data Collection The upgrade projects of lecture capture are categorized into several parts, practices, information of examination and choice and those are carried out by the research methodology as stated byBresler and Stake2017. The benefits that are obtained from this methodology is utilized for analyzing the reliability and validity of the data and information about the work done. The description of the characteristics are studied well through this method. This is then represents the idea of the fragments irrespective of the overall work. 3.1.4. Data Collection The data collection technique used here is the secondary way of collecting the data. The data is gathered by the team and then analysis id done on the data and information. By the virtue of electronic means the gathered data is sorted and further reviewing and publishing is done along with other case studies. The data is collected from the records available on the internet (Kerzner, 2018). The benefit of this collection is that the gap is well understood in the project and the required data to be added can be collected too.
18CONSTRUCTION PROJECT 3.1.5. Analysis The analysis of data is of two type one is the qualitative and the other one is the quantitative and this study has used the qualitative way so that the topic related details get clearer. The assumptions are the key to the success and project manager utilizes that only to get all the information of the three concepts of project management that is risk, scope and cost (v, 2015). The data that is collected represents the concepts of project management better so that the values can be understood from them and the people behaviors can be understood (Humphries, 2017). The selected topic of the project is benefited from the researcher’s point of view in the documentation. 3.1.6. Findings The facilities of the lecture capture for the lecture room is upgraded as found on the documents and secondary research data collected relating to the topic undertaken. The lecturer rooms can be upgraded as the scope of availability of the classrooms are present with nearly 160 in n umber. The upgrade will be expected to be in active mode when all the lecturer rooms are shut together (Binder, 2016). The expectations that are done from the tasks are scope articulation, administration plan, venture sanction, cost plan, etc. The risks of the project were the deficiency in the planning of the project, the incompetence of the university about communicating with the officers at the ground about the changes in the lecture room. The delays in the project have occurred due to the negligence in planning and not performing communication effectively with the people related to the project. The scheduling of the activities of the project are not up to the mark and standards of the project hence it causes a great degradation in the lagging of the project (TOMAIZEH, 2016). The staffs are also
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19CONSTRUCTION PROJECT responsible for some of the issues as they reach the lecture rooms behind the schedule and causes disruption in the overall timeframe of the project. The assigned time for the completion of the project was four days, however, the series of events that caused delays have extended the time limit as well as the cost of the project also increased drastically. The manager of the project t is supposed to keep the team on the track of the schedule so that the project does not go beyond the budget that is assigned on the initial phase of the project. 3.1.7. Recommendations The recommendation are the better scheduling so the project plan have a clear upgrade as per the tasks and activities related to the project. The scheduling will also help in the better estimation of the cost of the project and control the extra expenses of the project. Another recommendation is about the management of risk related to the project, the policies of risk and the processes to mitigate them must be formulated and communicated to the members of the team by the manager of the project. The effective ways of mitigating the issues before it impacts the project needed to be undertaken by the project manager. 3.1.8. Conclusions The overall project can be concluded as the upgrade of the lecturer rooms are required and hence, to implement the same some necessary changes in the process of the project needed to be change that is the communication of all the members of the team and the staff of the university to maintains the scope of the project. The strategic approach to achieve the goal of the project is the most important task that needed to be understood by all the people involved in the project. The risks of the project are observed by the manager to mitigate them on time before any negative impact is made on the project.
20CONSTRUCTION PROJECT 3.2Case Study 2: Sydney Opera House 3.2.1.Introduction The Sydney Opera House is one difficult construction project that is based on the contextual analysis. The management and the financial planning of the project makes it more dangerous. This project consist of clear goal and objectives that needed to be achieved in the overall process of the project. The client of the project have defined the goal beforehand. The development of the Sydney Opera House consist of the factors such as cost, quality and time. The delays is project was observed due to some development work of unrestricted goals. The funding of the project t is obtained from some lottery and there was no pressure on the government in the aspect of cost. The development plan of the project explores the aspect of the three knowledge areas of project management those are the scope, cost and time. The undertaken project is clearly based on the development of works that is related to the scope management of the vastly as stated byCorvello, Javernick-Will and Ratta2017. The management of risk is about reducing the possible issues in the developing project so that the risks cannot cause any harmful effect of the objectives of the project. As perSteyn2017, the idea behind incorporating cost management is to keep the budget of the project under the control and maintain the work that is under development. Hence, this procedure will lower the expenses of the business and keep the project away from exceeding the budget. 3.2.2.Problem Description The problems that are associated in the construction project of the Sydney Opera House are as follows:
21CONSTRUCTION PROJECT i.When the construction project started, the client suddenly changed his requirement of constructing 4 theaters in place of 2 theater, along with that the design of the building has also changed drastically. This affected the time of the construction from the planning before. ii.The budget of the project got affected with the sudden change in the requirement of the project. The coast of the project increased on the year 1962 by AUS $1.2 million and it got completed by 1963 by the budget of AUS $5.2 million. The schedule of the project also got pushed by 47 weeks. iii.The construction of the Opera House started before the competition of the planning and designing of the building. iv.The latest scenario of the Sydney Opera House incorporated new designs in the project as on the structure that the Sydney house stands. The effect was directly seen on the time taken by the project in completion that is of 14 years which was supposed to be 4 years and the budget ran up-to AUS $85 million. v.The changes in the designing caused changes in the second phase of the project and as the cost increased with no effective change in the construction, the government of Australia became more prone to not to clear the payments of the construction. 3.2.3.Research Methodology and Data Collection According toQuinlanet al., 2019,the methodology of research is aimed to provide effective process of the project so that the data related to the project are accessed well and utilized better in the course of the project. The case study of Sydney Opera House is the clear representation of descriptive research as per the reaction of the people involved in the project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22CONSTRUCTION PROJECT of constructing the building. The validation of the [project is done better when a group is taken under consideration in any project. The construction work is carried out by the team members on the basis of the information already available on construction. Hence, the method of data collection used is the secondary procedure. The data are reviewed through the means of electronics (Al Sebeyi, 2016). The research is further taken forward by documenting the records of the project as collected in the several steps of the project. The gaps in the project are identified well by this procedure and hence, helps in the case study analysis. 3.2.4.Analysis The undertaken project of Sydney Opera House, has utilized the data collected and they followed up with the qualitative approach to analyze it better. The investigation about the aspects of the project along with people is done similarly with the qualitative method. The people involved have responded better about the project scenario (Silverman, 2016). The knowledge areas that are taken into consideration of the project are the cost, scope and risk (Harrison & Lock, 2017). Hence, as per the knowledge areas the data about the project are collected alongside the concepts under consideration. 3.2.5.Findings The data collected of the project are documented well, the synchronization of the scope of the project is matched with the objectives as well as the timeframe allotted with the project. The undertaken factors that is cost, time and quality will be basis of the project and hence developed further(Harris, 2017). However, one benefit of this project that the budget and funding of the project is most attractive as lumsu amount is provided by the government. The financial issues are most likely to not occur.
23CONSTRUCTION PROJECT In the aspect of risks related to the project, the scheduling and planning g of the projectareexpectedtogetaffectedduringtheproceduresoftheproject.Themain problematic situation occurred when the client changed the designing all of a sudden, hence the change in the timeline and the budget all got dis-balanced and the time pushed to 14 years for completion. Also the demand for the changes in the designing of the building was done after the start of the project, hence it became more complicated to change in the middle of the project. The aspects of cost management was seen as the estimated budget was done on the designing that was in the middle of completion and the new demand and requirement have turned the budget to different direction with the conduction of the survey leading to approved decisions (Tonchia, 2018). The budget of the project rose to AUS $102 million from AUS $7 million. The control on the budget was available to the manager of the project only. 3.2.6.Recommendations The proposed recommendation on the above case study is for the conduction of planning procedure and the other one is the effective panning of communication. The planning of the project must have been done in the earlier process and the change in the requirement must have closed in the planning phase of the project only. Along with that the project must have start only after complete planning of the overall project. The chances of allowing change will have no room further. The communication plan must be strong to its ground, the conveying of all the policies to the stakeholders of the project beforehand and any occurrence in change must be update through some means to the people on the project. The project can only be completed after proper follow-up of the rules so that the desired goal can be achieved.
24CONSTRUCTION PROJECT 3.2.7.Conclusions It can be concluded from the above study that the control of the activities of the project must be done by the manager with following of a set of rules and regulations. The change in the scope of the project must have accepted and incorporated with the better management of budget of the project. The risks occurrence and mitigating techniques must have followed by the manager before it puts any negative impact on the success of the project. 3.3 Case Study 3:Severe Exploitation of Foreign Workers in Australia 3.3.1.Introduction The construction of the building complex is most focused about the process of contextual analysis in Queensland. The contract of the building was passed by 50% lower rate apart from the other available construction tenders. The completion of the project is expected in six months. The stonemasons worked for all the days in a week and they were completely living their life in the containers with the working days to be five per week. The payment received by the workers were $45 in every month and $100 to their families. Later it was found that the sub-contracting exists for stonemason(Huemann, 2016). The workers were getting lower that the actual payment that they must receive which was a strong case in the Australian court. The study aims to explore the knowledge areas of scope, risk and cost related to all the elements of the study. The plan of the project that is developed is aiming to the effective scope management.Theprocessoftheprojectmanagementarelinkedwiththeeffective management of the construction project with relating to the knowledge areas. The approval
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
25CONSTRUCTION PROJECT of the project is the most crucial part hence the cost management procedure is implemented for better estimation of cost and resources required in the project (Nguyen & Mohamed, 2018). The management of the risk related to the project is totally dependent of the developing stage of the project and it is the duty of the manager to achieve the goal while mitigating the risks. 3.3.2.Problem Description The number of issues tnbat6 have occurred in the study of the project are as follows: i.The time of the completion of the project id delayed by six months, which increased the cost of each activity as well as overall budget of the project. The loss in the profit as well as original revenue of the business also lowered by this. Along with this the reputation of the business also got compromised. ii.As the project manager went for the cheaper tender for the project that did not worked out well in place of that the construction work got delayed. Some profits were made by the tender due to the situation the project developed. iii.The worker’s safety issue became a concern, their safety got hampered and assistance of medical care was provided to them by the management of the project. The payment received to the workers were not considered by the developers present there. 3.3.3.Research Methodology and Data Collection The methodology taken under consideration in the respect of the research is of the secondary ways. The sources of the information for clarifying the question occurred during the research are from the already existing cases of complicated buildings. The results of those research are evaluated well to obtain the possible changes in the scope, cost and risk of the undertaken project(Quinlan et al., 2019).
26CONSTRUCTION PROJECT The sources of collecting information for proceeding with the research are from article, journal and any published articles. Understanding those and applying the knowledge on the undertaken project is carried out effectively. This ways is done vastly to investigate the variable aspect of researches (Fletcher, 2017). This data collection techniques is known as the qualitative approach of data collection 3.3.4.Analysis The procedure of displaying the research in a descriptive way is by conducting the analysis qualitatively. The considered knowledge areas are evaluated by the methods in the qualitative analysis. The benefits of this approach is that the hidden consequences are identified well with the effects of exploration for the undertaken project work(Kerzner, 2017). The procedures of the project are evaluated well by bthe present of the injformstion essential for the conduction of the projectand evaluating the process at every stage of data collection. It also helps in presenting modification of the assessed results through people’s perspectives. 3.3.5.Findings The findings of the project are based on the three knowledge areas undertaken that is the scope, risk and cost. The scope management is related to the defining of the scope and achieve it by proper allocation of work to the workers by the project manager, they also assigned the cost with all the tasks assigned individually to the worker. The three phases of projectthatisthecontrolling,planningandclosureareeffectedbytheeffective management of the scope. When the scope of the project in the construction was undefined the probability of the occurrence of creep scope increases and the chances in the delay of the work increase in the same way(Piercy, 2018). The management plan of scope ensures the
27CONSTRUCTION PROJECT inclusion of work. The work then needed to complete irrespective of the work not demanded in the project. The finishing of the project result in the keeping the scope of the project intact. It provides information about project scope in a well-defined nature of the project. The basic idea behind the risk management procedure in the project is that the risks can be identified at the required time and the mitigating process can be undertaken and applied properly to the risk that occurs at the activities of the construction project. The project manager tracks all the possible risks and try to reduce it so that the tasks can get completed at the assigned time of each (Hamad, Burhanuddin, Ghani, Khanapi, Elzamly, & Doheir, 2019). The maintenance of the schedule of the project is also important while managing the risks as the risks mostly target to hamper the schedule of the project and makes the works run behind the planned schedule. It also allows the manager to stay within the project budget with the approach undertaken by the manager. The project experiences all the stages of project lifecycle and one constant activity that is followed throughout is the risk handling techniques. The challenges and problem that are faced by the workers in constructing the high raised building can be solved by the tasks assigned throughout the life cycle of the project as well as the ways in which the risk mitigation is taking place(Nielsen & Faber, 2017). Another aspect is the solution of the consequences obtained throughout the activities of constructing the building by the aid of risk mitigating techniques. Lastly, the knowledge area of the cost management is presented in which the cost of the project t is controlled so that the possible activities, procedures and the overall probability of the project is determined. The planning phase of the project consist of the determination and sorting of the cost of the activities, resources and all the inventory items of the project. Those are approved and reviewed by the management of the top levels. It is
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
28CONSTRUCTION PROJECT the responsibility of the manager to keep track of all the expenses of the project along with cutting of the cost if required at any stage of the project. The aim of the manager is to keep the cost under the budget that is defines at the planning phase (Huemann, 2016). The variation in the information about the result as per the change in the scope will result in the change of the cost too. The cost associated with the operations of the activities are also added to the budget of the project. 3.3.6.Recommendations After the project is completed it can be recommended that the workers of the project are the most important people, therefor, their safety and health is the most important factor to be considered in the project process. The workplace of the worker must have the proper facilities of medical care in any emergency case related to the health of the worker. The availability of medical assistance must be provided specially from the side of the manager at the entry level works are done by them only. The lower the rate of illness of the worker, the higher the productivity of the project. It also lowers the overall turnover and enhancing the quality of the work done by the team. The morality of the employees are increased when the safety is provided for them, they remain assured of their health and focuses on the work better. 3.3.7.Conclusions Afterconductingtheresearchitcanbeconcludedthattheknowledgeareas considered that is the scope, cost and risk are the most beneficial aspects that helps the project manager in enhancing his skills and taking the project to its success. The knowledge areas can help the project manager to make a huge difference in the professional field as well as utilizing the outcomes on the management of the projects. The control of the budget
29CONSTRUCTION PROJECT of the project is facilitated by the scope and cost regulation throughout the process of the project. The activities taken up by the project manager are in the aspects to managing the cost and scope, so that the project gets completed within the budget and achieve all the scope defined at the beginning of the project following the schedule at every stage. Hence, the defined knowledge areas are required to meet the success of the project. 4.Challenges 4.2.Cost Management challenges The challenges faced by this knowledge are is possible as some of them are provided below: Schedule and Cost integration:The management of cost consist of one crucial downside when the cost of a project is intertwined with the schedule of the project. The managers of the project face a huge challenge in balancing both at the same time. The scheduling team of the project arranges the task as per the WBS that is the work breakdown structure, on the other hand the financial department handles the overall cost of the project as well as the activities going inside it. The transactions, analysis of the cost and many other aspects of cost is handled by the cost manager. Hence, the differences in the priorities of the different managers becomes a huge challenge to manage. The advanced tools to managers those data about cost and schedule together is a bit challenging for the management(Napier, Keil & Tan, 2009). Cost estimation behind the time schedule:One of the biggest challenges that is faced by the managers of project when the cost of the project estimated is running behind the schedule of the project. The profit of the project gets hampered when the costing is not done on time. The slow estimation in the costing of the project can cause cost overrun and hamper the project by worst. However, if the cost estimation is done within in the stipulated time then it becomes easier for the managers to bid for the profit of the project.
30CONSTRUCTION PROJECT Forecasting and budgeting:The forecasting and budgeting in any project is dependent on the approaches and the background of the person carrying out the total sorting of the cost of the project. If not maintained properly the chance in the loss of consistency is common to occur.Hence the inability of the companies to provide consistent budget and forecast it as required time can hamper the overall reliability of the costing of the project. Customer relationship management:The presence of the customer are always associated with a project. The demand of the customers or the stakeholders may be to obtain the cost report as per their choice. This may result in the preparation of the budget as per the requirement of the customer and budgeting system to the project team is different (Ridwan & Poespowidjojo,, 2017). This well push the manager to develop the budgeting system as per the customer and this will involve some additional cost. The investment of extra cost and time and then forecasting it to them is not practical to undertake. Change Control:The control of the occurred change in a project are most difficult for the aspects of management of cost. At the initial stage the budget is set as per the requirement. However, with the gradual incorporation of the changes the budget gets to fluctuate and controlling it may not be under the control of the manager. It may jeopardize the overall budgeting as well as comers in the path of success. 4.3.Scope Management challenges One of the biggest challenges in the world of project is the challenges in scope management along side the cost management. The challenges are: Change in scope:The change in the scope of the project is the most undesirable aspect from the project managers. The change in scope changes several aspects of the project sand addressing all together is very much challenging for the managers. It can affect in the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
31CONSTRUCTION PROJECT demand and requirement change for the stakeholders in the course of the project. Hence, changes demand from the stakeholder will result in the change of many aspect of project. Therefore, it becomes a challenge for the project success and the management team(Napier, Keil & Tan, 2009). Vagueness in scope:The possibility of unclearness in scope can be challenging for the management of project scope and becomes a hurdle for the managers. This may result in the difficulty to achieve the desired success in the project. The defining g of scope is important as the project proceed after the definition of the scope only. Therefore, the effective scope definition is important alongside the proper communication of the stakeholders to define and manage the scope better. The disbalance in the lifecycle of the project can be seen if the proper definition of scope does not occur(Napier, Keil & Tan, 2009). Poor scope definition:One of the important point in the project is the definition of the project scope and formulating the desired and details scope is required. The managers some time fail to that and the overall basis of the project may change. As the outcome of the project is dependent on the definition of the scope hence, the interfaces and expanding of the scope all depend on the correct definition of the scope. Uncertainty in scope:The prioritizing the requirements of the project are essential and the comparing the specific features with the product are conducted. However the uncertainty remains of the how those features can be shaped for obtaining the product (Pourzolfaghar & Ibrahim,, 2014).The gap between the assumption of the company performing the project and the demand of the customer becomes challenging to meet. Thus, the possibility of change in the scope with the uncertainty in the demands of the customer becomes a downfall.
32CONSTRUCTION PROJECT 4.3Risk management Challenges The last challenge is related to the risk management and those are as follows: Difficulty in identification of risk:The inability to find the risk at the early stage of this challenging. The possibility to understanding the risks related to time and finances are difficult to observe. The activity takes up a lot of time too that can hamper the timeline of the project too. Difficulty in predicting future:The prediction of the future of the project is difficult to observe, hence the issues related to the project are riskier in the later phases of the project. The unavailability of proper knowledge about the risks may cause challenge for undertaking the strategies to mitigate the risks(Tomomitsu, Carvalho & Moraes, 2018). Casualty in risk assessment:The assessment of the risks related to the project is needed to give attention to. All the risks must be assess well so that the risks that may have the biggest impact on the project does not go unnoticed. Prioritizing the risks are also important which is generally ignored by the managers. This becomes a huge challenge for the sensitive projects. No transparency:The requirement of having open conversation about the associated risks in the project, escalations, accountability. This is not followed in many organization and turn out to be a huge challenge afterward. The effective communication between the managers and the workers about the possible risks that anyone assume can be recorded and studied well (Moayeri, Moselhi & Zhu, 2016). The inability of the executive to reach the managers and connect directly to share their thoughts about the risks from their past experiences increases the chances of attacks more to the project.
33CONSTRUCTION PROJECT 5.Strategies 5.2.Cost Management Strategy In order to implement cost management, the strategies that must be undertaken are as follows: Techniques of cost control The techniques of cost control are necessary to undertake by the managers of the project. Some of the techniques can be earned value analysis, budget planning,cost tracking, change controlling and time management. The use of the tools of cost management can enhance the final cost to get the better result. Project requirement analysis One of the important aspects of managing the cost of the project is the understanding of the requirementofproject.Moreover,analyzingtherequirementaspertheeffective incorporation of the requirement makes it effective. This will help in estimating the overall cost of the project and mitigate the chances of cost overrun in the project (Nawaz, Waqar, Shah, Sajid & Khalid, 2019). The allocation of the resources is also possible by the analysis. This technique is essential to keep track of the budget of the project with defining the possible drawbacks. Analysis of value chain:The activities and tasks that contribute to the final product or service obtained at the end of the project is termed as the analysis of value chain. The chain activities to reach the final cost of the project consist of several inventory steps and the values associated with each of them are analyzed to manage and control each of them and reduce the final cost eventually.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
34CONSTRUCTION PROJECT Enhance the business position:The organizations must incorporate the process that keep them on the top of their competitive industry. This is achieve with the intension of taking the company to its success but channelizing the cost to the lowest way possible. For a construction company, choosing of the right step in producing of the end product will indulge in several costs and providing the resources from the places of low cost and delivering high quality product. 5.3.Scope Management Strategies The scope management strategies can be implemented by the project manager to obtain the effectiveness of the scope: Handling the scope change:The changes in the scope must be undertaken with the essential elements that needed to be considered in the process. The elements are return in investment, risk and liability of products, need of the market, schedule and cost impact and added value. Engagement in effective communication:The stakeholders, managers and the members of the team are required to engage in effective communication so that their requirement and needs can be discussed with everyone and expectation of each of them can be identified. Planned meeting between all must be arranged to gain project success proper management of the scope. Planning of the scope:The expectation from the project are defined from the perspective of the customer as well as the project team. The goal is the meeting of the requirement and then the search for the resources and sorting them, to the most suitable members of the team with the most experience and knowledge about the resources and then proceeding with it.
35CONSTRUCTION PROJECT 5.4.Risk Management strategy The management of risks of the project are important to incorporate to gain most benefit out of it. Analysis by expert Taking advice from the experienced person is the most effective ways in the earlier days. The project managers or experts in the same area can be interviewed to understand their opinions and experience related to risk management of project. The risks related to the project can be of any form starting from analyzing the wants till the mitigating them hence the experts can use their experience and place the methods to solve the risks and present it to the best possible way to the customer and it becomes the customer centric also the effectiveness used to be better that the new comer in the field of risk management. Working of risk management by representing data In order to understand the solutions of the techniques applied for managing the risks of the project the engagement of the project manager, team members and the stakeholders are essential to observe. The requirement of showing the comparison of the management techniques undertaken and the success in the project observed(Hysa & Spalek, 2019). 6.Conclusion and Recommendations The recommendation that can be made for incorporating the effectiveness of project management in any project are defined below: Communication-The benefits of communication huge as it keeps all the members involved in the project with the updates of the project and thus helps in controlling the budget of the project and makes the project follow the schedule.
36CONSTRUCTION PROJECT Identification of risks-The development of framework that can easily detect the potential risks of the project in the initiation phase of the project. As per that a team that will be responsible for mitigating the risks must be prepared and perform needful controlling of the risks throughout the project(Napier, Keil & Tan, 2009). Creation of work plan-The development of plan which will be followed throughout the project is essential. It will the blueprint of the project and following that will make the team members a specified path to progress in the project. The plan will have all the aspects of the project starting from the timelines, budgets, information, responsibilities, deadline of tasks, etc.(Anantatmula, 2010). Keeping track of the project progress-The necessity to monitor the project every stage is crucial to obtain the most benefit out of the project. This is done by the manager of the project. Hence, it can be concluded that the knowledge areas of the project management are essential for the practices of project management in order to achieve the desired goal of the project. The challenges that have been discussed in the report shows that any practical project will consist these three basic knowledge areas and the probable challenges. The strategies however, are essential for all types of project and effective implementation by the managers will result in gating the best result for their project. The recommendation section will benefit the manager most in developing plan in the initial stage and tracking it throughout the duration of the project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
37CONSTRUCTION PROJECT 7.Reference Ainslie, R., Donti, N., Maloney, J., Mehta, R., Subramanian, Y., & Wang, Y. (2014). Ithaca Area Wastewater Facility Treatment Engineering Managemnet Project. Al Sebeyi, R. O. A. A. (2016).An Exploration of Critical Success Factors of Virtual Distributed Projects(Doctoral dissertation, The British University in Dubai (BUiD)). Anantatmula, V. (2010). Project Manager Leadership Role in Improving Project Performance. Engineering Management Journal,22(1), 13-22. doi: 10.1080/10429247.2010.11431849 Atkinson, R., Crawford, L., & Ward, S. (2006). Fundamental uncertainties in projects and the scope of project management. International Journal Of Project Management, 24(8), 687- 698. doi: 10.1016/j.ijproman.2006.09.011 Banihashemi, S., Hosseini, M., Golizadeh, H., & Sankaran, S. (2017). Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries. International Journal Of Project Management, 35(6), 1103-1119. doi: 10.1016/j.ijproman.2017.01.014 Basari, I. (2017). Estimation Risk of High Risk Building Project on Contractor.IPTEK The Journal of Engineering,3(2). Benjaoran, V. (2009). A cost control system development: A collaborative approach for small and medium-sized contractors. International Journal Of Project Management, 27(3), 270- 277. doi: 10.1016/j.ijproman.2008.02.004 Binder, J. (2016).Global project management: communication, collaboration and management across borders. Routledge.
38CONSTRUCTION PROJECT Bresler, L., & Stake, R. E. (2017). Qualitative research methodology in music education. Critical Essays in Music Education(pp. 113-128). Routledge. Brown, S. J. (2015).A SCM approach to project management in the South African construction industry(Doctoral dissertation, Stellenbosch: Stellenbosch University). Corvello, V., Javernick-Will, A., & Ratta, A. M. L. (2017). Routine project scope management in small construction enterprises.International Journal of Project Organisation and Management,9(1), 18-30. Dandage, R., Mantha, S., Rane, S., & Bhoola, V. (2017). Analysis of interactions among barriers in project risk management. Journal Of Industrial Engineering International, 14(1), 153- 169. doi: 10.1007/s40092-017-0215-9 Evju, M., & Mai, N. B. N. (2014).How clients influence building projects-a comparison of the construction industry and the petroleum industry in Norway(Master's thesis, University of Stavanger, Norway). Fletcher, A. J. (2017). Applying critical realism in qualitative research: methodology meets method.International Journal of Social Research Methodology,20(2), 181-194. Girma, A. (2018).The Role Of Maintenance, Repair And Overhaul Supply Chain Integrationand Inventory Managemnet In Flight Dispatch Reliablity; The Case Of Ethiopian Airlines (Doctoral dissertation, aau). Hamad, Y., Burhanuddin, M. A., Ghani, A., Khanapi, M., Elzamly, A., & Doheir, M. (2019). Identifying Critical Factors to Adopt E-HRM Based Cloud Computing System for Healthcare Organizations.International Journal of Advanced Science and Technology, 28(8), 30-46. Harris, E. (2017).Strategic project risk appraisal and management. Routledge.
39CONSTRUCTION PROJECT Harrison, F., &Lock,D.(2017).Advancedprojectmanagement:astructuredapproach. Routledge. Heravi, G., & Gholami, A. (2018). The Influence of Project Risk Management Maturity and Organizational Learning on the Success of Power Plant Construction Projects.Project Management Journal,49(5), 22-37. doi: 10.1177/8756972818786661 Hopkinson,M.(2017).Theprojectriskmaturitymodel:Measuringandimprovingrisk management capability. Routledge. Huemann, M. (2016). Managing the project-oriented organization. InGower Handbook of Project Management(pp. 493-506). Routledge. Humphries, B. (2017).Re-thinking social research: anti-discriminatory approaches in research methodology. Routledge. Hysa, B., & Spalek, S. (2019). Opportunities and threats presented by social media in project management. Heliyon, 5(4), e01488. doi: 10.1016/j.heliyon.2019.e01488 Ifeanyi, E. (2019). Quantitative Approach to Project Scope Change Management in Building Projects.Retrievedfrom https://pmworldlibrary.net/wp-content/uploads/2019/05/PMWJ81-May2019-Ifeanyi- quantitative-approach-to-project-scope-change-management.pdf Javernick Will, A., La Ratta, A., & Corvello, V. (2017). Routine project scope management in smallconstructionenterprises.InternationalJournalOfProjectOrganisationAnd Management,9(1), 18. doi: 10.1504/ijpom.2017.10003939 Kerzner, H. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kliem, R. L., & Ludin, I. S. (2019).Reducing project risk. Routledge.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
40CONSTRUCTION PROJECT Lock, D. (2017).The essentials of project management. Routledge. MATAWAL, M. E. (2018). THE ROLE OF MEDIA IN CONFLICT MANAGEMNET (A CASE STUDY OF JOS NORTH LOCAL GOVERNMENT AREA OF PLATEAU STATE). Meikandasivam, S., Vijayakumar, D., & Priya, D. (2017, April). An analysis of cost efficiency on home appliances using smart power distribution. In2017 Innovations in Power and Advanced Computing Technologies (i-PACT)(pp. 1-4). IEEE. Moayeri, V., Moselhi, O., & Zhu, Z. (2016). Design change time ripple effect analysis using a bim-based quantification model. InConstruction Research Congress 2016(pp. 28-36). Napier, N., Keil, M., & Tan, F. (2009). IT project managers' construction of successful project management practice: a repertory grid investigation.Information Systems Journal,19(3), 255-282. doi: 10.1111/j.1365-2575.2007.00264.x Nawaz, A., Waqar, A., Shah, S. A. R., Sajid, M., & Khalid, M. I. (2019). An innovative frameworkforriskmanagementinconstructionprojectsindevelopingcountries: Evidence from Pakistan.Risks,7(1), 24. Nayak,V.M.(2014).TIMEISMONEYMANAGEMNET-AFEWTECHNIQUESTO MANAGE IT EFFECTIVELY. Nguyen, T. S., & Mohamed, S. (2018). Stakeholder management in complex projects. InThe 7th World Construction Symposium 2018: Built Asset Sustainability: Rethinking Design, Construction and Operations(pp. 497-506). Nicholas, J. M., & Steyn, H. (2017).Project management for engineering, business and technology. Routledge.
41CONSTRUCTION PROJECT Nielsen, L., & Faber, M. H. (2017). Survey and Design of Master Level Programs in Disaster Risk Management. In1 st International Symposium K-FORCE 2017(pp. 230-247). Higher Education Technichal School of Professional studies and University of Novi Sad, Faculty of Technical Sciences. Olawale, Y., & Sun, M. (2015). Construction project control in the UK: Current practice, existing problems and recommendations for future improvement. International Journal Of Project Management, 33(3), 623-637. doi: 10.1016/j.ijproman.2014.10.003 Piercy, N. F. (Ed.). (2018).The Management implications of new information technology(Vol. 41). Routledge. Pourzolfaghar, Z., & Ibrahim, R. (2014). Impacts of adding knowledge flow to an activity-based framework for conceptual design phase on performance of building projects.Electronic Journal of Knowledge Management,12(3), 166. Quinlan, C., Babin, B., Carr, J., & Griffin, M. (2019).Business research methods. South Western Cengage. Raman, K. V., Dayakar, P., Venkatkrishniah, D. R., & Mani, D. A. (2019). Study on Time and Cost Management in Construction.International Journal of Civil Engineering and Technology,10(3). Ridwan, A., & Poespowidjojo, D. A. L. (2017). The New Effective Model of Financing Without Providing Collateral and Free of Risk for Developing Small and Medium Enterprises. International Journal of Economic Research,14(15 (2)), 23-34. Silverman, D. (Ed.). (2016).Qualitative research. Sage. Smith, P. (2014). Project Cost Management – Global Issues and Challenges.Procedia - Social And Behavioral Sciences,119, 485-494. doi: 10.1016/j.sbspro.2014.03.054
42CONSTRUCTION PROJECT Sols,A.(2018).AComprehensiveApproachtoDynamicProjectRiskManagement. EngineeringManagementJournal,30(2),128-140.doi: 10.1080/10429247.2018.1450030 Suh, D. S., & Kim, Y. J. (2016). A study on priority of policy for smart farming system using AHP approach.Journal of the Korea Academia-Industrial cooperation Society,17(11), 348-354. TOMAIZEH, M. M. D. (2016). VARIATIONS OF OWNER'S ESTIMATED QUANTITIES FOR HIGHWAY PROJECTS IN UNIT PRICE CONTRACTS IN SAUDI ARABIA. Tomomitsu, H., Carvalho, M., & Moraes, R. (2018). The evolution of the relationship between projectmanagementandknowledgemanagement:a bibliometricstudy.Gestão& Produção,25(2), 354-369. doi: 10.1590/0104-530x3150-16 Tonchia,S.(2018).ProjectCostManagementandFinance.InIndustrialProject Management(pp. 153-170). Springer, Berlin, Heidelberg. WEKESA,E.W.(2016).InfluenceofStrategicSuccessFactorsonImplementationof InformationCommunicationTechnologyProjectsinKenyanCommercialBanks. University of Nairobi. Zain, E. N. B. M., & Ghazali, P. L. B. (2018). Non-performing loans and its implications toward Bank Performance: Comparison on Islamic and Conventional Banks.INTERNATIONAL JOURNAL OF ACADEMIC RESEARCH IN BUSINESS AND SOCIAL SCIENCES,8(12).