This document provides a comprehensive guide on ICT project management. It covers topics such as measurable organizational value, scope management plan, work breakdown structure, project risk analysis, quality management plan, and more. The document also includes a table of contents, milestones, and project budget.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: ICT PROJECT MANAGEMENT ICT Project Management Name of Student Name of University Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 ICT PROJECT MANAGEMENT Table of Contents Part 1: MOV- Measurable Organisational Value................................................................3 1.1. Project Description...................................................................................................3 1.2. Desired Area of Impact.............................................................................................3 1.3. Identified Project Value............................................................................................3 1.4. Stakeholders’ Expectations and Target....................................................................4 1.4. Set Timeline for MOV..............................................................................................5 1.5. Summary of the MOV..............................................................................................5 Part 2: Scope and Scope Management Plan....................................................................6 2.1. Scope of the Project..................................................................................................6 2.2. List of Resources in the Project................................................................................6 Part 3: Work Breakdown Structure (WBS).........................................................................7 3.1. Work Breakdown Structure for TAHS.....................................................................7 3.2. Deliverable and Milestone and Project budget.......................................................10 Part 4: Project Risk Analysis and Plan..............................................................................15 4.1. Project Assumptions...............................................................................................15 4.2. Risk and Risk Mitigation Plan................................................................................15 Part 5: Quality Management Plan......................................................................................16 5.1. Team’s Objective....................................................................................................16 5.2. Verification Activities............................................................................................16
3 ICT PROJECT MANAGEMENT Part 1: MOV- Measurable Organisational Value 1.1. Project Description The Globex firm has more than 30 years of experience in business related to agriculture. The company has embarked on a mission of providing training to the high school students (TAHS) regarding agricultural business so that the can easily secure a job. For the same, a computer based system for management of the Training and Apprenticeship program for the high school students. The project is to develop the computer based system. The project is undertaken by Virtucon, a client of Globex Corporation. 1.2. Desired Area of Impact Strategy:The development of the computer based system is likely to manage the training program more efficiently. Customer:The system will be beneficial for the customers as it eliminates the need of any manual record keeping. Financial:The system is expected to work for the profit of Globex Corporation Operational:The project is undertaken by Virtucon and is expected to have a high operational output. Social:The training program is expected to help the High school students in securing a good job. 1.3. Identified Project Value
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 ICT PROJECT MANAGEMENT Value Impact Area Better(Ona scale of 1 to 5) Faster(Ona scale of 1 to 5) Cheaper (On a scale of 1 to 5) Do More(Ona scale of 1 to 5) Customer2242 Strategy3444 Operational3444 Social2533 Financial4553 1.4. Stakeholders’ Expectations and Target StakeholdersExpectationsTarget Kashish Bawa (Project manager)Appropriatemanagement of the project To ensure project is completed within the time specified Aarish khan (System Designer)This stakeholder is expected to prepare the design of the student Todevelopadesignasper specifications GurvinderKaur(Business analyst) This stakeholder is expected to analyse the business profitability To assist in appropriate project development Saloni (Developer)This stakeholder is expected toCodingthecomputerbased
5 ICT PROJECT MANAGEMENT contribute in project codingsystem as per specifications Deepjot Kaur (Tester)This stakeholder is expected to test the software developed Toensurethataworking software is delivered. Globex RepresentativeThis stakeholder is expected to ensurethattheprojectis completed according to the set specifications To provide needed guidance 1.4. Set Timeline for MOV 1.5. Summary of the MOV MOVDescription Area of ImpactThedesiredareaofimpactoftheprojectis identifiedonbasisofstrategy,customers, operation, financial and society. Project ValueThe values of the project is identified. A high performance and low budget system is needed to be developed.
6 ICT PROJECT MANAGEMENT Stakeholder’s ExpectationThe expectations and the target of the stakeholders are identified. Time Required for MOV266 Days Part 2: Scope and Scope Management Plan 2.1. Scope of the Project The TAHS project scopes are as follows- Development of the a well functional computer based system for TAHS Management of the entire development process Execution of the project in a low cost The out of scope requirements of the project are as follows- The project does not incorporate training The project should not be delayed 2.2. List of Resources in the Project
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 ICT PROJECT MANAGEMENT Part 3: Work Breakdown Structure (WBS) 3.1. Work Breakdown Structure for TAHS
8 ICT PROJECT MANAGEMENT
9 ICT PROJECT MANAGEMENT TAHS Computer-Based System Project StartsPlanning Phase Meeting With Globex Specification identification Requirements Gathering Sharing the Documents with Globex for Approval Development of a Project Plan Milestone 1: Approval of Project Plan Inititaion Phase Development of the Project Schedule as per plan Development of Project Budget Approval of Schedule and Budget of the Project Development of Project Charter Milestone 2: Approval of Project Charter Execution Phase Design Phase Designing the Interface of the Software Finalization of the graphical designs Coding Coding the Software Database Coding Linking the software with the Database Milestone 3: Completion of Project Coding and Linking with Database Testing Phase System Testing of the Software Beta Testing User Acceptance Testing Identification of Bugs in the System Fixing the Bugs Milestone 4: Completion of Software Testing Evaluation Phase Validation of the Software Developed Checking if the Project is able to meet the requirements specified Verification of the specification Milestone 5: Detailed Project Documentation Closure Phase Payment Completion Client Sign Off Resource Release Documentation Milestone 6: Project Completion Figure 1: Work Breakdown of TAHS Computer based system Project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13 ICT PROJECT MANAGEMENT Off13- 01-2001-20 7.3Resource Release7 days Mon 20- 01-20 Tue 28-01- 20 38Resource Manager$2,016.00 7.4Documentation3 days Wed 29- 01-20 Fri 31- 01-2039Writer$360.00 7.5 Milestone 6: Project Completion 0 days Fri 31- 01-20 Fri 31- 01-2040Globex ,Project manager$0.00 In the table above, the milestones are marked in red. The schedule Gantt Chart for TAHS computer based system is as follows-
14 ICT PROJECT MANAGEMENT
15 ICT PROJECT MANAGEMENT Part 4: Project Risk Analysis and Plan 4.1. Project Assumptions The major assumptions associated with the implementation of this project are as follows- ï‚·An efficient communication is ensured among the project team members, so that the issues associated with the project are effectively shared with the stakeholders ï‚·It is assumed that the resources assigned in the project will be easily available 4.2. Risk and Risk Mitigation Plan The risk and their mitigation plan is evaluated in the table below- RiskDescriptionProbabilityImpactRisk OwnerRisk Response Resource Unavailability Theallocated resourcesis insufficient MediumHighResource manager Theresource assignment shouldbe appropriate Technical faultTheComputer based system is incompatible HighHighTechnical Manager, Coder Technical manageris expectedto supervisethe development process Schedule RiskThetime allocatedis insufficient MediumHighProject manager Appropriate timeis allocated
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16 ICT PROJECT MANAGEMENT Budget RiskThebudget allocatedis insufficient HighMediumProject Manager An appropriate budgetis proposed Communicatio n Issues Inappropriate communication channel leadingto communication issues LowLowProject Manager A communication planis developed Part 5: Quality Management Plan 5.1. Team’s Objective The project team aims in completing the project is a low cost. The computer based system that is to be developed should be of high functionality. 5.2. Verification Activities The verification activities include appointment of a supervisor to examine each and every phases of project development to ensure that the project is following the specified requirements. 5.3. Validation Activities The validation activities include testing of the software at the end of the development phase to ensure that the required functionality of the system is achieved. Part 6: Closure and Evaluation
17 ICT PROJECT MANAGEMENT The project closure and evaluation is the last stage of project development lifecycle. The project evaluation phase is important as it validates and verifies the specifications of the project (refer to appendix). 6.1. Project Closure Checklist The project closure checklist for the TAHS computer based projects are as follows- Checklist ItemsResponse (Yes/No) Has the project covered all specifications?Yes Has the project been completed with the assigned resources? Yes Has the project been completed within the time allocated? Yes Is the software tested before release?Yes Have the feedbacks been collected?Yes Is the project evaluation stage completed?Yes 6.2. Project Evaluation The MOV of the project will be evaluated by analysing the extent to which the project is able to fulfil its goals. The project evaluation will be done at the end of the project. It is the responsibility of the project manager to evaluate the MOV of the project.
18 ICT PROJECT MANAGEMENT Bibliography Davis,K.(2014).Differentstakeholdergroupsandtheirperceptionsofproject success.International journal of project management,32(2), 189-201. Ensslin, S. R., Ensslin, L., de Oliveira Lacerda, R. T., & de Souza, V. H. A. (2014). Disclosure ofthestateoftheartofperformanceevaluationappliedtoproject management.American Journal of Industrial and Business Management,4(11), 677. Harrison, F., &Lock,D.(2017).Advancedprojectmanagement:astructuredapproach. Routledge. Heagney, J. (2016).Fundamentals of project management. Amacom. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kostalova, J., Tetrevova, L., & Svedik, J. (2015). Support of project management methods by project management information system.Procedia-Social and Behavioral Sciences,210, 96-104. Marchewka, J. T. (2014).Information technology project management. John Wiley & Sons.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19 ICT PROJECT MANAGEMENT Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Nicholas, J. M., & Steyn, H. (2017).Project management forengineering, business and technology. Routledge. Xu, Y., & Yeh, C. H. (2014). A performance-based approach to project assignment and performance evaluation.International Journal of Project Management,32(2), 218-228.
20 ICT PROJECT MANAGEMENT Appendix Davis,K.(2014).Differentstakeholdergroupsandtheirperceptionsofproject success.International journal of project management,32(2), 189-201. According to Davis, (2014), a particular group of stakeholders might have different perception to project’s success. As per the views of the different stakeholders group, the project’s success is based on a number of factors. One of such factors is appropriate project evaluation. Project success is important for its implementation and the works associated with ensuring the project success is considered to be project based works. There are a number of reasons behind the failure of a project which are needed to be evaluated in order to understand the reason behind the project success.According to Davis, (2014), quality is an important factor behind the project’s success and therefore, it becomes a necessity to make sure that a particular project is being implemented with an appropriate quality. Apart from that, team collaboration becomes an essential aspect of ascertaining that a project is successful. Apart from that, it is the responsibility of the entire team to ascertain that an appropriate quality of project is received. While leading a project, the project manager is required to be certain that the project that is being implemented is actually fulfilling the given specification. This is validated in the project evaluation phase and therefore, this phase of project implementation is important. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalof project management,32(2), 202-217.
21 ICT PROJECT MANAGEMENT According to Mir & Pinnington, (2014), the success of project management is linked with the performance of project management. One critical aspect of project management is project evaluation. It has been observed that several business organizations are making use of the different project management tools with an aim of increasing the business profit. Following an appropriate project management process, ascertains that any project is implemented as per the desired specifications. Therefore, it can be concluded that the project evaluation is needed to ascertain that specific project quality is achieved. The factors behind success of a project differ mainly because the project differ in size, complexity and uniqueness. Therefore, the factors behind the success of the project differs as well. However, the evaluation phase of the project remains constant for each and every project as it validates the specifications and objectives of the project. In this research paper, the author identifies a number of alternative frameworks related to measurement of project success. These frameworks include the need of ensuring that the project that is being implemented matches the specifications provided by the client. Therefore, it is necessary to ascertain that the project is following appropriate project management methods for project completion. Xu, Y., & Yeh, C. H. (2014). A performance-based approach to project assignment and performance evaluation.International Journal of Project Management,32(2), 218- 228. According to Xu & Yeh, (2014), project assignment and project evaluation is considered to be two major issues related to management of a project. A project is associated with fulfilling the objectives and the specifications of the client. In doing so, project evaluation becomes a necessity. An organization based project aims in fulfilling the objectives of the organization. The extent to which an organization is able to fulfil the required objective of the project is determined
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22 ICT PROJECT MANAGEMENT in the project evaluation phase. Therefore, this particular phase of project implementation holds a lot of importance in management of a project. The research report indicates that project evaluation phase has a significant contribution in successful management of a project. The performanceevaluationphaseoftheprojecthelpsinaccuratelyassessingtheactual achievements and the issues related to a project.