Project-Risk Assessment and Project Schedule

   

Added on  2023-05-28

13 Pages1498 Words69 Views
1
Running head: PROJECT-RISK ASSESSMENT AND PROJECT SCHEDULE
PROJECT-RISK ASSESSMNET AND PROJECT SCHEDULE
Leonid Akbashev
Purdue Global
Project-Risk Assessment and Project Schedule_1
2
ASSIGNMENT 4: PROJECT-RISK ASSESSMENT AND PROJECT SCHEDULE
Table of Contents
Updated WBS..................................................................................................................................3
Risk Assessment Document..........................................................................................................12
Likelihood..................................................................................................................................12
Severity......................................................................................................................................12
Risk Assessment Matrix.............................................................................................................13
Reference List................................................................................................................................15
Appendices....................................................................................................................................16
Appendix 1: Resource Graph for the networking project..........................................................16
Project-Risk Assessment and Project Schedule_2
3
ASSIGNMENT 4: PROJECT-RISK ASSESSMENT AND PROJECT SCHEDULE
Updated WBS
This WBS is linked to the developed WBS in the previous unit. In this segment, the
learner has established a more detailed WBS with the description and responsibilities of each
activity. According to Heagney (2016), a detailed WBS ensures successful completion of any
project. Hence, the following WBS reflects on detailed aspects of this networking project.
[Referred to Appendix 1]
Project Roles Names Initials
Web designer Lara Dom LD
Networking Specialist Dixie Xang DX
Web developer Paul Oberoy PO
Project Manager Suzan Diane SD
Human resource Heymond Rian HR
Project Team members Luis Oracle, Matt Taylor,
Pollard Shaun, Sian Gon
LO, MT, PS, SG
Task Name Duration Start Finish Predecessors Cost Resource Initials
Network
designing
Project
211
days
Wed
02-01-
19
Wed 23-
10-19
$70,138.00
Project
Planning
30 days Wed
02-01-
Tue 12-02-
19
$5,000.00 HR,PO,SD,DX,LD
Project-Risk Assessment and Project Schedule_3
4
ASSIGNMENT 4: PROJECT-RISK ASSESSMENT AND PROJECT SCHEDULE
19
Gathering
resources
15 days
Wed
02-01-
19
Tue 22-01-
19
$3,000.00 HR
Identification
of network design
specification
10 days
Wed
23-01-
19
Tue 05-02-
19
3 $1,000.00 PO
Assigning
professionals
5 days
Wed
06-02-
19
Tue 12-02-
19
4 $1,000.00 SD
Analysis Phase 97 days
Thu 14-
02-19
Fri 28-06-
19
$29,796.00
DX,LD,LO,MT,PO,
PS,SD,SG
Network
Flow Analysis
5 days
Thu 14-
02-19
Wed 20-
02-19
$4,000.00 SG
Network
Mapping
15 days
Thu 21-
02-19
Wed 13-
03-19
7 $5,000.00 PO
Network
Characterization
18 days
Thu 14-
03-19
Mon 08-
04-19
8 $4,500.00 SD
Network
Sampling
4 days
Tue 09-
04-19
Fri 12-04-
19
9 $3,254.00 DX,SD
Network
Modeling
3 days Mon
15-04-
Wed 17-
04-19
10 $1,469.00 LD,LO
Project-Risk Assessment and Project Schedule_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Boeing's Supersonic Commercial Planes
|5
|583
|392

Project Management: Time Inc.
|16
|2347
|145

ICT Project Management
|20
|2439
|276

Business Project Management
|7
|1291
|18

Project Progress Report 13 Project Scheduling: Network Diagram Activity Data
|15
|1200
|349

Project Management: Benefits Administration Software
|4
|811
|299