Melbourne Global Music Festival: Project Management Plan

   

Added on  2023-06-11

13 Pages1897 Words53 Views
Running head: MELBOURNE GLOBAL MUSIC FESTIVAL
Melbourne Global Music Festival
Name of the student:
Name of the university:
Author Note
Melbourne Global Music Festival: Project Management Plan_1
1MELBOURNE GLOBAL MUSIC FESTIVAL
Discussion on scope of project management plan on Melbourne Global Music
Festival:
1. Objective of project:
The objective of the project of Melbourne global music festival entertainment international
private lies in the following facts.
To bring different indigenous music group together from various nations at Melbourne
To promote the musical culture, appreciate musical cultures, share experiences from various
communities.
To assure that the project is done under schedule and budget with the risks being managed
and tasks being monitored.
To develop an event where the festival includes bands, adults and youth orchestras.
Melbourne Global Music Festival: Project Management Plan_2
2MELBOURNE GLOBAL MUSIC FESTIVAL
2. Timeline of the project:
Project Leader or Manager: ALPN Group
Anticipated Project Start Date: 16th February 2018
Sponsors: Commonwealth Banks, Victoria community, Victoria Anticipated, Victoria multicultural
society
Project End Date: 25.5.18
This is demonstrated through the following table.
Task Name Duration Start Finish Predecessors
Phase 1 12 days Fri
2/16/18
Tue
3/20/18
Conducting survey around Melbourne to
collect data about how to process with the
plan
2 days Fri
2/16/18
Mon
2/19/18
Initiating project plan for Melbourne
Global Music Festival
2 days Tue
2/20/18
Wed
2/21/18
2
Schedule time for project manager 2 days Fri
2/16/18
Mon
2/19/18
Identification of communication medium
for reaching desires ensembles
2 days Thu
2/22/18
Fri
2/23/18
3
Determining possible participants and
starting initial communication
2 days Mon
2/26/18
Tue
2/27/18
5
Phase 2 10 days Tue Mon 6
Melbourne Global Music Festival: Project Management Plan_3
3MELBOURNE GLOBAL MUSIC FESTIVAL
6/12/18 6/25/18
Securing the event funding 2 days Wed
2/28/18
Thu
3/1/18
Approaching the event sponsors 2 days Fri
3/2/18
Mon
3/5/18
8
Finding the budget for various global
bands like logistics and transportation
2 days Tue
3/6/18
Wed
3/7/18
9
Leasing security services for proving
security
2 days Thu
3/8/18
Fri 3/9/18 10
Creating project budget 2 days Mon
4/9/18
Tue
4/10/18
11
Phase 3 43 days Tue
2/27/18
Thu
4/26/18
Creating official invitations and various
confirmation of the ensembles and groups
for attending this event
2 days Wed
4/11/18
Thu
4/12/18
12
Scheduling time for singers (arrival and
departuture)
1 day Tue
2/27/18
Tue
2/27/18
Arranging accommodation for obtaining
and band rates
3 days Fri
4/13/18
Tue
4/17/18
14
Placing adverts for events in different
media
2 days Wed
4/18/18
Thu
4/19/18
16
Melbourne Global Music Festival: Project Management Plan_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Tasks 2022
|4
|382
|15

Project Management for Music Event: Stakeholder Analysis, Risk Analysis, and Communication Strategies
|17
|2773
|60

Gantt Chart of Software Training Program_modified | Desklib
|2
|579
|69

Project Management Assignment 3: Unit Project Part B
|29
|4746
|459

Gantt Chart Project Management Project Management Name of the University Schedule
|8
|960
|443

Construction Project Management Assignment
|12
|1544
|89