Mobile Application Development Example – Communications Planv1.0.1 Page1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10.Integrated Change Control 10.1 Change Control Narrative Change control is known as some systematic approach that is used to manage the changes that are made in a product or in a system. The main purpose of change control is ensuring the there is no change in the project and the changes that are made are documented in the project document. With the change in a project, the delivery or the service is not generally gets affected and there is efficient use of resource. There are some basics steps that are to be followed while carrying out a change control in a project. The change control processes are shown in the figure below. 10.2 Project Change Control Narrative The change control is done in this particular project is increasing the cost of the project by 10% and for that the time schedule of the project is also increased by 10 %. The project manager has tried to control the change in this project by documenting all the changes that happens in the project. The stakeholder who is responsible for the change in the project for developing the mobile application is the system developer. The system developer has to responsibility to carry out the project and complete the testing in the changed schedule and make the project to be successful one. As increasing the total number of days will also increase the total budget of the project and there might be a shortage of contingency resource that is available for the project. The change control template is shown in the below section that defines all the changes that takes place in the project. Example – Communications Planv1.0.1 Page3
10.3 Project Change Control Flowchart There are five steps that are implemented in a change control that shows the five steps that re to be carried out. The first step is change request that states requesting the change that is to be undertaken in a project, the impact of the change is analyzed in the second step. The third step includes approval of the change from the project team leader or the project manager. after the changes gets approved, the change is implemented in the project and lastly, the change is documented and reviewed for future use. Figure 1: ChangeChange Control plan and process diagram (Source: Created by Author) Example – Communications Planv1.0.1 Page4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10.4 Project Change request Form Template Change Request Project: Mobile Application DevelopmentDate: Change Requestor: System DesignerChange No: Change Category (Check all that apply): □Schedule□Cost□Scope□Requirements/Deliverables □Testing/Quality□Resources Does this Change Affect (Check all that apply): □Corrective Action□Preventative Action□Defect Repair□Updates □Other Example – Communications Planv1.0.1 Page6
Describe the Change Being Requested: The system designer request the project manager to increase the time of the project because the system designer needs time to test the unit of the application that is being built. Describe the Reason for the Change: There is a need of unit testing while developing the android application for the bank. So, the change request is to be initiated. Describe all Alternatives Considered: The alternatives that are to be considered are testing each unit of the application. Describe any Technical Changes Required to Implement this Change: Technical change required is changing the time schedule of the project. Describe Risks to be Considered for this Change: Increase the cost of the project. Estimate Resources and Costs Needed to Implement this Change: The cost of the project will increase. Example – Communications Planv1.0.1 Page7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Describe the Implications to Quality: The quality of the project will not change as testing will be required for increasing the quality pf the project. Disposition: □Approve□Reject□Defer Justification of Approval, Rejection, or Deferral: This is justified as testing phase will increase the quality of the project. Example – Communications Planv1.0.1 Page8