Online Booking Solution Project Charter & Plan

Develop an online booking solution for a medium-sized car rental company to effectively manage their car inventory, bookings, and billing information.

18 Pages3367 Words368 Views
   

Added on  2023-06-07

About This Document

This report includes the project charter and project plan for an online booking solution for a car rental company. It covers project background, scope, objectives, business problem/opportunity, information gathering activities, detailed project plan, project schedule, project budget, project roles & responsibilities, risk management plan, quality management, quality assurance & control, communication plan & procedures, disaster recovery plan, maintenance/support plan, and sign-off form.

Online Booking Solution Project Charter & Plan

Develop an online booking solution for a medium-sized car rental company to effectively manage their car inventory, bookings, and billing information.

   Added on 2023-06-07

ShareRelated Documents
Project Charter & Plan
Online Booking Solution Project Charter & Plan_1
Online Booking Solution
Table of Contents
Introduction...........................................................................................................................................2
Project Charter.......................................................................................................................................2
Project Background...........................................................................................................................2
Project Scope.....................................................................................................................................2
Project Objectives..............................................................................................................................2
Business Problem/Opportunity..........................................................................................................3
Charter Sign-Off................................................................................................................................3
Information Gathering Activities...........................................................................................................3
Interviews..........................................................................................................................................3
Domain Analysis...............................................................................................................................3
Observations......................................................................................................................................4
Group Discussions.............................................................................................................................4
Detailed Project Plan.............................................................................................................................4
Work Breakdown Structure...............................................................................................................4
Project Schedule................................................................................................................................5
Project Budget...................................................................................................................................6
Project Roles & Responsibilities...........................................................................................................7
Risk Management Plan..........................................................................................................................8
Quality Management...........................................................................................................................10
Quality Assurance & Control..........................................................................................................10
Communication Plan & Procedures.....................................................................................................11
Disaster Recovery Plan........................................................................................................................14
Maintenance/Support Plan...................................................................................................................15
Sign-off Form......................................................................................................................................15
References...........................................................................................................................................16
References...........................................................................................................................................16
Online Booking Solution Project Charter & Plan_2
Online Booking Solution
Introduction
Project management is one of the necessary disciplines that are required to be followed and
implemented in the projects for project success. There are various deliverables that a project
team needs to provide as a part of the project management process. Project charter and
project plan are the two deliverables that are provided in the initiation and planning phases
and set up the base of the project. The charter and project plan for an online booking solution
for a car rental company are included in the report.
Project Charter
Project Background
The project is being developed for a medium sized car rental company. The company
provides its customers with the car and truck rental services and operates in three different
locations. The company currently has a total of 35 vehicles available for rent. The
organization is looking to expand in the other locations and there will be an online booking
solution needed with the expansion of the business.
Project Scope
The project scope will cover the following activities for the online booking solution:
Initiation and planning activities for the online booking solution covering feasibility
estimation, estimations, and planning of the project areas.
Design, development, and implementation of the online solution (Atkin, 2012).
Testing and change management of the solution.
Quality, communication, and risk planning & management for the solution.
Deployment of the system and conduction of the closure processes and activities.
Project Objectives
To provide the customers with the ability to book and track their vehicles using the
online medium.
To provide the company resources with the ability to keep a track of and manage the
bookings.
To allow the customers to check the availability of the vehicles for offering them the
ease of service and operations.
Online Booking Solution Project Charter & Plan_3
Online Booking Solution
To allow the customers to make payments for the bookings for enhanced customer
engagement and satisfaction.
Business Problem/Opportunity
The medium sized car rental company is looking to expand in the other locations and there
will be an online booking solution needed with the expansion of the business. The absence of
the online solution will lead to difficulty in manage the bookings and the customer
engagement levels may also come down. However, the implementation of the online solution
will allow the company to enhance its customer engagement levels and gain competitive
advantage in the market (Ahmad, 2012).
Charter Sign-Off
Date of Submission Date
Submitted By Project Manager Name
Submitted To Name of the Stakeholder
Signature of the Stakeholder Signature
Comments by the Stakeholder Comments on the project charter submitted
List of Changes to be Made Details and names of changes to be made to the charter
Sign-off/Approval Status Status of the approval of the charter
Plan of Action Follow-up actions
Information Gathering Activities
Interviews
The technique will involve the identification of the stakeholders and candidates to be
interviewed for the online booking solution. The interview questions will then be prepared in
a formal document for each of the candidate or stakeholder group. The conduction of the
interviews will be done in which the candidates will be asked the questions and their response
will be recorded through automated recoding tools. The analysis of the response provided by
the stakeholders will be made.
Online Booking Solution Project Charter & Plan_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
(PDF) Revenue management in the car rental industry
|7
|1990
|267

The Learning Communities LC-01A) building will go through
|2
|428
|150

(PDF) Online Car Rental System
|20
|2862
|884

Drive Through Super Markets
|25
|5448
|496

Implementation of Cloud Based Integrated System in Star Car Rentals
|10
|720
|366

Project Management Plan for Learning Communities (LC01A) Building
|21
|2825
|444