Developing Online Study Farm Management System

   

Added on  2023-06-12

13 Pages2478 Words270 Views
 | 
 | 
 | 
ID Developing Online Stud
Farm Management
System
Developing Online Study Farm Management System_1

1. Part One
1. 1 MOV - Measurable Organisational Value
Ranking Area of Impact
1 Customer Satisfaction
2 Social value of the project will be high
3 Financial enhancement
4 Operational activities will be enhanced in an
efficient and effective manner
1.2 Project value
Following are the values that the organization can gain through the successful delivery of the project
Better: This implementation will be helpful in enhancing the quality of the services and products being
deliver to their consumers as it will be helpful I delivering faster and accurate services.
Cheaper: The developed system through successful accomplishment of this project will no doubt
enhance the productivity and output but it will also be cheaper to be implemented within the existing system.
Further the maintenance will be managed by the vendor that will also be helpful; in restricting the budget of
the proposed system.
1.3 Comparison Metric and Time Frame
Rank Area of Impact Metric Time Frame
1 Customer
Satisfaction Satisfaction level will be enhanced
through two times than present
condition
3 months
2 Social value of the
project will be high Socially feasible system will be
developed that will allow the users
feel free and in associated with the
system
2 months
3 Financial
enhancement 10% enhancement in the overall
revenue
3 months
4 Operational
activities will be
enhanced in an
efficient and
effective manner
Smooth, effective and accurate
delivery of the operational
activities will be driven through the
developed system
2 month
2. Part Two:
2.1 Scope
In-scope of the project can be listed as follows:
Increase the production and output
Allow the employees to work efficiently
Developing Online Study Farm Management System_2

Developing a database management system
Developing a sophisticated design and model fort this project delivery
Embed an attractive and easy user interface
Allowing the employees to work smoothly and accurately
Increase the customer experience and expectations
Migrate data over an online system
Mitigate the problems related to the human error and redundancy
Perform simulation testing
Deliver the project efficiently
Propose an effective and efficient solution
2.2 Out of Scope
Standard of the project
Future maintenance
2.3 Assumptions
All the drafts will be approved by the organization’s head
All the man force will contribute their hundred percent with full attendance
The activities will be accomplished within the timeline of the project
2.4 Constraints
High quality delivery of the project
Total budget of the project is $ 49,120
Total timeline of the project is 89 days
2.5 Scope Management Plan
The identified resources would be capable of delivering the project constraints
Market analyst will analyse the entire market and will propose effective solutions
The project will meet scope and objectives of the project
Proper audit and monitoring will done for the management of the project constraint
2.6 Resource Plan
Human Resources
Resource Name Std. Rate
System Analyst $20.00/hr
HR Manager $25.00/hr
Planner $20.00/hr
Designer $25.00/hr
Project Manager $25.00/hr
System Developer $20.00/hr
UI Designer $10.00/hr
Database Admin $25.00/hr
Database Vendor $10.00/hr
IT Engineer $20.00/hr
Risk Analyst $15.00/hr
Contractor $10.00/hr
Developing Online Study Farm Management System_3

Trainer $3.00/hr
Trainees $10.00/hr
Technology
Network Intranet, Internet,
Software My – SQL, software testing platform, developing platform
Hardware Storage, RAM, computer systems, routers, cables, electrical
components
Facilities
The resources will be available throughout the project lifecycle and the activities will be
delivered in an efficient and effective manner.
Other
Travel Requirements Incentives for the employees
Training Requirements For the employees
3. Part Three:
3.1 Project Milestones
Task Name Durati
on Start Finish
Online Stud Farm Management System
development 89 days Tue 5/22/18 Fri 9/21/18
Project Initiation 7 days Tue 5/22/18 Wed 5/30/18
Milestone one: draft approval 0 days Wed 5/30/18 Wed 5/30/18
Project Planning 11 days Thu 5/31/18 Thu 6/14/18
Milestone two: Charter Approval 0 days Thu 6/14/18 Thu 6/14/18
Designing proposed solution 11 days Fri 6/15/18 Fri 6/29/18
Milestone Three: Design Approval 0 days Fri 6/29/18 Fri 6/29/18
Project Execution 21 days Mon 7/2/18 Mon 7/30/18
Milestone four: Execution Completed 0 days Mon 7/30/18 Mon 7/30/18
System Deployment 39 days Tue 7/31/18 Fri 9/21/18
Milestone Five: System Development completed 0 days Mon 8/20/18 Mon 8/20/18
Developing Online Study Farm Management System_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Management System Assignment
|19
|3799
|29

Developing Online Stud Farm Management System - Project Plan
|17
|3308
|252

Online Stud Farm Management System Part One: Project Delivery Approach
|15
|2333
|249

Online Stud Farm Management System
|16
|3563
|91

Developing Online Stud Farm Management System PDF
|15
|2490
|38

Development of Online management system Assignment
|15
|2056
|27