Online Ticketing System for Riverina Agriculture and Lifestyle Show (RALS) - Project Management Plan
VerifiedAdded on 2023/06/03
|21
|2464
|355
AI Summary
The report provides a project management plan for planning, executing and monitoring the project of developing an online ticketing system for Riverina Agriculture and Lifestyle Show. PMBoK principles shall be applied to successfully complete the project. The report also includes the recommendations for future developments in the similar projects.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Assignment title
Assignment title
Student name
Student number
Lecturer details
Assignment title
Student name
Student number
Lecturer details
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Executive summary
Globex organization aims a developing an online ticketing system for Riverina Agriculture and
Lifestyle Show. The current system faces considerable number of issues due to manual processing of
managing tickets. Along with this, manual system makes it difficult for the exhibitors to manage
ticket booking. In order to avoid human mistakes, Globex decided to develop an online system for
booking tickets for the show. The report provides a project management plan for planning,
executing and monitoring the project. PMBoK principles hall be applied to successfully complete the
project. Also, the report presents the recommendations for future developments in the similar
projects.
1
Globex organization aims a developing an online ticketing system for Riverina Agriculture and
Lifestyle Show. The current system faces considerable number of issues due to manual processing of
managing tickets. Along with this, manual system makes it difficult for the exhibitors to manage
ticket booking. In order to avoid human mistakes, Globex decided to develop an online system for
booking tickets for the show. The report provides a project management plan for planning,
executing and monitoring the project. PMBoK principles hall be applied to successfully complete the
project. Also, the report presents the recommendations for future developments in the similar
projects.
1
Table of Contents
Title.......................................................................................................................................................3
Start date...............................................................................................................................................3
End date................................................................................................................................................3
Goals and objectives..............................................................................................................................3
Project plan...........................................................................................................................................3
Project scope.....................................................................................................................................3
Constraints........................................................................................................................................4
Functional requirements...................................................................................................................4
Non-functional requirements............................................................................................................4
Work Breakdown Structure...............................................................................................................5
Time estimation................................................................................................................................6
Project resources..............................................................................................................................7
Gantt chart........................................................................................................................................7
Network diagram..............................................................................................................................8
Cost estimation...............................................................................................................................10
Quality plan.....................................................................................................................................11
Stakeholder analysis........................................................................................................................12
Communication plan.......................................................................................................................14
Risk management plan....................................................................................................................15
Risk assessment..........................................................................................................................15
Risk Mitigation............................................................................................................................16
Deployment plan.............................................................................................................................17
Project sign off.....................................................................................................................................17
Conclusion...........................................................................................................................................18
Post project review and recommendations.......................................................................................18
References...........................................................................................................................................20
2
Title.......................................................................................................................................................3
Start date...............................................................................................................................................3
End date................................................................................................................................................3
Goals and objectives..............................................................................................................................3
Project plan...........................................................................................................................................3
Project scope.....................................................................................................................................3
Constraints........................................................................................................................................4
Functional requirements...................................................................................................................4
Non-functional requirements............................................................................................................4
Work Breakdown Structure...............................................................................................................5
Time estimation................................................................................................................................6
Project resources..............................................................................................................................7
Gantt chart........................................................................................................................................7
Network diagram..............................................................................................................................8
Cost estimation...............................................................................................................................10
Quality plan.....................................................................................................................................11
Stakeholder analysis........................................................................................................................12
Communication plan.......................................................................................................................14
Risk management plan....................................................................................................................15
Risk assessment..........................................................................................................................15
Risk Mitigation............................................................................................................................16
Deployment plan.............................................................................................................................17
Project sign off.....................................................................................................................................17
Conclusion...........................................................................................................................................18
Post project review and recommendations.......................................................................................18
References...........................................................................................................................................20
2
Title
Ticketing System for Riverina Agriculture and Lifestyle Show (RALS)
Start date
1st November 2018
End date
29th January 2019
Goals and objectives
Following are key goals and objectives of proposed online ticketing system of RALS:
The exhibitors will be able to book exhibition sites through online medium.
The facility will be able to book tickets through mobile phone also.
The proposed online system will be able to allow end users to reduce manual mistakes in
RALS work.
The online system ticket and entry passes have a barcode to conduct verification and
validation of exhibition sites.
Project plan
Project scope
In Scope Includes
System Functions Ability to allow RALS users to manage tickets online i.e.
users will be able crate a booking, cancel a booking and
update booking through online system.
Ability to demonstrate system qualities such as
usability, reliability, scalability and availability.
Ability to ensure that only authorized users are allowed
to access the online site to make any changes in the
system such as booking tickets, etc.
System Documentation Project charter
Security plan report
User manual
Implementation plan
Closure reports
Training Staff shall be provided training to understand the
3
Ticketing System for Riverina Agriculture and Lifestyle Show (RALS)
Start date
1st November 2018
End date
29th January 2019
Goals and objectives
Following are key goals and objectives of proposed online ticketing system of RALS:
The exhibitors will be able to book exhibition sites through online medium.
The facility will be able to book tickets through mobile phone also.
The proposed online system will be able to allow end users to reduce manual mistakes in
RALS work.
The online system ticket and entry passes have a barcode to conduct verification and
validation of exhibition sites.
Project plan
Project scope
In Scope Includes
System Functions Ability to allow RALS users to manage tickets online i.e.
users will be able crate a booking, cancel a booking and
update booking through online system.
Ability to demonstrate system qualities such as
usability, reliability, scalability and availability.
Ability to ensure that only authorized users are allowed
to access the online site to make any changes in the
system such as booking tickets, etc.
System Documentation Project charter
Security plan report
User manual
Implementation plan
Closure reports
Training Staff shall be provided training to understand the
3
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
features of new online ticketing system.
End users shall be provided with a guidance “Help”
section for the same.
Constraints
Following are key constraints of the proposed project:
In case, project exceeds the assigned budget, project manager should consult the RALS
management for extra budget.
Resources are required to be available 100% throughout the project. In case as resource is
not available, an immediate replacement shall need to be done.
If project is not able to meet deadline, then project manager should update the sponsor and
get extra resources allocated to the project.
Functional requirements
Following are key functional requirements of the proposed system:
Customer should be able to create online account.
Customer should be able to book, update or cancel a ticket.
Customer should be able to make payment for the booking.
Customer should be able to report any feedbacks about the system.
Management should be able to generate reports.
Non-functional requirements
Following are key non-functional requirements of the proposed system:
System should be 24x7 available.
System should have very low learning curve.
System should prompt users about next likely action during performing an action.
System should allow access only to the authorized users.
4
End users shall be provided with a guidance “Help”
section for the same.
Constraints
Following are key constraints of the proposed project:
In case, project exceeds the assigned budget, project manager should consult the RALS
management for extra budget.
Resources are required to be available 100% throughout the project. In case as resource is
not available, an immediate replacement shall need to be done.
If project is not able to meet deadline, then project manager should update the sponsor and
get extra resources allocated to the project.
Functional requirements
Following are key functional requirements of the proposed system:
Customer should be able to create online account.
Customer should be able to book, update or cancel a ticket.
Customer should be able to make payment for the booking.
Customer should be able to report any feedbacks about the system.
Management should be able to generate reports.
Non-functional requirements
Following are key non-functional requirements of the proposed system:
System should be 24x7 available.
System should have very low learning curve.
System should prompt users about next likely action during performing an action.
System should allow access only to the authorized users.
4
Work Breakdown Structure
5
5
(Siami-Irdemoosa, Dindarloo & Sharifzadeh, 2015)
Time estimation
6
Time estimation
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project resources
Gantt chart
7
Gantt chart
7
Network diagram
8
8
9
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Cost estimation
10
10
Quality plan
The quality framework at RALS includes for quadrants: staff and customer access and outcomes,
organizational health, financial health and innovation. The purpose of quality plan includes:
To ensure customer and staff access to the proposed online ticketing system which stands
on expectations of RALS.
To satisfy the objectives of agreed requirements in providing quality platform with
innovative strategies.
To explore best practices in providing service delivery.
Quality plan shall investigate processes and not the people:
Quality improvement must be continuous which should include defining, improving and
measuring quality.
Quality online ticketing system should include effort of both developing team and staff. All
RALS staff is responsible for quality improvement.
Accountabilities of management should be clearly defined for efficient improvement.
Implementation of quality plan
All staff members of every department will have a defined action plan for every project objective.
The action plan will include supporting actions and implementation plan along with the evaluation
plan with defined timeline. The improvement model used for quality plan implementation is Deming
Cycle i.e. “Plan, Do, Study, Act” (PDSA) model (Milunovic & Filipovic, 2013).
11
The quality framework at RALS includes for quadrants: staff and customer access and outcomes,
organizational health, financial health and innovation. The purpose of quality plan includes:
To ensure customer and staff access to the proposed online ticketing system which stands
on expectations of RALS.
To satisfy the objectives of agreed requirements in providing quality platform with
innovative strategies.
To explore best practices in providing service delivery.
Quality plan shall investigate processes and not the people:
Quality improvement must be continuous which should include defining, improving and
measuring quality.
Quality online ticketing system should include effort of both developing team and staff. All
RALS staff is responsible for quality improvement.
Accountabilities of management should be clearly defined for efficient improvement.
Implementation of quality plan
All staff members of every department will have a defined action plan for every project objective.
The action plan will include supporting actions and implementation plan along with the evaluation
plan with defined timeline. The improvement model used for quality plan implementation is Deming
Cycle i.e. “Plan, Do, Study, Act” (PDSA) model (Milunovic & Filipovic, 2013).
11
It is necessary that quality plan is communicated and disseminated to all RALS staff. Quality team
shall make presentations to all departmental staff members so that front-end and back-end staff
becomes aware of data included in the corporate Quality plan.
Stakeholder analysis
Key Stakeholder Expectations Perceptions of Success Measure of success
Project owner Project is delivered
on time and within
allocated budget;
Proficient project
management;
No negative impact
on the sales of
tickets;
Increase in
customer retention;
Increase is market
reach
Project is executed
smoothly;
Increase in sales by 40%;
Increase in customer base
by 30%.
Increased interaction
between customers
and staff;
Increase in revenue
by 30%;
Positive coverage by
media
12
shall make presentations to all departmental staff members so that front-end and back-end staff
becomes aware of data included in the corporate Quality plan.
Stakeholder analysis
Key Stakeholder Expectations Perceptions of Success Measure of success
Project owner Project is delivered
on time and within
allocated budget;
Proficient project
management;
No negative impact
on the sales of
tickets;
Increase in
customer retention;
Increase is market
reach
Project is executed
smoothly;
Increase in sales by 40%;
Increase in customer base
by 30%.
Increased interaction
between customers
and staff;
Increase in revenue
by 30%;
Positive coverage by
media
12
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
of project
Project team Project has been
delivered on time
and in assigned
budget;
No hamper to
project due to any
conflicts among
resources;
No negative
publicity by media.
Project is executed
smoothly;
Resolution in conflicts;
0.001% defects in testing;
Increased interaction
between customers
and staff;
Positive coverage by
media
Project manager Project has been
delivered on time
and in assigned
budget;
No hamper to
project due to any
conflicts among
resources;
No negative
publicity by media.
Project is executed
smoothly;
Resolution in conflicts;
UAT happened with
only 0.001% bugs;
Management
received 100 more
bookings than
average bookings in 3
months of launching
the online ticketing
site.
Staff Project has been
delivered on time
and in assigned
budget;
Online system minimizes
human error by 80%
Increase in sales by
40%
Exhibitors/End
users
Project has been
delivered on time
and in assigned
budget;
Booking time is reduced by
89%
Increase in number of
offerings on every
ticket booking.
13
Project team Project has been
delivered on time
and in assigned
budget;
No hamper to
project due to any
conflicts among
resources;
No negative
publicity by media.
Project is executed
smoothly;
Resolution in conflicts;
0.001% defects in testing;
Increased interaction
between customers
and staff;
Positive coverage by
media
Project manager Project has been
delivered on time
and in assigned
budget;
No hamper to
project due to any
conflicts among
resources;
No negative
publicity by media.
Project is executed
smoothly;
Resolution in conflicts;
UAT happened with
only 0.001% bugs;
Management
received 100 more
bookings than
average bookings in 3
months of launching
the online ticketing
site.
Staff Project has been
delivered on time
and in assigned
budget;
Online system minimizes
human error by 80%
Increase in sales by
40%
Exhibitors/End
users
Project has been
delivered on time
and in assigned
budget;
Booking time is reduced by
89%
Increase in number of
offerings on every
ticket booking.
13
Communication plan
Stakeholders Who What are their information
needs
How & when will we
provide them information
RALS management Project
Sponsor
Details regarding the progress
reports, change requests, project
schedule, budget and time
estimation.
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Investors Associated
investors of
RALS
Launch date;
Benefits from project;
Project objectives
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Customers i.e. exhibitors End users of
RALS
Launch date;
Project benefits
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Suppliers The suppliers
who are
responsible for
delivery of
required
hardware for
implementatio
n.
Equipment list Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Business Partners Partners
associated
Details regarding the progress
reports, change requests, project
Weekly meetings through
video-conferencing.
14
Stakeholders Who What are their information
needs
How & when will we
provide them information
RALS management Project
Sponsor
Details regarding the progress
reports, change requests, project
schedule, budget and time
estimation.
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Investors Associated
investors of
RALS
Launch date;
Benefits from project;
Project objectives
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Customers i.e. exhibitors End users of
RALS
Launch date;
Project benefits
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Suppliers The suppliers
who are
responsible for
delivery of
required
hardware for
implementatio
n.
Equipment list Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Business Partners Partners
associated
Details regarding the progress
reports, change requests, project
Weekly meetings through
video-conferencing.
14
with RALS schedule, budget and time
estimation.
Updates – Official mails
Information sharing –
Through SharePoint
Project Team The core
project team
responsible for
carrying out
the project
activities
Project requirements, project
funds, business case, existing
system details
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Risk management plan
Risk assessment
Risk # Possible Unwelcome Event Likelihood
(L)
Low, Med,
High
Severity
(S)
Low, Med,
High
Ranking
L * S
1 The allocated budget exceeds the
allocated budget of the proposed
project.
Low High 3
2 The assigned deadline exceeds the
actual finish date of the project.
Low High 3
3 Technical bugs High Med 6
4 Errors in operations High Med 6
5 Security attacks High High 9
6 Data information attacks High High 9
7 Project resources are not available Med High 6
8 Scope screep Med High 6
1 = Low risk
9 = High risk
15
estimation.
Updates – Official mails
Information sharing –
Through SharePoint
Project Team The core
project team
responsible for
carrying out
the project
activities
Project requirements, project
funds, business case, existing
system details
Weekly meetings through
video-conferencing.
Updates – Official mails
Information sharing –
Through SharePoint
Risk management plan
Risk assessment
Risk # Possible Unwelcome Event Likelihood
(L)
Low, Med,
High
Severity
(S)
Low, Med,
High
Ranking
L * S
1 The allocated budget exceeds the
allocated budget of the proposed
project.
Low High 3
2 The assigned deadline exceeds the
actual finish date of the project.
Low High 3
3 Technical bugs High Med 6
4 Errors in operations High Med 6
5 Security attacks High High 9
6 Data information attacks High High 9
7 Project resources are not available Med High 6
8 Scope screep Med High 6
1 = Low risk
9 = High risk
15
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Risk Mitigation
(Peixoto, Tereso, A., Fernandes, & Almeida, 2014)
Id Event Risk mitigation or contingency
1 The allocated budget exceeds the
allocated budget of the proposed project.
Avoid - Conduct frequent reviews to ensure
that tasks involving high cost can be figured
out on time and hence be avoided.
2 The assigned deadline exceeds the actual
finish date of the project.
Avoid - Conduct frequent reviews to ensure
that tasks involving more time can be figured
out on time and extra resources can be
allocated to it.
3 Technical bugs Mitigate - Get the code reviewed by
developers and regular testing should be
performed by the testing team.
4 Errors in operations Mitigate - Consult trainers to provide
training to the staff and help manual for end
users.
5 Security attacks Avoid - Consult industry experts to enhance
the security of the infrastructure by using
defending techniques such as intrusion
detection techniques and monitoring tools.
6 Data information attacks Avoid - Consult industry experts to enhance
the security by implementing security and
access controls with improved identity
management
7 Project resources are not available Avoid – Conduct one-to-one session with the
employees to understand their concerns and
resolve the conflicts, if any.
8 Scope screep Mitigate – This risk can be mitigated by
having feedback of client after completion of
every phase and required changes should be
16
(Peixoto, Tereso, A., Fernandes, & Almeida, 2014)
Id Event Risk mitigation or contingency
1 The allocated budget exceeds the
allocated budget of the proposed project.
Avoid - Conduct frequent reviews to ensure
that tasks involving high cost can be figured
out on time and hence be avoided.
2 The assigned deadline exceeds the actual
finish date of the project.
Avoid - Conduct frequent reviews to ensure
that tasks involving more time can be figured
out on time and extra resources can be
allocated to it.
3 Technical bugs Mitigate - Get the code reviewed by
developers and regular testing should be
performed by the testing team.
4 Errors in operations Mitigate - Consult trainers to provide
training to the staff and help manual for end
users.
5 Security attacks Avoid - Consult industry experts to enhance
the security of the infrastructure by using
defending techniques such as intrusion
detection techniques and monitoring tools.
6 Data information attacks Avoid - Consult industry experts to enhance
the security by implementing security and
access controls with improved identity
management
7 Project resources are not available Avoid – Conduct one-to-one session with the
employees to understand their concerns and
resolve the conflicts, if any.
8 Scope screep Mitigate – This risk can be mitigated by
having feedback of client after completion of
every phase and required changes should be
16
approved before implementing it. Extra
budget and time also needs to be confirmed
before implementing it.
Deployment plan
The deployment plan shall follow the phased deployment strategy. The proposed online ticketing
system shall be rolled out in phases. Every phase shall add components to the final system. The
system will be tested in every phase before the execution of next phase. Since, RALS does not have
any existing system for integration, phased deployment is need not to mix with parallel deployment.
All the deployment activities were carried out in closure phase of the project after the testing of new
installed online system.
Deployment shall need resources such as network engineer, network analyst and network tester to
facilitate the entire process. It will be conducted by executing following steps:
Deployment Planning – It will include planning deployment approach and methods.
Deployment Execution – In this phase, planned deployment strategies are executed as
finalized in the planning phase.
Deployment closure – In this phase, the testing activities are performed to ensure working of
the deployed system.
Project sign off
Project Name: Project Manager:
Start Date: 1st Nov 2018 Completion Date: 29th January 2019
Project Duration: 63.5 days Sponsor:
Project Goal: Online ticket booking system for RALS
17
budget and time also needs to be confirmed
before implementing it.
Deployment plan
The deployment plan shall follow the phased deployment strategy. The proposed online ticketing
system shall be rolled out in phases. Every phase shall add components to the final system. The
system will be tested in every phase before the execution of next phase. Since, RALS does not have
any existing system for integration, phased deployment is need not to mix with parallel deployment.
All the deployment activities were carried out in closure phase of the project after the testing of new
installed online system.
Deployment shall need resources such as network engineer, network analyst and network tester to
facilitate the entire process. It will be conducted by executing following steps:
Deployment Planning – It will include planning deployment approach and methods.
Deployment Execution – In this phase, planned deployment strategies are executed as
finalized in the planning phase.
Deployment closure – In this phase, the testing activities are performed to ensure working of
the deployed system.
Project sign off
Project Name: Project Manager:
Start Date: 1st Nov 2018 Completion Date: 29th January 2019
Project Duration: 63.5 days Sponsor:
Project Goal: Online ticket booking system for RALS
17
Project Deliverables:
Project plan
Status report
Progress reports
Quality plan
Minutes of meeting report.
Clients: RALS
I acknowledge that I have submitted all the
stated deliverables at the agreed quality.
I acknowledge that I have received all the
stated deliverables at the agreed quality.
Project Manager Name and Signature: Sponsor Name and Signature:
Date: Date:
Conclusion
The project depicts that principles of project management helped in developing and executing the
online ticketing system for RALS. They formed a base for the project execution till closure. Along
with this, schedule and time had been planned appropriately with the project taking 63.5 days to
complete.
Post project review and recommendations
Key lessons learnt during the implementation of project are as follows (Lenfle, 2012):
Required resources should be available at the starting and during the project
implementation.
Milestone should be monitored before 7 days of their assigned date of completion for
ensuring quality delivery.
Regular meetings should be conducted to resolve any arising conflicts among the team
members.
18
Project plan
Status report
Progress reports
Quality plan
Minutes of meeting report.
Clients: RALS
I acknowledge that I have submitted all the
stated deliverables at the agreed quality.
I acknowledge that I have received all the
stated deliverables at the agreed quality.
Project Manager Name and Signature: Sponsor Name and Signature:
Date: Date:
Conclusion
The project depicts that principles of project management helped in developing and executing the
online ticketing system for RALS. They formed a base for the project execution till closure. Along
with this, schedule and time had been planned appropriately with the project taking 63.5 days to
complete.
Post project review and recommendations
Key lessons learnt during the implementation of project are as follows (Lenfle, 2012):
Required resources should be available at the starting and during the project
implementation.
Milestone should be monitored before 7 days of their assigned date of completion for
ensuring quality delivery.
Regular meetings should be conducted to resolve any arising conflicts among the team
members.
18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Regular communication should be maintained with vendor or suppliers to ensure timely
delivery.
19
delivery.
19
References
Lenfle, S. (2012). Exploration, project evaluation and design theory: a rereading of the
Manhattan case. International Journal Of Managing Projects In Business, 5(3), 486-
507. doi: 10.1108/17538371211235335
Milunovic, S., & Filipovic, J. (2013). Methodology for quality management of projects in
manufacturing industries. Total Quality Management & Business Excellence, 24(1-2),
91-107. doi: 10.1080/14783363.2012.728851
Peixoto, J., Tereso, A., Fernandes, G., & Almeida, R. (2014). Project Risk Management
Methodology: A Case Study of an Electric Energy Organization. Procedia
Technology, 16, 1096-1105. doi: 10.1016/j.protcy.2014.10.124
Sanchez, H., Robert, B., Bourgault, M., & Pellerin, R. (2009). Risk management applied to
projects, programs, and portfolios. International Journal Of Managing Projects In
Business, 2(1), 14-35. doi: 10.1108/17538370910930491
Siami-Irdemoosa, E., Dindarloo, S., & Sharifzadeh, M. (2015). Work breakdown structure
(WBS) development for underground construction. Automation In Construction, 58,
85-94. doi: 10.1016/j.autcon.2015.07.016
20
Lenfle, S. (2012). Exploration, project evaluation and design theory: a rereading of the
Manhattan case. International Journal Of Managing Projects In Business, 5(3), 486-
507. doi: 10.1108/17538371211235335
Milunovic, S., & Filipovic, J. (2013). Methodology for quality management of projects in
manufacturing industries. Total Quality Management & Business Excellence, 24(1-2),
91-107. doi: 10.1080/14783363.2012.728851
Peixoto, J., Tereso, A., Fernandes, G., & Almeida, R. (2014). Project Risk Management
Methodology: A Case Study of an Electric Energy Organization. Procedia
Technology, 16, 1096-1105. doi: 10.1016/j.protcy.2014.10.124
Sanchez, H., Robert, B., Bourgault, M., & Pellerin, R. (2009). Risk management applied to
projects, programs, and portfolios. International Journal Of Managing Projects In
Business, 2(1), 14-35. doi: 10.1108/17538370910930491
Siami-Irdemoosa, E., Dindarloo, S., & Sharifzadeh, M. (2015). Work breakdown structure
(WBS) development for underground construction. Automation In Construction, 58,
85-94. doi: 10.1016/j.autcon.2015.07.016
20
1 out of 21
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.