Project Management Application

Verified

Added on  2020/04/21

|31
|5383
|78
AI Summary
This assignment delves into the practical application of project management principles. Students are tasked with developing various project management tools and diagrams, including a Work Breakdown Structure (WBS), Gantt chart, Critical Path analysis, Network Diagram, and Time-Phased Budget. These tools illustrate the different phases, dependencies, and resource allocation involved in managing a project effectively.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
Task 1...............................................................................................................................................3
1. Type of project for JKB Bloggins Ltd.....................................................................................3
2. Scope Management and tools useful for the scope subdivision..............................................3
3. Difference between Gantt chart and critical path....................................................................4
4. Project Success Evaluation......................................................................................................4
5. Change Management Plan.......................................................................................................4
6. Methods of Project Success.....................................................................................................5
Task 2...............................................................................................................................................6
Introduction..................................................................................................................................6
Purpose of the Plan..................................................................................................................6
Project Background.................................................................................................................6
Project Approach (Project Lifecycle Description)..................................................................6
Skills and Competencies required by Project Manager...........................................................7
Goals and Objectives...................................................................................................................8
Scope (Scope Statement).............................................................................................................8
Project Deliverables.................................................................................................................8
Project Milestone.....................................................................................................................9
Technical Requirements........................................................................................................10
Limits and Exclusions............................................................................................................10
Document Page
2PROJECT MANAGEMENT
Work Breakdown Structure...................................................................................................10
Stakeholder Analysis.................................................................................................................11
Project Team Structure..............................................................................................................12
Project Scheduling.....................................................................................................................12
Project Gantt chart.................................................................................................................16
Network Diagram..................................................................................................................17
Resource Plan............................................................................................................................17
Risk Plan....................................................................................................................................18
Communication Plan.................................................................................................................19
Monitoring Process....................................................................................................................20
Evaluation and Closure..............................................................................................................20
Conclusion.................................................................................................................................20
Bibliography..............................................................................................................................22
Appendices................................................................................................................................27
Appendix A: Work Breakdown Structure.............................................................................27
Appendix B: Gantt chart........................................................................................................28
Appendix C: Critical Path......................................................................................................29
Appendix D: Network Diagram.............................................................................................30
Appendix E: Time Phased Budget.........................................................................................31
Document Page
3PROJECT MANAGEMENT
Task 1
1. Type of project for JKB Bloggins Ltd
The project for the JKB Bloggins Ltd would include the development of a specific site
building along with the required equipments. The type of the project is Market Driven as the
construction of the building for JKB Bloggins Ltd. is inspired from the needs of the customer
and to some extent the trend of the market.
The JKB Bloggins Ltd is employed for the development of their operations with the
manufacturing of the new building for the construction and installing new equipments. The
market driven project is implied for the formation of the effective employment (Fleming and
Koppelman 2016). The integration of the deployed methods would be formed for the
development of the operations of JKB Bloggins Ltd and it would form the management of the
operations.
2. Scope Management and tools useful for the scope subdivision
According to Devaux (2014), the scope management is a process of ensuring that all the
required works in the project is include so that the project can be completed successfully along
with controlling the project. The alignment of the project in scope items is formed for ensuring
that the project is aligned successfully.
The scope management is deployed for ensuring that all crucial works of the projects is
implied for the development of the improved functional analysis along with the integration of the
operations (Schwalbe 2015). The management of the operations would be formed for the
alignment of the project management principles for JKB Bloggins Ltd. The use of the WBS

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT
would be helpful for showing the sub divisions of the scope by the help of the work packages as
the work packages are aligned with the scope of the project.
3. Difference between Gantt chart and critical path
The full project Gantt chart is deployed for the development of the detailed project
schedule development (Walker 2015). The use of the specific Gantt chart would be helpful for
ensuring that the project schedule is developed successfully. The Gantt chart represents the
complete list of the activities of the project and it would form the development of the complete
analysis of the processes. However, the critical path helps in analysing the crucial and important
activities of the project. A critical path may omit the activities that can run along a critical project
activity or activities.
4. Project Success Evaluation
The project success evaluation can be done by analysing the activities of the project in
terms of the success factors (Larson and Gray 2013). The deployment of the success criteria
evaluation would be helpful for realizing the development of the project and evaluate the
progress. The project must be completed in the expected cost and time for ensuring the success
of the project.
5. Change Management Plan
The changes in the project can be managed by the help of the change management plan
and implying it for the successful change implication (Devaux 2014). A project might require the
modification of the operations, scope or activities and the change management plan helps in
ensuring that the changes of the project are implied successfully. The change management plan
Document Page
5PROJECT MANAGEMENT
is helpful for managing both internal and external changes. The activities of the change
management are,
1) Introduction of the process for submission, evaluation, and approval of the
changes
2) Definition of the guidelines for the team members
3) Review of the changes with the project team
4) Approval of the changes and communication of the changes concerned
5) Documentation and tracking of the changes for the project
Some changes that would be included in the project of constructing the new
manufacturing site for the JKB Blogging Ltd along with improved equipments and technology
are relocation, data migration, handling of new equipments, and alignment of the operations at
the new manufacturing site. The development of the change management plan would be helpful
for overcoming the issues of the changes and implement it successfully.
6. Methods of Project Success
The project evaluation, monitoring, and control are implied for ensuring that the project
is completed in the estimated time duration (Kerzner 2013). The development of the project
evaluation is done by evaluating the project in terms of cost and time. The Monitoring of the
project is done with the help of the development of the project progress report for ensuring that
the project is progressing as expected. The use of the project schedule and cost estimation plan
would be helpful in ensuring that the project is completed in the estimated time and budget. The
project progress report would help the operations of the project.
Document Page
6PROJECT MANAGEMENT
Task 2
Introduction
The project management unit has been playing a significant role in the development of
the improved processes. The alignment of the profound development would be helpful for
carrying out the development of the operations and forming the consideration of the operations.
The following assignment is formed for the development of a report for the project of
Construction of Manufacturing Site at JKB Bloggins Ltd. The report had covered the scope,
objectives, deliverables, milestone, project schedule, network diagram, work breakdown
structure, risk matrix, communication plan, and quality management. The alignment of the
project would help the analysis of the project formation.
Purpose of the Plan
The project had been formed for constructing a new site for the JKB Bloggins Ltd for
implementing their operations. The alignment of the project plan would help in forming the
development of the improved operations for the construction activities.
Project Background
The project is held responsible for the alignment of the operations and development of
the effective management process. The formation of the activities would be helpful for forming
the deployment of the effective project operations. The Construction of Manufacturing Site at
JKB Bloggins Ltd is helpful for integrating the formation of the manufacturing of the site for the
organization.
Project Approach (Project Lifecycle Description)

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7PROJECT MANAGEMENT
The task of Development of New Manufacturing Site for JKB Bloggins Ltd. takes after
Agile (Adaptive) Lifecycle. The Agile undertaking lifecycle can be ordered into introductory
stage, arranging stage, outlining stage, execution stage, testing stage, and conclusion stage
(Martone et al. 2016). The underlying stage incorporates the improvement of the underlying
documentation and asset advancement. The arranging stage would include choosing an
undertaking design technique and building up the calendar for the task. The planning stage
would include influencing the outline for the working of the assembling to site. The execution
stage would contain the usage of the exercises for the undertaking. The testing stage would
include the examination of the results of the execution stage and alter the exercises if required.
The venture conclusion stage would contain the advancement of the exercises for definite
shutting of the undertaking.
Skills and Competencies required by Project Manager
The project manager plays a significant role in the development of the project and
completion of the project successfully. The complete management and alignment of the project
activities fall under the responsibility of the project manager. The skills and competencies
required by the project manager for this large project are listed in the table below,
Skills Competencies
Communication
Leadership
Team Management
Negotiation
Personal Organization
Execution
Decision Making
Strategy Development
Technical Competence
Critical Thinking
Document Page
8PROJECT MANAGEMENT
Risk Management Business Expert
Goals and Objectives
The objectives of the project of Construction of Manufacturing Site at JKB Bloggins Ltd
are given below,
To form the development of the project plan that would help in constructing the
manufacturing site for JKB Bloggins Ltd.
To complete the project in the estimated time and budget so that JKB Bloggins Ltd can
get the benefit
To successfully form the project of implementing the construction activities for aligning
the development of the new manufacturing site of JKB Bloggins Ltd
To recruit and train some candidates for working at the new manufacturing site of JKB
Bloggins Ltd.
Scope (Scope Statement)
The project of Construction of Manufacturing Site at JKB Bloggins Ltd consists of both
in scope and out of scope items. The project plan, documents, risk management plan, and
manufacturing site are the in scope items of the project. These should be included in the project
for the development of proper documents and alignment of the operations.
Project Deliverables
The deliverables for the project of Construction of Manufacturing Site at JKB Bloggins
Ltd are given below,
Document Page
9PROJECT MANAGEMENT
Documents: The Project Initiation and Charter Documents are made for the project in 7
days by Tue 10/4/16. The final documents of the project are made in 5 days by Tue 3/6/18.
Plan and Design: The complete reviewed plan is developed in 23 days by Thu 12/1/16
and the design is developed in 45 days by Thu 3/2/17.
Site and Structure: The site of the new manufacturing unit of JKB Bloggins Ltd is
bought for HK$ 6,000,000.00 on Mon 3/20/17. The structure of the building is built in 171 days
by Tue 12/19/17
Equipments and Materials: The materials are bought at a price of HK$ 2,789,200.00 on
Wed 5/10/17 and the equipments are bought at a price of HK$ 668,800.00 on Tue 11/21/17.
Final Documentation and Manufacturing Site: The final documentation is formed in 5
days by Tue 3/6/18. The manufacturing site will be in work by Thu 3/29/18.
Recruiting and Training of staff: The training and recruiting of staffs is another major
factor that would be required in the project. The training session would last of 12 months and it
would be helpful for the staff recruited for working at the new manufacturing site of JKB
Bloggins Ltd.
Project Milestone
The project plan consists of 6 phase namely initial phase, plan phase, design phase,
execution phase, documentation and approval phase, and closure phase and they act as
milestones of the project (Keatley et al. 2017). The milestone of the project of Construction of
Manufacturing Site at JKB Bloggins Ltd along with the time schedule is given in the table
below,

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT MANAGEMENT
WBS Task Name Duratio
n Start Finish
M1 Initial Phase 24 days Mon 9/19/16 Thu 10/20/16
M2 Plan Phase 23 days Tue 11/1/16 Thu 12/1/16
M3 Design Phase 45 days Fri 12/30/16 Thu 3/2/17
M4 Execution Phase 251 days Fri 3/3/17 Fri 2/16/18
M5 Documentation and Approval 22 days Wed 2/28/18 Thu 3/29/18
M6 Project is closed 1 day Fri 3/30/18 Fri 3/30/18
Table 1: Project Milestones with Schedule Duration
(Source: Created by the author)
Technical Requirements
The technical requirements of the project are Analyst, Documenter, Project Manager,
Planner, Designer, Client, Contractor, Workers, Engineer, Government Officer, Site,
Equipments, Iron Pillars, Cement, Brick, Sand, Clay, and Transportation Cost.
Limits and Exclusions
The transportation of the materials is aligned for the construction of the building site
where the manufacturing of the materials would take place. The out of scope of the project are
change management, transportation of the materials, and marketing of the event for the project.
Work Breakdown Structure
The work breakdown structure is developed for forming the specific work packages and
aligning the operations of the project for ensuring that the project is completed in specific time.
Document Page
11PROJECT MANAGEMENT
The work breakdown structure for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd is in the appendix section of the report below.
Stakeholder Analysis
Resource Name
Analyst Analyzing the requirements
Documenter
Developing PID document, Charter
Documentation, Submission of the documents,
and Making final documents
Project Manager
Review and Sign off, Plan Approval, Design
review and approval, Review and Sign off the
final documents, Project is closed, and Final
Inspection of the completed building structure
Planner
Selecting Plan Strategy, Developing plan
outline, Plan review, and Plan Completion
Designer
Selecting Building Design Platform,
Developing design of the new building,
Reviewing the design, and Simulation of the
design
Client Site Approval, Work Started at New
Manufacturing Site, Selection of the site for
Document Page
12PROJECT MANAGEMENT
the new building, and Final Inspection of the
completed building structure
Contractor
Site Clearing, Different Sections of
Manufacturing unit are built, and Final
Inspection of the completed building structure
Workers
Floors are built, Emergency Exit is
constructed, Laying of Iron Pillars for
building, and Building Structure is formed
Engineer
Fire Safety is installed, Final Inspection of the
completed building structure, Testing the
functionality of the equipments installed,
Equipments are installed, and Training of the
Staffs
Project Team Structure

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
13PROJECT MANAGEMENT
Project Scheduling
The project schedule for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd has been developed by using the Ms-Project software and it has been shown in the
table below,
WBS Task Name Duration Start Finish
0
Construction of Manufacturing Site at
JKB Bloggins
400 days Mon 9/19/16 Fri 3/30/18
M1 Initial Phase 24 days Mon 9/19/16 Thu 10/20/16
1.1 Analyzing the requirements 5 days Mon 9/19/16 Fri 9/23/16
1.2 Developing PID document 7 days Mon 9/26/16 Tue 10/4/16
1.3 Charter Documentation 7 days Wed 10/5/16 Thu 10/13/16
1.4 Submission of the documents 3 days Fri 10/14/16 Tue 10/18/16
1.5 Review and Sign off 2 days Wed 10/19/16 Thu 10/20/16
M2 Plan Phase 23 days Tue 11/1/16 Thu 12/1/16
2.1 Selecting Plan Strategy 3 days Tue 11/1/16 Thu 11/3/16
2.2 Developing plan outline 5 days Fri 11/4/16 Thu 11/10/16
2.3 Plan review 3 days Fri 11/11/16 Tue 11/15/16
2.4 Plan Completion 10 days Wed 11/16/16 Tue 11/29/16
Document Page
14PROJECT MANAGEMENT
2.5 Plan Approval 2 days Wed 11/30/16 Thu 12/1/16
M3 Design Phase 45 days Fri 12/30/16 Thu 3/2/17
3.1 Selecting Building Design Platform 3 days Fri 12/30/16 Tue 1/3/17
3.2 Developing design of the new building 15 days Wed 1/4/17 Tue 1/24/17
3.3 Reviewing the design 7 days Wed 1/25/17 Thu 2/2/17
3.4 Simulation of the design 10 days Fri 2/3/17 Thu 2/16/17
3.5 Design review and approval 5 days Fri 2/24/17 Thu 3/2/17
4 Training Phase 253 days Fri 3/3/17 Tue 2/20/18
4.1 Development of training manual 13 days Fri 3/3/17 Tue 3/21/17
4.2 Hiring of the trainers 5 days Wed 3/22/17 Tue 3/28/17
4.3 Training Scheduling 8 days Wed 3/29/17 Fri 4/7/17
4.4 Training Session initiated 3 days Mon 4/10/17 Wed 4/12/17
4.5 Training Completed 2 days Mon 2/19/18 Tue 2/20/18
M4 Execution Phase 251 days Fri 3/3/17 Fri 2/16/18
5.1 Site Development 37 days Fri 3/3/17 Mon 4/24/17
Document Page
15PROJECT MANAGEMENT
5.1.1
Selection of the site for the new
building
5 days Fri 3/3/17 Thu 3/9/17
5.1.2 Land is Bought 7 days Fri 3/10/17 Mon 3/20/17
5.1.3 Site Approval 10 days Tue 3/21/17 Mon 4/3/17
5.1.4 Site Clearing 15 days Tue 4/4/17 Mon 4/24/17
5.2 Infrastructure Development 214 days Tue 4/25/17 Fri 2/16/18
5.2.1 Requirement Materials are bought 12 days Tue 4/25/17 Wed 5/10/17
5.2.2 Laying of Iron Pillars for building 15 days Thu 6/1/17 Wed 6/21/17
5.2.3 Building Structure is formed 40 days Thu 6/22/17 Wed 8/16/17
5.2.4 Floors are built 25 days Thu 8/17/17 Wed 9/20/17
5.2.5
Different Sections of Manufacturing
unit are built
20 days Thu 9/21/17 Wed 10/18/17
5.2.6 Equipments are installed 24 days Thu 10/19/17 Tue 11/21/17
5.2.7 Equipments are transported 15 days Wed 11/22/17 Tue 12/12/17
5.2.8 Fire Safety is installed 5 days Wed 12/13/17 Tue 12/19/17
5.2.9 Emergency Exit is constructed 8 days Wed 12/20/17 Fri 12/29/17
5.2.10 Final Inspection of the completed 5 days Mon 1/1/18 Fri 1/5/18

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
16PROJECT MANAGEMENT
building structure
5.2.11
Testing the functionality of the
equipments installed
10 days Mon 1/8/18 Fri 1/19/18
5.2.12 Training of the Staffs 20 days Mon 1/22/18 Fri 2/16/18
M5 Documentation and Approval 22 days Wed 2/28/18 Thu 3/29/18
6.1 Making final documents 5 days Wed 2/28/18 Tue 3/6/18
6.2
Review and Sign off the final
documents
4 days Wed 3/7/18 Mon 3/12/18
6.3 Government Inspection 3 days Tue 3/13/18 Thu 3/15/18
6.4 Approval of the government 7 days Fri 3/16/18 Mon 3/26/18
6.5
Work Started at New Manufacturing
Site
3 days Tue 3/27/18 Thu 3/29/18
M6 Project is closed 1 day Fri 3/30/18 Fri 3/30/18
Table 2: Project Schedule in a table format
(Source: Created by the author)
Project Gantt chart
The Gantt chart of the project is formed by using Ms-Project Software and it is consists
of a table of project schedule and a time frame showing the extent of the project operations
Document Page
17PROJECT MANAGEMENT
(Siami-Irdemoosa, Dindarloo and Sharifzadeh 2015). The Gantt chart of the project of
Construction of Manufacturing Site at JKB Bloggins Ltd is shown below,
Critical Path Analysis: The critical path of the project of Construction of Manufacturing
Site at JKB Bloggins Ltd is shown by highlighting in the appendix section of the report below.
The critical path node structure for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd is given below,
0
M11.11.21.31.41.5M22.12.22.32.42.5M44.14.1.14.1.2
4.1.34.1.44.24.2.34.2.44.2.54.2.64.2.74.34.44.5M55.15.25.3
5.45.55.6M6
Network Diagram
Network diagrams are made for ensuring that the project is represented in a stratified
diagram that shows the activities of the project in a cohesive manner (Keatley et al. 2017). The
network diagram for the project of Construction of Manufacturing Site at JKB Bloggins Ltd is in
the appendix section of the report below.
Resource Plan
The cost budget for the project is developed in Ms-Excel with the help of formulas and
tables (Yildiz et al. 2014). The budget of the project of Construction of Manufacturing Site at
JKB Bloggins Ltd is shown below,
Project Budget for the Project of Construction of Manufacturing Site at JKB
Bloggins
Resource Name Resource Rate Usage Cost
Document Page
18PROJECT MANAGEMENT
Type
Analyst Human £
700.00 40 £
28,000.00
Documenter Human £
800.00 176 £
140,800.00
Project Manager Human £
1,500.00 152 £
228,000.00
Planner Human £
900.00 168 £
151,200.00
Designer Human £
1,150.00 280 £
322,000.00
Client Human £ - 184 £ -
Contractor Human £
1,250.00 320 £
400,000.00
Workers Human £
1,000.00 704 £
704,000.00
Engineer Human £
1,400.00 512 £
716,800.00
Government
Officer Human £ - 80 £ -
Site Cost £
6,000,000.00 1 £
6,000,000.00
Equipments Material £
400,000.00 1 £
400,000.00
Iron Pillars Material £
650,000.00 1 £
650,000.00
Cement Material £
600,000.00 1 £
600,000.00
Brick Material £
618,000.00 1 £
618,000.00
Sand Material £
500,000.00 1 £
500,000.00
Clay Material £
421,200.00 1 £
421,200.00
Transportation
Cost Material £
120,000.00 1 £
120,000.00
Total Budget £
12,000,000.00
Table 3: Cost Budget for the project
(Source: Created by the author)

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
19PROJECT MANAGEMENT
Time Phase Budget: The time phased budget is developed with the help of the Cash
Flow tab of the Ms-Project software. The diagram has money values in pounds in the Y axis and
the time period in quarters of years in the X axis. The quarter 3, 2016 exhausts a budget of £
60,000.00. The quarter 4, 2016 exhausts a budget of £ 285,200.00. The quarter 1, 2017 exhausts
a budget of £ 6,372,800.00. The quarter 2, 2017 exhausts a budget of £ 3,115,200.00. The quarter
3, 2017 exhausts a budget of £ 534,000.00. The quarter 4, 2017 exhausts a budget of £
1,038,800.00. The quarter 1, 2018 exhausts a budget of £ 94,000.00. The time phased budget for
the project of Construction of Manufacturing Site at JKB Bloggins Ltd is in the appendix section
of the report below.
Risk Plan
The project risk matrix for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd are given below,
Risk Name and Description Risk Type Probability Severity Impact Mitigation
Delay in project activities: The
time plays a significant factor
for the project and due to any
issues the project activities
might get delayed.
Operational Almost
Certain
Medium High Development of
a proper project
schedule
Cost Overrun: The cost overrun
is the issue when the project
cannot be completed with the
amount of resources gathered
within the period.
Financial Likely Very
High
Extreme Making
provisional
budgeting
Quality Issues: The construction
activities of the project would
involve the use of the raw
materials and the degraded
quality of the materials would
cause the issues in project.
Procuremen
t
Possible High Very
High
Ensuring the
quality of the
project raw
materials
Table 4: Project Risk Matrix
(Source: Created by the author)
Communication Plan
Document Page
20PROJECT MANAGEMENT
The project communication plan for the project of Construction of Manufacturing Site at
JKB Bloggins Ltd are given below,
Information to be
Send
Receiver Communication
Timing
Communication
Method
Sender
Project Status Report Project Client Quarterly Documents Project
Manager
Project and Change
Requirements
Project Team Weekly Email Project
Manager
Work Requests Project
Manager
Monthly Messages Project
Client
Progress Documents Documenter Daily Documents
Team Responsibility Project Team Daily Reports Planner
Table 5: Project Communication Matrix
(Source: Created by the author)
Monitoring Process
The undertaking control procedure can be shaped by following the means said
underneath,
A. Baseline Plan
B. Authorize work
C. Expedite
D. Monitor Progress
E. Scope Change
F. Evaluate and Forecast
G. Circulate Report
H. Problem Solving and Decision Making
I. Revise Update
Document Page
21PROJECT MANAGEMENT
J. Close out Report
Evaluation and Closure
The Transactional Leadership authority is exceptionally useful for the advancement of
the enhanced exercises of the undertaking combination and administration (Cable and Cheung
2017). The arrangement of the venture operations would be useful for shaping the arrangement
of the operations. The arrangement of the exercises would help in shaping the improvement of
the operations.
Conclusion
It can be concluded that the project of the Construction of Manufacturing Site at JKB
Bloggins Ltd had been formed with the help of the project management operations. The
principles and functions of the project management had been helpful for overcoming the
management of the site. The construction of the manufacturing site for JKB Bloggins Ltd had
been formed and this report had formed the use of the project development model for the project
documentation. The project plan, documents, risk management plan, and manufacturing site
were the in scope items of the project while the change management, transportation of the
materials, and marketing of the event were the out of scope items for the project. The
deliverables for the project of Construction of Manufacturing Site at JKB Bloggins Ltd were
Project Initiation and Charter Documents, complete reviewed plan, site of the new manufacturing
unit of JKB Bloggins Ltd, Equipments and Materials, and Final Documentation and
Manufacturing Site. The project plan consisted of 6 phase namely initial phase, plan phase,
design phase, execution phase, documentation and approval phase, and closure phase and they
acted as milestones of the project. The Total Budget of the project of Construction of
Manufacturing Site at JKB Bloggins Ltd was £12,000,000.00. However some risk factors like

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
22PROJECT MANAGEMENT
Delay in project activities, Cost Overrun, and Quality Issues were responsible for the generation
of the issues for the project.
Document Page
23PROJECT MANAGEMENT
Bibliography
Bury, R. (2017). Carillion under pressure to inject funds amid growing pension concerns.
[online] The Telegraph. Available at: http://www.telegraph.co.uk/business/2017/07/15/carillion-
pressure-inject-funds-amid-growing-pension-concerns/ [Accessed 20 Nov. 2017].
Cable, J. and Cheung, C., 2017. Eight Principles of Effective Online Teaching: A Decade-Long
Lessons Learned in Project Management Education.
Cicmil, S., Cooke-Davies, T., Crawford, L. and Richardson, K., 2017, April. Exploring the
complexity of projects: Implications of complexity theory for project management practice.
Project Management Institute.
Coombs, W.T., 2014. Ongoing crisis communication: Planning, managing, and responding.
Sage Publications.
Devaux, S.A., 2014. Managing Projects as Investments: Earned Value to Business Value. CRC
press.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Flyvbjerg, B., 2013. From Nobel prize to project management: getting risks right. arXiv preprint
arXiv:1302.3642.
Document Page
24PROJECT MANAGEMENT
Ganesh, M.K.S. and Thanushkodi, K., 2015. An efficient software cost estimation technique
using fuzzy logic with the aid of optimization algorithm. International Journal of Innovative
Computing, Vol11 (2) Pp-587-597.
Hegazy, T., 2013. Computer-Based Construction Project Management: Pearson New
International Edition. Pearson Higher Ed.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Keatley, D.A., Ferguson, E., Lonsdale, A. and Hagger, M.S., 2017. Lay understanding of the
causes of binge drinking in the United Kingdom and Australia: a network diagram
approach. Health education research, 32(1), pp.33-47.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Li, T., Qiu, W.G., Wang, L.C. and Man, S., 2013. study of project duration risk in the network
diagram based on matrix algorithm. In Applied Mechanics and Materials (Vol. 405, pp. 3401-
3405). Trans Tech Publications.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
25PROJECT MANAGEMENT
Martin, B., 2017. The politics of electricity planning in South Africa: A review of dominant
advocacy coalitions seeking to influence the Integrated Resource Plan of 2010 (IRP2010), and
its update in 2013 (Doctoral dissertation, University of Cape Town).
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Martone, R.G., Erickson, A., Mach, M., Hale, T., McGregor, A., Prahler, E.E., Foley, M.,
Caldwell, M. and Hartge, E.H., 2016, February. EcoPrinciples Connect: A Pilot Project
Matching Ecological Principles with Available Data to Promote Ecosystem-Based Management.
In AGU Fall Meeting Abstracts.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Mohammad, I., van den Broek, H., Boots, M.L. and Wong, R., Oracle International Corporation,
2016. Showing relationships between tasks in a Gantt chart. U.S. Patent 9,336,502.
Nakamura, S., Kaneko, K., Okada, Y., Yin, C. and Ogata, H., 2015. Cubic gantt chart as
visualization tool for learning activity data. In 23rd International Conference on Computers in
Education, ICCE 2015. Asia-Pacific Society for Computers in Education.
Nam, S., Lee, D.K., Jeong, Y.K., Lee, P. and Shin, J.G., 2016. Environmental impact assessment
of composite small craft manufacturing using the generic work breakdown
structure. International Journal of Precision Engineering and Manufacturing-Green
Technology, 3(3), pp.261-272.
Document Page
26PROJECT MANAGEMENT
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Pritchard, C.L. and PMP, P.R., 2014. Risk management: concepts and guidance. CRC Press.
Sallis, E., 2014. Total quality management in education. Routledge.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Siami-Irdemoosa, E., Dindarloo, S.R. and Sharifzadeh, M., 2015. Work breakdown structure
(WBS) development for underground construction. Automation in Construction, 58, pp.85-94.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Turner, R., 2016. Gower handbook of project management. Routledge.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Document Page
27PROJECT MANAGEMENT
Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S., 2014. A knowledge-based
risk mapping tool for cost estimation of international construction projects. Automation in
Construction, 43, pp.144-155.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
28PROJECT MANAGEMENT
Appendices
Appendix A: Work Breakdown Structure
Construction of
Manufacturing Site at
JKB Bloggins
Initial Phase
Analyzing the
requirements
Developing PID
document
Charter
Documentation
Submission of the
documents
Review and Sign off
Plan Phase
Selecting Plan
Strategy
Developing plan
outline
Plan review
Plan Completion
Plan Approval
Design Phase
Selecting Building
Design Platform
Developing design of
the new building
Reviewing the
design
Simulation of the
design
Design review and
approval
Recruitment and Training
Phase
Collecting CVs of
the Candidates
Sorting the names of
appropriate
candidates
Selecting the
Trainees from the
list
Development of
training manual
Hiring of the trainers
Training Scheduling
Training Session
initiated
Training Completed
Execution Phase
Site Development
Selection of the site
for the new building
Land is Bought
Site Approval
Site Clearing
Infrastructure
Development
Requirement Materials
are bought
Laying of Iron Pillars
for building
Building Structure is
formed
Floors are built
Different Sections of
Manufacturing unit are
built
Equipments are
installed
Equipments are
transported
Fire Safety is
installed
Emergency Exit is
constructed
Final Inspection of
the completed
building structure
Testing the
functionality of the
equipments installed
Training of the
Staffs
Documentation and
Approval
Making final
documents
Review and Sign off
the final documents
Government
Inspection
Approval of the
government
Work Started at New
Manufacturing Site
Project is closed
Figure 1: Work Breakdown Structure for the Project
(Source: Created by the author)
Document Page
29PROJECT MANAGEMENT
Appendix B: Gantt chart
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Construction of Manufacturing
Site at JKB Bloggins
484 days Mon 9/19/16 Thu 7/26/18
1 M1 Initial Phase 24 days Mon 9/19/16 Thu 10/20/16
2 1.1 Analyzing the requirements 5 days Mon 9/19/16 Fri 9/23/16
3 1.2 Developing PID document 7 days Mon 9/26/16 Tue 10/4/16
4 1.3 Charter Documentation 7 days Wed 10/5/16 Thu 10/13/16
5 1.4 Submission of the documents 3 days Fri 10/14/16 Tue 10/18/16
6 1.5 Review and Sign off 2 days Wed 10/19/16 Thu 10/20/16
7 M2 Plan Phase 23 days Tue 11/1/16 Thu 12/1/16
8 2.1 Selecting Plan Strategy 3 days Tue 11/1/16 Thu 11/3/16
9 2.2 Developing plan outline 5 days Fri 11/4/16 Thu 11/10/16
10 2.3 Plan review 3 days Fri 11/11/16 Tue 11/15/16
11 2.4 Plan Completion 10 days Wed 11/16/16 Tue 11/29/16
12 2.5 Plan Approval 2 days Wed 11/30/16 Thu 12/1/16
13 M3 Design Phase 45 days Fri 12/30/16 Thu 3/2/17
14 3.1 Selecting Building Design Platform3 days Fri 12/30/16 Tue 1/3/17
15 3.2 Developing design of the new building15 days Wed 1/4/17 Tue 1/24/17
16 3.3 Reviewing the design 7 days Wed 1/25/17 Thu 2/2/17
17 3.4 Simulation of the design 10 days Fri 2/3/17 Thu 2/16/17
18 3.5 Design review and approval 5 days Fri 2/24/17 Thu 3/2/17
19 4 Recruitment and Training Phase 365 days Fri 3/3/17 Thu 7/26/18
20 4.1 Collecting CVs of the Candidates12 days Fri 3/3/17 Mon 3/20/17
21 4.2 Sorting the names of appropriate
candidates
5 days Tue 3/21/17 Mon 3/27/17
22 4.3 Selecting the Trainees from the list3 days Tue 3/28/17 Thu 3/30/17
23 4.4 Development of training manual 13 days Fri 3/31/17 Tue 4/18/17
24 4.5 Hiring of the trainers 5 days Wed 4/19/17 Tue 4/25/17
25 4.6 Training Scheduling 8 days Wed 4/26/17 Fri 5/5/17
26 4.7 Training Session initiated 3 days Mon 5/8/17 Wed 5/10/17
27 4.8 Training Completed 2 days Wed 7/25/18 Thu 7/26/18
28 M4 Execution Phase 251 days Fri 3/3/17 Fri 2/16/18
29 5.1 Site Development 37 days Fri 3/3/17 Mon 4/24/17
30 5.1.1 Selection of the site for the
new building
5 days Fri 3/3/17 Thu 3/9/17
31 5.1.2 Land is Bought 7 days Fri 3/10/17 Mon 3/20/17
32 5.1.3 Site Approval 10 days Tue 3/21/17 Mon 4/3/17
33 5.1.4 Site Clearing 15 days Tue 4/4/17 Mon 4/24/17
34 5.2 Infrastructure Development 214 days Tue 4/25/17 Fri 2/16/18
35 5.2.1 Requirement Materials are bought12 days Tue 4/25/17 Wed 5/10/17
36 5.2.2 Laying of Iron Pillars for building15 days Thu 6/1/17 Wed 6/21/17
37 5.2.3 Building Structure is formed 40 days Thu 6/22/17 Wed 8/16/17
38 5.2.4 Floors are built 25 days Thu 8/17/17 Wed 9/20/17
39 5.2.5 Different Sections of
Manufacturing unit are built
20 days Thu 9/21/17 Wed 10/18/17
40 5.2.6 Equipments are installed 24 days Thu 10/19/17 Tue 11/21/17
41 5.2.7 Equipments are transported 15 days Wed 11/22/17 Tue 12/12/17
42 5.2.8 Fire Safety is installed 5 days Wed 12/13/17 Tue 12/19/17
43 5.2.9 Emergency Exit is constructed 8 days Wed 12/20/17 Fri 12/29/17
44 5.2.10 Final Inspection of the
completed building structure
5 days Mon 1/1/18 Fri 1/5/18
45 5.2.11 Testing the functionality of the
equipments installed
10 days Mon 1/8/18 Fri 1/19/18
46 5.2.12 Training of the Staffs 20 days Mon 1/22/18 Fri 2/16/18
47 M5 Documentation and Approval 22 days Wed 2/28/18 Thu 3/29/18
48 6.1 Making final documents 5 days Wed 2/28/18 Tue 3/6/18
49 6.2 Review and Sign off the final documents4 days Wed 3/7/18 Mon 3/12/18
50 6.3 Government Inspection 3 days Tue 3/13/18 Thu 3/15/18
51 6.4 Approval of the government 7 days Fri 3/16/18 Mon 3/26/18
52 6.5 Work Started at New Manufacturing Site3 days Tue 3/27/18 Thu 3/29/18
53 M6 Project is closed 1 day Fri 3/30/18 Fri 3/30/18
Analyst
Documenter
Documenter
Documenter
Project Manager
Planner
Planner
Planner
Planner
Project Manager
Designer
Designer
Designer
Designer
Project Manager
Client
Site[1]
Client
Contractor
Iron Pillars[1],Cement[1],Brick[1],Sand[1],Clay[1]
Workers
Workers
Workers
Contractor
Equipments[1],Engineer
Transportation Cost[1]
Engineer
Workers
Engineer,Contractor,Project Manager,Client
Engineer
Engineer
Documenter
Project Manager
Government Officer
Government Officer
Client
Project Manager
8/7 10/9 12/11 2/12 4/16 6/18 8/20 10/22 12/24 2/25 4/29 7/1 9/2
July 1 November 11 March 21 August 1 December 11 April 21 September 1
Figure 2: Gantt chart of the Project
(Source: created by the author)
Document Page
30PROJECT MANAGEMENT
Appendix C: Critical Path
Construction of
Manufacturing Site at
JKB Bloggins
Initial Phase
Analyzing the
requirements
Developing PID
document
Charter
Documentation
Submission of the
documents
Review and Sign off
Plan Phase
Selecting Plan
Strategy
Developing plan
outline
Plan review Plan Completion Plan Approval
Design Phase
Selecting Building
Design Platform
Developing design of
the new building
Reviewing the
design
Simulation of the
design
Design review and
approval
Recruitment and Training
Phase
Collecting CVs of
the Candidates
Sorting the names of
appropriate
candidates
Selecting the
Trainees from the
list
Development of
training manual
Hiring of the trainers Training Scheduling Training Session
initiated
Training Completed
Execution Phase
Site Development
Selection of the site
for the new building Land is Bought
Site Approval Site Clearing
Infrastructure
Development
Requirement Materials
are bought
Laying of Iron Pillars
for building
Building Structure is
formed Floors are built
Different Sections of
Manufacturing unit are
built
Equipments are
installed
Equipments are
transported
Fire Safety is
installed
Emergency Exit is
constructed
Final Inspection of
the completed
building structure
Testing the
functionality of the
equipments installed
Training of the
Staffs
Documentation and
Approval
Making final
documents
Review and Sign off
the final documents
Government
Inspection
Approval of the
government
Work Started at New
Manufacturing Site
Project is closed
Figure 3: Critical Path of the Project
(Source: Created by the author)