Project Management Plan for 24X7 Facilities and Services in Upper West Side

Verified

Added on  2023/06/09

|25
|5611
|153
AI Summary
This project management plan outlines the project parameters, roles and responsibilities, deliverables, goals and strategies, monitoring and reporting strategies, risk management plan, legislative requirements, and project plan for the implementation of 24X7 facilities and services in Upper West Side.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Table of Contents
Introduction......................................................................................................................................3
Determine Project Parameters.........................................................................................................3
1. Project Brief.........................................................................................................................3
2. Negotiation of Project Objectives and Timeline and Identification of Client and
Stakeholders.................................................................................................................................4
3. Roles and Responsibilities...................................................................................................4
4. Deliverables and Desired Outcomes....................................................................................5
5. Goals and Strategies............................................................................................................6
6. Monitoring and reporting strategies.....................................................................................7
7. Risk Management Plan........................................................................................................8
8. Legislative Requirements....................................................................................................9
9. Project Plan........................................................................................................................10
Organize Support Processes..........................................................................................................12
10. Identification of the Resources..........................................................................................12
11. Targets and Milestones......................................................................................................13
12. Communication Strategies.................................................................................................15
13. Documents and Checklists.................................................................................................16
14. Encountered Contingencies...............................................................................................16
Monitor Project processes and outcomes......................................................................................17
15. Progress Monitoring..........................................................................................................17

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16. Controlling Expenditure and Resource Usage...................................................................17
17. Requirement of mentoring or coaching.............................................................................19
18. Progress Report..................................................................................................................19
19. Systems, Records, and Reporting Procedures...................................................................21
Evaluate Project Outcomes............................................................................................................21
20. Project Processes and Outcomes.......................................................................................21
21. Evaluation Results.............................................................................................................21
22. Improvement Recommendations.......................................................................................22
23. Sign off documentation......................................................................................................22
Conclusion.....................................................................................................................................22
Bibliography..................................................................................................................................23
Document Page
Introduction
Project Management has always been helpful for executing the project in an orderly
process for easing the implication of the operations1. The scheduling, planning, budgeting,
estimating, and managing of the projects are well executed for developing the successful
completion of the project. The support and development of the projects had eased the implication
and alignment for developing the support for improving the utilization of the factors. The
alignment would also be helpful for supporting the development of the options for aligning with
the implication of the effective project management principles for the project of 24X7 facilities
and services in the upper west side. The following assignment would be developed based on the
implication of the facilities defining the implication of the operations and aligning the utilization
of the factors.
Determine Project Parameters
1. Project Brief
The following assignment has been made for implementing the 24X7 facilities and
services in the upper west side. The alignment would be dependent on forming the support and
implementation of the effective alignment of the facilities2. The improved services in the
building would be installed for developing the improved facilities and operations. The successful
alignment would be helpful for easing the implication of the factors defining the support and
influence of activities. The completion of the improved functional analysis would form the major
impact on the alignment of the support and configuration of the options. The camera services,
Existing camera is reviewed, development of information hub, ordering keys and swipes,
developing parcel delivery system, improving general cleanliness, upgrade lightning and design,
BBQ area signage, and Madison Tower Level Upgrade. The implication of the activities would
help in easing the alignment of the factors defining the alignment of the improved services for
the complex building.
1 Kerzner, Harold, and Harold R. Kerzner. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons, 2017.
2 Harrison, Frederick, and Dennis Lock. Advanced project management: a structured approach. Routledge,
2017.
Document Page
2. Negotiation of Project Objectives and Timeline and Identification of Client
and Stakeholders
The project has the primary objective of defining the implication of the improved
facilities and aligning the utilization of the factors. The project objective would include the
factors of developing the improved services for the development of the factors3. The implication
would be eased with the utilization of the support and development. The deployment would be
eased with the utilization of the factors aligning the development of the support and integration.
The support and integration would be utilized for easing the implication and alignment of
operations so that the improved functional development can be achieved. The negotiation with
the client on objectives and timeline of the project would be based on the implication of the
factors defining the analysis of the support and development. The analysis of the factors would
be affected by the simplification of the support and development.
The stakeholders of the project are Owners Corporation 1, Owners Corporation 2,
Owners Corporation 4, Owners Corporation 5, Owners Corporation 6, Owners Corporation 7,
and Australian Property Management Pty Ltd.
3. Roles and Responsibilities
The following table would show the roles and responsibilities of the individual for the
execution of the project.
Name Roles and Responsibilities
Shawn Lu Australian
Property Management Pty
Ltd
Management of the project and execution for successful completion
of the project
Esin Ibrahim – Australian
Property Management Pty
Ltd
In charge of project resources and estimation of the budget required
for the project
3 Nicholas, John M., and Herman Steyn. Project management for engineering, business and technology.
Routledge, 2017.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Lip Phua Australian
Property Management Pty
Ltd
Scheduling and Planning the project for ensuring the smooth
operations of the service development for upper west side
Justin Barr Australian
Property Management Pty
Ltd
Making required documentation and reports that would be helpful
for executing the project activities.
Tapan Reang – Australian
Property Management Pty
Ltd
Supporting documentation and development for easing
development of the factors for developing the implication of the
operations and aligning the development of the factors.
Carla Nessel – Australian
Property Management Pty
Ltd
Execution of the development and renovation activities for easing
the formation of the utilities to form the extension of the operations
Paul Alabach – Australian
Property Management Pty
Ltd
Deploying the utilization of the factors developing the alignment of
the improved functional and effective development of operations
Sonia Arora – Australian
Property Management Pty
Ltd
In charge of HR activities for developing the successful integration
of the functions aligning the significant formation of improved
activities
4. Deliverables and Desired Outcomes
The project of 24X7 facilities and services in the upper west side is developed for
improving the functional analysis of the factors supporting the utilization of the support and
development. The deliverables of the project are,
Document Page
Security Camera Upgrade: The security camera upgrade would be developed for aligning
with the development of the facilities for aligning the implication of the effective and smart
processing.
Community Hub: The community hub would be developed for supporting the effective
communication and alignment of the factors supporting the implication of the improved
operations.
Improvement of general cleanliness: The general cleanliness would be improved with the
help of the innovative technology and new management installation.
Upgrade lightning and design: The upgrade of the lightning and design would be required
for the technology innovation and development of the factors aligning the simplification.
BBQ area signage: The BBQ area signage would be developed for easing the utilization
of the development factors for general meeting and communication development.
Madison Tower Level Upgrade: The tower level would be upgraded with the general
alignment of the technology development and execution.
Reduction in Levies Owning: The reduction of the levies owning would be eased in the
project activities execution and development.
5. Goals and Strategies
The project has the primary goal of defining the implication of the improved facilities and
aligning the utilization of the factors. The project goal would include the factors of developing
the improved services for the development of the factors4. The implication would be eased with
the utilization of the support and development. The deployment would be eased with the
utilization of the factors aligning the development of the support and integration. The support
and integration would be utilized for easing the implication and alignment of operations so that
the improved functional development can be achieved.
4 Larson, Erik W., Clifford F. Gray, Ursula Danlin, Beverly Honig, and David Bacarini. Project
management: The managerial process. Vol. 6. Grandview Heights, OH: McGraw-Hill Education, 2014.
Document Page
The strategies used for the development of the project activities would be eased with the
implication of the facilities defining the alignment of the improved factors. The scheduling,
planning, budgeting, estimating, and managing of the projects are well executed for developing
the successful completion of the project5. The support and development of the projects had eased
the implication and alignment for developing the support for improving the utilization of the
factors. The alignment would also be helpful for supporting the development of the options for
aligning with the implication of the effective project management principles for the project of
24X7 facilities and services in the upper west side.
6. Monitoring and reporting strategies
The monitoring and reporting of the project of 24X7 facilities and services in the upper
west side would be deployed with the help of easing the implication of the factors of supporting
the implication of the factors aligning the definition of the activities favouring the alignment of
the activities6. The use of the Gantt chart and checklist would be helpful for keeping track of the
project progress and schedule. The use of various testing processes like alpha testing, beta
testing, prototyping, and simulation would be helpful for easing the development of the
activities. The various strategies of monitoring and reporting in the project include,
Baseline Report: The baseline report is helpful for ensuring that the effective
communication process is implied successfully. The support and development would also be
helpful for easing the process of the keeping track of the project activities. For example: the
report would help in checking how much work of the project has been completed after time
interval of one fourth, half, three fourth, and full completion of the estimated time.
Checklist Development: The checklist development would be helpful for easing the
utilization of effective implication management. The checklist would be developed keeping in
mind the implication of the successful completion of the operations. For example- the developed
5 Mir, Farzana Asad, and Ashly H. Pinnington. "Exploring the value of project management: linking project
management performance and project success." International journal of project management 32, no. 2 (2014): 202-
217.
6 Svejvig, Per, and Peter Andersen. "Rethinking project management: A structured literature review with a
critical look at the brave new world." International Journal of Project Management 33, no. 2 (2015): 278-290.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
checklist would keep track of the achievement of the deliverables of plan, documentation,
infrastructure, technology, equipments, and final report.
Progress Journal: The progress journal is helpful for noting the day to day activities and
aligning the implication of the successful development of the factors. The progress journal would
allow the implication of the factors for easing the utilization of the operations. For example- the
progress journal would help in back tracking the problem of schedule and change it so that the
rest of the project can be completed successfully.
Figure 1: Project Life Cycle Analysis
(Source:
7. Risk Management Plan
The risk management plan would be developed aligning the utilization of the factors
defining the simplification of the factors supporting the utilization of the factors aligning the
simplicity of the activities deploying the utilization of the factors developing the simplification
of the operations7. The risk management plan comprises of risk analysis and risk mitigation for
supporting the utilization of the factors defining the implication of the operations. The risk
management would involve the following factors,
7 Hopkin, Paul. Fundamentals of risk management: understanding, evaluating and implementing effective
risk management. Kogan Page Publishers, 2018.
Document Page
Risk Cause of the risk Likelihood Severity Mitigation Ranking
Delay in
completion
The delay can be resulted by
many reasons such as lack of
the materials, human errors, or
equipment failure that would
result in halting the progress of
the project.
Likely Moderate Accept 3rd
Over budget
The over budget is resulted due
to the lack of the proper
development process and
inclusion of the effective
implication of the factors.
Possible Major Avoid 2nd
Technology
Issues
The technology issues are
resulted when the equipments
fail to involve the alignment of
the operations and significant
development of the factors. The
device may fall short for
aligning the simplification and
developed operations
Unlikely Critical Mitigate 1st
8. Legislative Requirements
The 24X7 facilities and services in the upper west side project would be based on the
ground works and the technology innovation implementation. The following legislative
requirements must be followed for the project,
Abiding to the community welfare and development process for easing the
implication of the new services
Following the safety policies and procedures for the emergency exits and safety
drills
Document Page
Aligning the implication of the factors defining the utilization of the innovative
technology development
According to Industry and Technology Development Act 1988, the
encouragement of the facility for residential and commercial section should be
used
According to Western Australian Products Symbol Act 1972, the development
is based on the prescribed promotion of the products
9. Project Plan
The 24X7 service technology implementation for Upper West Side project would involve
the use of the technology innovation for development of the effective plan development
supporting the implication of the improved development process. The following is the project
plan for the improved facilities and services of upper west side, ordering keys and swipes,
development of information hub, developing parcel delivery system, improving general
cleanliness, upgrade lightning and design, BBQ area signage, and Madison tower level upgrade.
s
WBS Task Name Duration Start Finish Predecessors
0 24X7 service technology implementation
for Upper West Side 61 days Thu
11/16/17 Thu 2/8/18
1 Initialization 8 days Thu
11/16/17
Mon
11/27/17
1.1 Project Analysis 2 days Thu
11/16/17
Fri
11/17/17
1.2 Resource Accumulation 3 days Mon
11/20/17
Wed
11/22/17 2
1.3 Initiation documents 2 days Thu
11/23/17
Fri
11/24/17 3
1.4 Submission of documents 1 day Mon Mon 4

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
11/27/17 11/27/17
1.5 Project Kick off 0 days Mon
11/27/17
Mon
11/27/17 5
2 Planning 13 days Tue
11/28/17
Thu
12/14/17
2.1 Activity Listing 2 days Tue
11/28/17
Wed
11/29/17 6
2.2 Scheduling the activities 1 day Thu
11/30/17
Thu
11/30/17 8
2.3 Plan Outline Development 3 days Fri 12/1/17 Tue
12/5/17 9
2.4 Review of Plan 2 days Wed
12/6/17
Thu
12/7/17 10
2.5 Complete Plan Development 5 days Fri 12/8/17 Thu
12/14/17 11
2.6 Plan Approval 0 days Thu
12/14/17
Thu
12/14/17 12
3 Execution 34 days Fri
12/15/17
Wed
1/31/18
3.1 Security Camera Upgrade 10 days Fri
12/15/17
Thu
12/28/17
3.1.1 Existing Camera is reviewed 2 days Fri
12/15/17
Mon
12/18/17 13
3.1.2 Upgrading the camera function 4 days Tue
12/19/17
Fri
12/22/17 16
3.1.3 Additional and multiple cameras are
installed 4 days Mon
12/25/17
Thu
12/28/17 17
3.2 Community Hub 9 days Fri
12/29/17
Wed
1/10/18
3.2.1 Development of Information Hub 3 days Fri
12/29/17 Tue 1/2/18 18
3.2.2 Ordering Keys and Swipes 2 days Wed 1/3/18 Thu 1/4/18 20
Document Page
3.2.3 Developing parcel delivery system 4 days Fri 1/5/18 Wed
1/10/18 21
3.3 Other Works 15 days Thu
1/11/18
Wed
1/31/18
3.3.1 Improving general cleanliness 3 days Thu
1/11/18
Mon
1/15/18 22
3.3.2 Upgrade lightning and design 3 days Tue
1/16/18
Thu
1/18/18 24
3.3.3 BBQ area signage 3 days Fri 1/19/18 Tue
1/23/18 25
3.3.4 Madison Tower Level Upgrade 3 days Wed
1/24/18 Fri 1/26/18 26
3.3.5 Reduction in Levies Owning 3 days Mon
1/29/18
Wed
1/31/18 27
4 Closure 6 days Thu 2/1/18 Thu 2/8/18
4.1 Final report is developed 3 days Thu 2/1/18 Mon 2/5/18 28
4.2 Submission of reports 1 day Tue 2/6/18 Tue 2/6/18 30
4.3 Review and sign off 2 days Wed 2/7/18 Thu 2/8/18 31
4.4 Project is closed 0 days Thu 2/8/18 Thu 2/8/18 32
Organize Support Processes
10. Identification of the Resources
The resources required for the execution of the project 24X7 facilities and services in the
upper west side are given below,
Human Materials
Document Page
Project Manager, Planner, Budgeter,
Documenter, Analyst, Technician, Material,
and Contractor
Construction Materials, System, Camera, Other
Devices
11. Targets and Milestones
The project of 24X7 facilities and services in the upper west side is developed for
improving the functional analysis of the factors supporting the utilization of the support and
development. The deliverables of the project are,
Security Camera Upgrade: The security camera upgrade would be developed for aligning
with the development of the facilities for aligning the implication of the effective and smart
processing.
Community Hub: The community hub would be developed for supporting the effective
communication and alignment of the factors supporting the implication of the improved
operations.
Improvement of general cleanliness: The general cleanliness would be improved with the
help of the innovative technology and new management installation.
Upgrade lightning and design: The upgrade of the lightning and design would be required
for the technology innovation and development of the factors aligning the simplification.
BBQ area signage: The BBQ area signage would be developed for easing the utilization
of the development factors for general meeting and communication development.
Madison Tower Level Upgrade: The tower level would be upgraded with the general
alignment of the technology development and execution.
Reduction in Levies Owning: The reduction of the levies owning would be eased in the
project activities execution and development.
WBS Task Name Duration Start Finish Predecessors

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
0 24X7 service technology implementation
for Upper West Side 61 days Thu
11/16/17 Thu 2/8/18
1.5 Project Kick off 0 days Mon
11/27/17
Mon
11/27/17 5
2 Planning 13 days Tue
11/28/17
Thu
12/14/17
2.1 Activity Listing 2 days Tue
11/28/17
Wed
11/29/17 6
2.2 Scheduling the activities 1 day Thu
11/30/17
Thu
11/30/17 8
2.3 Plan Outline Development 3 days Fri 12/1/17 Tue
12/5/17 9
2.4 Review of Plan 2 days Wed
12/6/17
Thu
12/7/17 10
2.5 Complete Plan Development 5 days Fri 12/8/17 Thu
12/14/17 11
2.6 Plan Approval 0 days Thu
12/14/17
Thu
12/14/17 12
3 Execution 34 days Fri
12/15/17
Wed
1/31/18
3.1 Security Camera Upgrade 10 days Fri
12/15/17
Thu
12/28/17
3.1.1 Existing Camera is reviewed 2 days Fri
12/15/17
Mon
12/18/17 13
3.1.2 Upgrading the camera function 4 days Tue
12/19/17
Fri
12/22/17 16
3.1.3 Additional and multiple cameras are
installed 4 days Mon
12/25/17
Thu
12/28/17 17
3.2 Community Hub 9 days Fri
12/29/17
Wed
1/10/18
3.2.1 Development of Information Hub 3 days Fri
12/29/17 Tue 1/2/18 18
Document Page
3.2.2 Ordering Keys and Swipes 2 days Wed 1/3/18 Thu 1/4/18 20
3.2.3 Developing parcel delivery system 4 days Fri 1/5/18 Wed
1/10/18 21
3.3 Other Works 15 days Thu
1/11/18
Wed
1/31/18
3.3.1 Improving general cleanliness 3 days Thu
1/11/18
Mon
1/15/18 22
3.3.2 Upgrade lightning and design 3 days Tue
1/16/18
Thu
1/18/18 24
3.3.3 BBQ area signage 3 days Fri 1/19/18 Tue
1/23/18 25
3.3.4 Madison Tower Level Upgrade 3 days Wed
1/24/18 Fri 1/26/18 26
3.3.5 Reduction in Levies Owning 3 days Mon
1/29/18
Wed
1/31/18 27
4.4 Project is closed 0 days Thu 2/8/18 Thu 2/8/18 32
12. Communication Strategies
The communication in the project are developed supplying the alignment of the improved
functional and development model8. The communication in the project can be eased with the
implication of the factors defining the synthesis of improved communication development. The
communication would be eased with the simplification of the effective communication strategies
like,
Transfer of information to the stakeholders with the help of email communication
Deployment of the support and development for the initiation of improved
communication process
Alignment of the factors defining the simplification of the information processing
and sharing
8 Lam, J., 2014. Enterprise risk management: from incentives to controls. John Wiley & Sons.
Document Page
Innovative technology utilization for transferring the information
13. Documents and Checklists
The various documents like initiation document, charter document, project plan
document, communication list, risk management plan, development listing, formation plan, and
other documents would be inclined for the development of project report.
The checklist for the project of 24X7 facilities and services in the upper west side is
given below,
Item Check
Gathering of initial information Yes No
Resources are accumulated Yes No
Alignment of operations and development of
factors
Yes No
Project Plan is developed Yes No
Infrastructure is developed Yes No
Technology Innovation is installed Yes No
14. Encountered Contingencies
The major problems for the execution of the project of 24X7 facilities and services in the
upper west side are,
Delay in completion of the project is one of the most common issues that most of the
projects have been facing in the contemporary world. However, the delay in projects would
result in forming the major problems for project.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Over budget is another major problem that the project would have to face as it would
result in forming the alignment of factors deploying the resource usage of the project.
Monitor Project processes and outcomes
15. Progress Monitoring
The progress monitoring of the project of 24X7 facilities and services in the upper west
side would be deployed with the help of easing the implication of the factors of supporting the
implication of the factors aligning the definition of the activities favouring the alignment of the
activities9. The use of the Gantt chart and checklist would be helpful for keeping track of the
project progress and schedule. The use of various testing processes like alpha testing, beta
testing, prototyping, and simulation would be helpful for easing the development of the
activities. The implication of the activities would be eased with the utilization of the innovation.
16. Controlling Expenditure and Resource Usage
OLD NEW
Owners Corporation 1
Legal cost & debt recovery $20,000.00 $5,000.00
Management Stationery $4,500.00 $2,500.00
Office Telephone charges $7,000.00 $3,000.00
Contingency line $10,000.00 $0.00
Provision of Maintenance Fund $10,000.00 $0.00
Insurance Recoverable $10,000.00 $1,000.00
Insurance Premiums $2,04,000.00 $2,60,000.00
Waste Compactor $12,000.00 $55,000.00
Electricity $18,000.00 $37,000.00
Water & Sewerage $2,10,000.00 $4,00,000.00
$5,05,500.00 $7,63,500.00
Owners Corporation 2
Function Room Expenses $7,50,000.00 $0.00
Contingency line $5,000.00 $0.00
Management Stationery $3,000.00 $1,000.00
General Maintenance $25,000.00 $40,000.00
9 Berger, Bruce K., and Juan Meng, eds. Public relations leaders as sensemakers: A global study of
leadership in public relations and communication management. Routledge, 2014.
Document Page
Gym equipment $23,000.00 $60,000.00
Garden Maintenance $51,000.00 $1,10,000.00
Electricity $1,02,000.00 $1,44,000.00
$9,59,000.00 $3,55,000.00
Owners Corporation 4
Building Manager/Facilities $4,02,200.00 $1,89,024.00
Auto Door Repairs $10,000.00 $5,000.00
Steam Cleaning $13,500.00 $17,000.00
Bin Chute Repairs $6,000.00 $16,000.00
General Maintenance $20,000.00 $30,000.00
Electricity $92,000.00 $1,15,000.00
$5,43,700.00 $3,72,024.00
Owners Corporation 5
Building Manager/Facilities $4,05,000.00 $1,89,024.00
Essential Services Repairs $5,000.00 $15,000.00
Auto Door Repairs $1,500.00 $7,000.00
Bin Chute Repairs $3,000.00 $13,000.00
Electrical Repairs $10,000.00 $18,000.00
General Repairs $38,376.00 $30,000.00
Lift Repairs $8,000.00 $15,000.00
Plumbing & drainage $8,000.00 $15,000.00
478876 302024
Owners Corporation 6
Building Manager/Facilities $4,04,300.00 $1,89,024.00
$4,04,300.00 $1,89,024.00
Owners Corporation 7
Building Manager $1,58,000.00 $1,28,599.00
Rubbish Chute repairs $20,000.00 $15,000.00
Electricity $60,000.00 $70,000.00
$2,38,000.00 $2,13,599.00
$31,29,376.00 $21,95,171.00
17. Requirement of mentoring or coaching
The project would be executed under the supervision of the project manager, contractor,
and Engineer for ensuring that the project is completed successfully in the estimated time and
budget estimation.
Document Page
18. Progress Report
WBS Milestone Start date Finish date Status
0 24X7 service technology implementation for Upper
West Side
Thu
11/16/17 Thu 2/8/18 Completed
1.5 Project Kick off Mon
11/27/17
Mon
11/27/17
Completed
2 Planning Tue
11/28/17
Thu
12/14/17
Completed
2.1 Activity Listing Tue
11/28/17
Wed
11/29/17
Completed
2.2 Scheduling the activities Thu
11/30/17
Thu
11/30/17
Completed
2.3 Plan Outline Development Fri 12/1/17 Tue 12/5/17 Completed
2.4 Review of Plan Wed 12/6/17 Thu 12/7/17 Completed
2.5 Complete Plan Development Fri 12/8/17 Thu
12/14/17
Completed
2.6 Plan Approval Thu
12/14/17
Thu
12/14/17
Completed
3 Execution Fri 12/15/17 Wed 1/31/18 Completed
3.1 Security Camera Upgrade Fri 12/15/17 Thu
12/28/17
Completed
3.1.1 Existing Camera is reviewed Fri 12/15/17 Mon
12/18/17
Completed

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
3.1.2 Upgrading the camera function Tue
12/19/17 Fri 12/22/17 Completed
3.1.3 Additional and multiple cameras are installed Mon
12/25/17
Thu
12/28/17
Completed
3.2 Community Hub Fri 12/29/17 Wed 1/10/18 Completed
3.2.1 Development of Information Hub Fri 12/29/17 Tue 1/2/18 Completed
3.2.2 Ordering Keys and Swipes Wed 1/3/18 Thu 1/4/18 Completed
3.2.3 Developing parcel delivery system Fri 1/5/18 Wed 1/10/18 Completed
3.3 Other Works Thu 1/11/18 Wed 1/31/18 Completed
3.3.1 Improving general cleanliness Thu 1/11/18 Mon 1/15/18 Completed
3.3.2 Upgrade lightning and design Tue 1/16/18 Thu 1/18/18 Completed
3.3.3 BBQ area signage Fri 1/19/18 Tue 1/23/18 Completed
3.3.4 Madison Tower Level Upgrade Wed 1/24/18 Fri 1/26/18 Completed
3.3.5 Reduction in Levies Owning Mon 1/29/18 Wed 1/31/18 Completed
4.4 Project is closed Thu 2/8/18 Thu 2/8/18 Completed
19. Systems, Records, and Reporting Procedures
The use of the Gantt chart and checklist would be helpful for keeping track of the project
progress and schedule. The use of various testing processes like alpha testing, beta testing,
prototyping, and simulation would be helpful for easing the development of the activities. The
various documents like initiation document, charter document, project plan document,
Document Page
communication list, risk management plan, development listing, formation plan, and other
documents would be inclined for the development of project report.
Evaluate Project Outcomes
20. Project Processes and Outcomes
The strategies used for the development of the project activities would be eased with the
implication of the facilities defining the alignment of the improved factors. The scheduling,
planning, budgeting, estimating, and managing of the projects are well executed for developing
the successful completion of the project. The use of various testing processes like alpha testing,
beta testing, prototyping, and simulation would be helpful for easing the development of the
activities. The support and development of the projects had eased the implication and alignment
for developing the support for improving the utilization of the factors.
21. Evaluation Results
Item Completed
Gathering of initial information Yes
Resources are accumulated Yes
Alignment of operations and development of factors Yes
Project Plan is developed Yes
Infrastructure is developed Yes
Technology Innovation is installed Yes
22. Improvement Recommendations
a) Utilization of the project management methodology
b) Proper Training Program Development
Document Page
c) Implementing the use of past documents and reports
23. Sign off documentation
Sign off:
<<name of the project manager>>
<<name of the project manager>>
Project Manager
Conclusion
Project Management had always been helpful for executing the project in an orderly
process for easing the implication of the operations. The scheduling, planning, budgeting,
estimating, and managing of the projects were well executed for developing the successful
completion of the project. The support and development of the projects had eased the implication
and alignment for developing the support for improving the utilization of the factors. The
following assignment had been made for implementing the 24X7 facilities and services in the
upper west side. The alignment had been dependent on forming the support and implementation
of the effective alignment of the facilities.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Bibliography
Berger, Bruce K., and Juan Meng, eds. Public relations leaders as sensemakers: A global study
of leadership in public relations and communication management. Routledge, 2014.
Bessis, Joel. Risk management in banking. John Wiley & Sons, 2015.
Binder, Jean. Global project management: communication, collaboration and management
across borders. Routledge, 2016.
Fleming, Quentin W., and Joel M. Koppelman. "Earned value project management." Project
Management Institute, 2016.
Goetsch, David L., and Stanley B. Davis. Quality management for organizational excellence.
Upper Saddle River, NJ: pearson, 2014.
Harbor, Jason, Laurie Carswell Petrucci, and Tatiana Bourlova. "Assignment 3 Project
Documentation: Creating a Content Module for Calculus 12." (2015).
Harrison, Frederick, and Dennis Lock. Advanced project management: a structured approach.
Routledge, 2017.
Heagney, Joseph. Fundamentals of project management. Amacom, 2016.
Hopkin, Paul. Fundamentals of risk management: understanding, evaluating and implementing
effective risk management. Kogan Page Publishers, 2018.
Jousse, Jérémie, Nicolas Ginot, Christophe Batard, and Elisabeth Lemaire. "Power line
communication management of battery energy storage in a small-scale autonomous photovoltaic
system." IEEE Transactions on Smart Grid 8, no. 5 (2017): 2129-2137.
Kerzner, Harold, and Harold R. Kerzner. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons, 2017.
Kerzner, Harold. Project management best practices: Achieving global excellence. John Wiley &
Sons, 2018.
Lam, J., 2014. Enterprise risk management: from incentives to controls. John Wiley & Sons.
Document Page
Larson, Erik W., Clifford F. Gray, Ursula Danlin, Beverly Honig, and David Bacarini. Project
management: The managerial process. Vol. 6. Grandview Heights, OH: McGraw-Hill
Education, 2014.
MacWhinney, Brian. The CHILDES project: Tools for analyzing talk, Volume II: The database.
Psychology Press, 2014.
Marchewka, Jack T. Information technology project management. John Wiley & Sons, 2014.
McNeil, Alexander J., Rüdiger Frey, and Paul Embrechts. Quantitative Risk Management:
Concepts, Techniques and Tools-revised edition. Princeton university press, 2015.
Mir, Farzana Asad, and Ashly H. Pinnington. "Exploring the value of project management:
linking project management performance and project success." International journal of project
management 32, no. 2 (2014): 202-217.
Mooney, Hailey, Jake Carlson, Karen Downing, and Lori Tschirhart. "Documentation in the
Middle: Active Phase Project Documentation for Inclusive and Effective Team-Based Research."
(2017).
Nicholas, John M., and Herman Steyn. Project management for engineering, business and
technology. Routledge, 2017.
Oliver, Kevin, and Jennifer Houchins. "Evidence of Computational Thinking in the After-School
Makerspace from Written Project Documentation." In EdMedia+ Innovate Learning, pp. 402-
407. Association for the Advancement of Computing in Education (AACE), 2018.
O'Neill, Raymond. "Recommendations for Updating the Alaska Department of Transportation
Construction Project Documentation Manual." (2015).
Ruehl, Christopher Hendrik, and Diana Ingenhoff. "Communication management on social
networking sites: Stakeholder motives and usage types of corporate Facebook, Twitter and
YouTube pages." Journal of Communication Management 19, no. 3 (2015): 288-302.
Document Page
Svejvig, Per, and Peter Andersen. "Rethinking project management: A structured literature
review with a critical look at the brave new world." International Journal of Project
Management 33, no. 2 (2015): 278-290.
Tench, Ralph, and Angeles Moreno. "Mapping communication management competencies for
European practitioners: ECOPSI an EU study." Journal of Communication Management 19, no.
1 (2015): 39-61.
Turner, Rodney. Gower handbook of project management. Routledge, 2016.
Verzuh, Eric. The fast forward MBA in project management. John Wiley & Sons, 2015.
Walker, Anthony. Project management in construction. John Wiley & Sons, 2015.
Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.
Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.