Running head: PROJECT MANAGEMENT
Project Management: Sony International Company Recycle
Nam of the student:
Name of the university:
Project Management: Sony International Company Recycle Gantt Chart and Phases_1
1PROJECT MANAGEMENT
Table of Contents
4. Gantt chart................................................................................................................... 5
4.1 Comprehensive human and physical resources.....................................................5
4.2 Cost effectiveness of the business.........................................................................5
5. Budget credible based on the human and physical resources.....................................5
References.......................................................................................................................5
Appendices...................................................................................................................... 5
Appendix 1....................................................................................................................5
Appendix 2....................................................................................................................5
Project Management: Sony International Company Recycle Gantt Chart and Phases_2
2PROJECT MANAGEMENT
4. Gantt chart
The Gantt chart presented in the below section is comprises of different four
phases and the activities involved in the project shows the sequential order that needs
to be followed by the project manager and project team members to develop CSR for
long term sustainable development of Sony International Company.
WB
S Task Name Duratio
n Start Finish Resource Names Cost
0 Project
schedule
1095
days
Mon
2/5/18
Fri
4/15/22
$1,000,000.0
0
1 Project
initiation 390 days Mon
2/5/18
Fri
8/2/19 $309,800.00
1.1
Measuring
current quality
of the products
30 days Mon
2/5/18
Fri
3/16/18 Project manager $9,600.00
1.2
Analyzing
expected
technical
innovation
50 days Mon
3/19/18
Fri
5/25/18 executive officer $24,000.00
1.3
Improving
the products
with
multifunctiona
l productivities
40 days Mon
5/28/18
Fri
7/20/18 Chief Security officer $17,280.00
1.4
Employing
radio
technologies to
the possible
products
50 days Mon
5/28/18
Fri
8/3/18
Functional
requirements[1],hardware[1],no
n functional
requirements[1],software [1]
$160,040.00
1.5
Estimation
net budget for
the project
60 days Mon
8/6/18
Fri
10/26/1
8
Finance manager $12,480.00
1.6
Measuring
the harmful
ray coming
from the usage
of these
products
200 days
Mon
10/29/1
8
Fri
8/2/19 Chief Security officer $86,400.00
Project Management: Sony International Company Recycle Gantt Chart and Phases_3
3PROJECT MANAGEMENT
2
Project
planning
phase
238 days Mon
8/5/19
Wed
7/1/20 $106,874.00
2.1 Stakeholder
management
plan
45 days Mon
8/5/19
Fri
10/4/19 Sales and marketing manager $14,400.00
2.2
Resource
management
plan
23 days Mon
10/7/19
Wed
11/6/19 Finance manager $4,784.00
2.3
Cross
checking the
responsiveness
and consumer
services offers
by Sony
International
company
50 days Thu
11/7/19
Wed
1/15/20 market campaigning cost[1] $12,000.00
2.4
Developing
the basic
structure of
Supply chain
management
system
50 days Thu
11/7/19
Wed
1/15/20 market campaigning cost[1] $12,000.00
2.5
Designing
the basic
structure for
Corporate
Social
Responsibility
70 days Thu
1/16/20
Wed
4/22/20 executive officer $33,600.00
2.6
Analyzing
possible
technologies
which may use
for recycling
50 days Thu
4/23/20
Wed
7/1/20 non functional requirements[1] $30,090.00
3
Project
execution
phase
282 days Thu
7/2/20
Fri
7/30/21 $290,086.00
3.1
Mobilizing
the company
workforce
110 days Thu
7/2/20
Wed
12/2/20 Chief Security officer $47,520.00
3.2 Focusing
to create
diverse are
65 days Thu
12/3/20
Wed
3/3/21
CSR policy planning
[1],Functional
requirements[1],Project
$105,355.00
Project Management: Sony International Company Recycle Gantt Chart and Phases_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Assignment 3: Unit Project Part B
|29
|4746
|459

Project Management: Work Breakdown Structure, Network Diagram, Gantt Chart, Budget, Risk, Communication, Status Report, Reflection
|32
|3729
|498

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463

Office Renovation: Project Scope, Deliverables, Gantt Chart, Cost, WBS, Network Diagram, Risk Assessment, and Cost Estimation Methods
|21
|3130
|107

Challenges of Internet Marketing | Assignment
|6
|481
|271

Development of a New Information Technology Centre – Stage 3
|9
|1217
|69