TASK 1 Analyze three project management methodologies PMM is strictly defined combination of logically related approaches, procedures and practices that identify how best to develop, plan, manage and deliver a project throughout continuous implementation procedures until successful termination & completion (Matos and et.al., 2019). It is essentially a set of process and guiding principles for managing a task. Types of project management methodologies- Waterfall- It is one of the oldest methodologies outlined by Dr Winston Royce as a response to operating increasingly difficult nature of software development (Hamad and Al Fayoumi, 2018). It has become highly used and adopted, most prominently in digital sector. The advantage of this project management method is easy to comprehend and utilize. Division between phases is innate & easy to grasp regardless of previous experience. On the other hand, rigidity of this approach means that when someone find need or error to change something, individual have to effectively begin project from starting, this substantially increase risk of task failure. Agile- It is another project management method emerged as response to failure of waterfall approach for managing complex tasks. It can be said that with this methodology person obtain regularfeedbackfromconsumers,managersandotherstakeholdersaswellasmake modification accordingly. It effectively and efficiently reduces risk of work failure since stakeholders are included at every phase. Whereas, agile method emphasizes responding to modified as they occur. It is lack of any fixed strategy makes scheduling and resource management harder rather than before. Individual will rapidly have to struggle assets, bringing them on an ad-hoc basis. Hybrid- This methodology used to help the organization in resolving the project in better way. As this methodology is the combination of formal as well as agile methodology of the project. This project generally used to look at the final result rather than project. It also used to describe the understanding of project in better way. Reliability of outcome is the issue with the methodology for the short term project in the organization. 3
TASK 2 Developing network diagram, gantt chart and critical analysis points Gantt chart S.no.Task NameDurationStartFinishPredecessorsEarly Finish Early StartLate StartLate Finish 1Budget Approval1 day Sun 7/15/1 8 Sun 7/15/18 Sun 7/15/18 Sun 7/15/18 Sun 7/15/18 Mon 7/16/18 2 Hire Publicity Director 14 days Mon 7/16/1 8 Thu 8/2/181Thu 8/2/18 Mon 7/16/18 Mon 7/16/18 Thu 8/2/18 3HireSet Designer14 days Mon 7/16/1 8 Thu 8/2/181Thu 8/2/18 Mon 7/16/18 Fri 1/11/19 Wed 1/30/19 4 HirePlace For Auditions 7 daysFri 8/3/18 Mon 8/13/182Mon 8/13/18 Fri 8/3/18 Fri 8/3/18 Mon 8/13/18 5 Advertising ToHire Crewand Cast 7 daysFri 8/3/18 Mon 8/13/182Mon 8/13/18 Fri 8/3/18 Fri 8/3/18 Mon 8/13/18 6 Hire Production &Publicity Crew 34 days Tue 8/14/1 8 Mon 12/31/1 8 4,5 Mon 12/31/1 8 Tue 8/14/18 Thu 9/13/18 Wed 1/30/19 7 Set Designed and Built 42 daysTue 1/1/19 Wed 2/27/193,6Wed 2/27/19 Tue 1/1/19 Thu 1/31/19 Fri 3/29/19 8 Train Production Crew 12 daysTue 1/1/19 Wed 1/16/193,6Wed 1/16/19 Tue 1/1/19 Thu 3/21/19 Fri 4/5/19 9Auditions To Hire Cast2 days Tue 8/14/1 8 Wed 8/15/184,5Wed 8/15/18 Tue 8/14/18 Tue 8/14/18 Wed 8/15/18 10Cast Rehearsal95 days Thu 8/16/1 8 Fri 4/5/199Fri 4/5/19 Thu 8/16/18 Thu 8/16/18 Fri 4/5/19 11Hire Orchestra7 days Mon 7/16/1 8 Tue 7/24/181Tue 7/24/18 Mon 7/16/18 Thu 1/31/19 Fri 2/8/19 4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Critical path Path 1: 1 + 2 +4 + 9+ 10 + 21+22 Days= 1 +14 + 7 +2 +2+ 95+ 1 +10 = 132 days Path 2:1 + 2 +5 + 9+ 10 + 21+22 Days = 1 +14 + 7 +2 +2+ 95+ 1 +10 = 132 days From the above data it has been seen that there are two route through which event can be completed within shortage period of time. It will take 132 days to complete the event in the University. TASK 3 Stakeholder Analysis StakeholderRoleInfluence Power Interest level Way to increase interest Project ManagerProjectmanagerisHighHighTo increase the interest 7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
oneofthemost important stakeholdersforthe project.Project manageristheone whowillprepare varietyoftheplan and provide different guidelinetothe projectteaminthe organization. On the basisofthesame different task will be performed in project. of the project manager in the project, sponsor andtheclienthasto makesurethatthey used to pass on good andclearmessageto theprojectmanager, also it has to be make sure that good amount of the resources should beprovidedtothe projectteamtocarry out different operation in an organization. Project SponsorProjectsponsorare the one who used to provide good support toprojectteamand managerin formulationdifferent guideline and plans in theorganization. They are the one who also used to provide the monitory support to the team and desire good return upon the same. HighModerateInterest level of Project sponsorcanbe increasedinthe organization by passing onthegood informationaboutthe progress of the project intheorganization. Thiswillhelpthe companyingetting goodandtimely financefordifferent taskinthe organization. Project teamProjectteamisthe groupofthe individualinthe ModerateModerateTo improve the interest level of project team in the organization project 8
organizationwho used to carry out the different operation of theeventinthe University. Professionalgrowth ofprojectteam generallydepends upon the outcome of the project. manager of the project has to make sure that theyusedtoprovide thegoodsortof rewards and monetary support to project team in the organization, so that they are motivated tocarryoutdifferent operation. Thirdparty Agency ThirdpartyAgency aretheoneinthe nationwhousedto provide different raw materialforthe project team to carry outthedifferent operationinan organization.They are mainly suppliers. LowModerateInterestlevelof differentsuppliercan beincreasedinthe Universityby clarifyingdifferent thingwhichwillbe require by the company before hand itself in the Event. 9
WBS TASK 4 Risk Management RiskImpactResponsible Authority Mitigation strategy Proper schedulingof tak: It is the biggest risk which may occur intheorganization. This is the risk which HighProject manager and Planner Thisriskcanbe overcomeinthe organizationby makingpropertime lineandgoing 10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
generally occur when projectmanagerand planner is not able to schedule the different taskappropriatelyin theUniversity.This certainlyusedto impact the efficiency ofdifferenttask performinthe organization. through it at the time ofscheduling different operation of thebusinessinthe organization. Inadequate finance: It is another risk which mayoccurinthe organization. This risk mayoccurinthe Eventwhenproject teamnotgetthe adequateamountof thefinancetocarry out different operation of the event. HighProject SponsorTo overcome this sort of the problem in the Event,project managerhasto makes sure that they usedtoprovidethe properprogressof theeventtothe project sponsor in the Event.Sothatthey canprovidethe adequatefinanceto carryoutdifferent task in the event. Employee Conflict: It is the type of the conflictwhichmay occurinthe organizationwhen there is some sort of ModerateEmployeeToovercomethis issueinthe UniversityProject managerinthe organizationhasto make sure that they 11
the confusion between thedifferent employeesaboutthe work which has to be carried out by them in the organization. This eventuallyusedto impacttheworking environmentofthe project. usedtobringand build good amount of clarityamongthe employeeinthe organization, this will eventuallyhelpthe individualin loweringdownthe amountofthe conflictinan organization. Resource Wastage: It is another issue which mayoccurinthe organization.This mayoccurinthe organizationdueto improper allocation of different resources in the organization. This sometimeusedto createthesituation wherecostofthe companyusedto increaseinan organization. ModerateResource allocatorToovercomethis type of the risk in the organization,project teamandproject allocator has to make sure that they used to forecast the different need of the resources and on the basis of thesamedifferent resourcesare allocatedinthe organization. Legal Risk This type of the risk mayoccurinthe organization,when organizationisnot LowProject managerThis type of risk can beovercomeinthe organizationby recruitingthe different authority in 12
abletocompilethe differentactivityof the event with variety of rules and regulation of the government. the organization who canlookatthis thingsinthe organization. 13
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
REFERENCES Books and Journals Eskerod, P. and Jepsen, A.L., 2016.Project stakeholder management. Routledge Royer,P.S.,2018.Riskmanagement:Theundiscovereddimensionofproject management.Project Management Journal.31(1). pp.6-13 Adelakun, O. and et.al., 2017. Hybrid Project Management: Agile with Discipline. InCONF- IRM(p. 14). Brewer, J. L. and Dittman, K. C., 2018.Methods of IT project management. Purdue University Press. Conforto, E. C. and Amaral, D. C., 2016. Agile project management and stage-gate model—A hybridframeworkfortechnology-basedcompanies.JournalofEngineeringand Technology Management,40, pp.1-14. Layton, M. C. and Ostermiller, S. J., 2017.Agile project management for dummies. John Wiley & Sons. Stoica,M.andet.al.,2016.AnalyzingAgileDevelopment-fromWaterfallStyleto Scrumban.Informatica Economica,20(4). Zuñiga, M. G., Flores, E. A. and Merino, J. C. A., 2018, November. Hybrid System (Solar- Wind) Management for Generating Electricity in High Andean Rural Regions in Peru. In2018 IEEE Sciences and Humanities International Research Conference (SHIRCON)(pp. 1-5). IEEE. Matos, P.V and et.al., 2019. The adoption of project management methodologies and tools by NGDOs: A mixed methods perspective.Journal of Business Research.101. pp.651-659. Hamad, R.M.H. and Al Fayoumi, M., 2018, November. Scalable Agile Transformation Process (SATP) to Convert Waterfall Project Management Office into Agile Project Management Office. In2018 International Arab Conference on Information Technology (ACIT)(pp. 1-8). IEEE. 14