This document provides information about the development of a new information technology centre in stage 2. It includes details about the work breakdown structure, organisational breakdown structure, responsibility assignment matrix, list of tasks and durations, Gantt chart, estimated cost, risk register, and sub-contractor schedule.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: PROJECT MANAGEMENT
Development of a New Information Technology Centre – Stage 2
Name of the Student
Name of the University
Development of a New Information Technology Centre – Stage 2
Name of the Student
Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT
Stage 2 – WBS and Manual Scheduling
Project Calendar
The project estimated duration of the project is around 12 months and the start and end
dates of the project are estimated as 01/07/2019 and 24/07/2020. The list of holidays that fall
within this period is shown in the following table.
Holiday Date
2019
Final before AFL Grand Final 27th September
Melbourne Cup 5th November
Christmas Day 25th December
Boxing Day 26th December
2020
New Year’s Eve 1st January
Australia Day 27th January
Labour Day 9th March
Good Friday 10th April
Easter 13th April
Queen’s Birthday 8th June
WBS, OBS, RAM
The work breakdown structure for the project is shown as follows.
Stage 2 – WBS and Manual Scheduling
Project Calendar
The project estimated duration of the project is around 12 months and the start and end
dates of the project are estimated as 01/07/2019 and 24/07/2020. The list of holidays that fall
within this period is shown in the following table.
Holiday Date
2019
Final before AFL Grand Final 27th September
Melbourne Cup 5th November
Christmas Day 25th December
Boxing Day 26th December
2020
New Year’s Eve 1st January
Australia Day 27th January
Labour Day 9th March
Good Friday 10th April
Easter 13th April
Queen’s Birthday 8th June
WBS, OBS, RAM
The work breakdown structure for the project is shown as follows.
2PROJECT MANAGEMENT
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The organisational breakdown structure is shown as follows.
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The organisational breakdown structure is shown as follows.
3PROJECT MANAGEMENT
Project Manager
Building Contractor Technical Supervisor
IT Developer System Tester
Labour
Figure 2: Organisational Breakdown Structure
(Source: Created by Author)
The responsibility assignment matrix is shown in the following table.
Task Name Stakeholders
Development of Information Technology Center
Development of the IT Center
Develop Project Plan Project Manager
Select Land for the Construction of the IT Center Project Manager
Purchase the Property Project Manager
Hire Contractor for the Construction Works Project Manager
Develop Blueprint for the IT Center Project Manager
Recruit Workers for the Construction of the IT Center Building Contractor
Project Manager
Building Contractor Technical Supervisor
IT Developer System Tester
Labour
Figure 2: Organisational Breakdown Structure
(Source: Created by Author)
The responsibility assignment matrix is shown in the following table.
Task Name Stakeholders
Development of Information Technology Center
Development of the IT Center
Develop Project Plan Project Manager
Select Land for the Construction of the IT Center Project Manager
Purchase the Property Project Manager
Hire Contractor for the Construction Works Project Manager
Develop Blueprint for the IT Center Project Manager
Recruit Workers for the Construction of the IT Center Building Contractor
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT MANAGEMENT
Procure Construction Materials Building Contractor
Start Construction Labour Team
Construction of the IT Center Labour Team
Interior and Exterior Works Labour Team
Development and Implementation of IT
Developing Requirements for IT Technical Supervisor
Hire IT Development Team Technical Supervisor
Discuss IT Requirements Technical Supervisor
Assign Funds Technical Supervisor
Purchase Hardware Technical Supervisor
Purchase Software Technical Supervisor
Installation of Hardware IT Developer
Installation of Software IT Developer
IT System Development IT Developer
System Testing System Tester
Handover and Go Live IT Developer, System Tester
Sign Off and Closing Project Manager, Technical Supervisor
List of Tasks, Durations and Logical Relationships
The list of tasks, durations and their logical relationships are shown in the following
table.
Task Name Duration Predecessors
Development of Information Technology Center 54 wks
Development of the IT Center 27 wks
Develop Project Plan 2 wks
Select Land for the Construction of the IT Center 2 wks 2
Procure Construction Materials Building Contractor
Start Construction Labour Team
Construction of the IT Center Labour Team
Interior and Exterior Works Labour Team
Development and Implementation of IT
Developing Requirements for IT Technical Supervisor
Hire IT Development Team Technical Supervisor
Discuss IT Requirements Technical Supervisor
Assign Funds Technical Supervisor
Purchase Hardware Technical Supervisor
Purchase Software Technical Supervisor
Installation of Hardware IT Developer
Installation of Software IT Developer
IT System Development IT Developer
System Testing System Tester
Handover and Go Live IT Developer, System Tester
Sign Off and Closing Project Manager, Technical Supervisor
List of Tasks, Durations and Logical Relationships
The list of tasks, durations and their logical relationships are shown in the following
table.
Task Name Duration Predecessors
Development of Information Technology Center 54 wks
Development of the IT Center 27 wks
Develop Project Plan 2 wks
Select Land for the Construction of the IT Center 2 wks 2
5PROJECT MANAGEMENT
Purchase the Property 4 wks 3
Hire Contractor for the Construction Works 1 wk 4
Develop Blueprint for the IT Center 3 wks 5
Recruit Workers for the Construction of the IT Center 2 wks 6
Procure Construction Materials 2 wks 7
Start Construction 1 wk 8
Construction of the IT Center 7 wks 9
Interior and Exterior Works 3 wks 10
Development and Implementation of IT 27 wks
Developing Requirements for IT 2 wks 11
Hire IT Development Team 2 wks 13
Discuss IT Requirements 2 wks 14
Assign Funds 1 wk 15
Purchase Hardware 1 wk 16
Purchase Software 1 wk 17
Installation of Hardware 3 wks 18
Installation of Software 2 wks 19
IT System Development 6 wks 20
System Testing 5 wks 21
Handover and Go Live 1 wk 22
Sign Off and Closing 1 wk 23
Execution Program (Gantt Chart)
The Gantt chart of the project (execution program) is shown in the following table.
Purchase the Property 4 wks 3
Hire Contractor for the Construction Works 1 wk 4
Develop Blueprint for the IT Center 3 wks 5
Recruit Workers for the Construction of the IT Center 2 wks 6
Procure Construction Materials 2 wks 7
Start Construction 1 wk 8
Construction of the IT Center 7 wks 9
Interior and Exterior Works 3 wks 10
Development and Implementation of IT 27 wks
Developing Requirements for IT 2 wks 11
Hire IT Development Team 2 wks 13
Discuss IT Requirements 2 wks 14
Assign Funds 1 wk 15
Purchase Hardware 1 wk 16
Purchase Software 1 wk 17
Installation of Hardware 3 wks 18
Installation of Software 2 wks 19
IT System Development 6 wks 20
System Testing 5 wks 21
Handover and Go Live 1 wk 22
Sign Off and Closing 1 wk 23
Execution Program (Gantt Chart)
The Gantt chart of the project (execution program) is shown in the following table.
6PROJECT MANAGEMENT
Figure 3: Gantt Chart of the Project
(Source: Created by Author)
Figure 3: Gantt Chart of the Project
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT MANAGEMENT
Estimated Cost as Per WBS and Listed Activities
The estimated cost as per the WBS and the listed activities are shown in the following
table.
Task Name Duration Resource Names Cost
Development of Information Technology Center 54 wks $62,636,400.00
Development of the IT Center 27 wks $38,384,000.00
Develop Project Plan 2 wks Project Manager $24,000.00
Select Land for the Construction of the IT
Center 2 wks Project Manager $24,000.00
Purchase the Property 4 wks Project Manager, Land
Costs[1] $30,048,000.00
Hire Contractor for the Construction Works 1 wk Project Manager $12,000.00
Develop Blueprint for the IT Center 3 wks Project Manager $36,000.00
Recruit Workers for the Construction of the IT
Center 2 wks Building Contractor $10,000.00
Procure Construction Materials 2 wks Building Contractor, Material
Costs[1] $4,010,000.00
Start Construction 1 wk Labour Team $20,000.00
Construction of the IT Center 7 wks Labour Team, Construction
Costs[1] $4,140,000.00
Interior and Exterior Works 3 wks Labour Team $60,000.00
Development and Implementation of IT 27 wks $24,252,400.00
Developing Requirements for IT 2 wks Technical Supervisor $20,000.00
Hire IT Development Team 2 wks Technical Supervisor $20,000.00
Discuss IT Requirements 2 wks Technical Supervisor $20,000.00
Assign Funds 1 wk Technical Supervisor $10,000.00
Purchase Hardware 1 wk Technical Supervisor,
Hardware Costs[1] $510,000.00
Purchase Software 1 wk Technical Supervisor,
Software Costs[1] $510,000.00
Installation of Hardware 3 wks IT Developer $24,000.00
Estimated Cost as Per WBS and Listed Activities
The estimated cost as per the WBS and the listed activities are shown in the following
table.
Task Name Duration Resource Names Cost
Development of Information Technology Center 54 wks $62,636,400.00
Development of the IT Center 27 wks $38,384,000.00
Develop Project Plan 2 wks Project Manager $24,000.00
Select Land for the Construction of the IT
Center 2 wks Project Manager $24,000.00
Purchase the Property 4 wks Project Manager, Land
Costs[1] $30,048,000.00
Hire Contractor for the Construction Works 1 wk Project Manager $12,000.00
Develop Blueprint for the IT Center 3 wks Project Manager $36,000.00
Recruit Workers for the Construction of the IT
Center 2 wks Building Contractor $10,000.00
Procure Construction Materials 2 wks Building Contractor, Material
Costs[1] $4,010,000.00
Start Construction 1 wk Labour Team $20,000.00
Construction of the IT Center 7 wks Labour Team, Construction
Costs[1] $4,140,000.00
Interior and Exterior Works 3 wks Labour Team $60,000.00
Development and Implementation of IT 27 wks $24,252,400.00
Developing Requirements for IT 2 wks Technical Supervisor $20,000.00
Hire IT Development Team 2 wks Technical Supervisor $20,000.00
Discuss IT Requirements 2 wks Technical Supervisor $20,000.00
Assign Funds 1 wk Technical Supervisor $10,000.00
Purchase Hardware 1 wk Technical Supervisor,
Hardware Costs[1] $510,000.00
Purchase Software 1 wk Technical Supervisor,
Software Costs[1] $510,000.00
Installation of Hardware 3 wks IT Developer $24,000.00
8PROJECT MANAGEMENT
Installation of Software 2 wks IT Developer $16,000.00
IT System Development 6 wks IT Developer, IT
Development Costs[1] $23,048,000.00
System Testing 5 wks System Tester $37,000.00
Handover and Go Live 1 wk IT Developer, System Tester $15,400.00
Sign Off and Closing 1 wk Project Manager, Technical
Supervisor $22,000.00
Risk Register using RBS
The risk register for the project using RBS is shown as follows.
Risk Name Chance of Occurrence Impact on Project Risk Rating
Life risks due to various
hazards during
construction
4 4 16
Poor quality materials
used during construction
3 5 15
Cyber attacks during
information system
implementation
5 5 25
Sub-Contractor Schedule for the Project
The sub-contractor schedule for the project is shown in the following table.
Task Name Duration Start Finish
Start Construction 1 wk Tue 10/22/19 Mon 10/28/19
Construction of the IT Center 7 wks Tue 10/29/19 Tue 12/17/19
Installation of Software 2 wks IT Developer $16,000.00
IT System Development 6 wks IT Developer, IT
Development Costs[1] $23,048,000.00
System Testing 5 wks System Tester $37,000.00
Handover and Go Live 1 wk IT Developer, System Tester $15,400.00
Sign Off and Closing 1 wk Project Manager, Technical
Supervisor $22,000.00
Risk Register using RBS
The risk register for the project using RBS is shown as follows.
Risk Name Chance of Occurrence Impact on Project Risk Rating
Life risks due to various
hazards during
construction
4 4 16
Poor quality materials
used during construction
3 5 15
Cyber attacks during
information system
implementation
5 5 25
Sub-Contractor Schedule for the Project
The sub-contractor schedule for the project is shown in the following table.
Task Name Duration Start Finish
Start Construction 1 wk Tue 10/22/19 Mon 10/28/19
Construction of the IT Center 7 wks Tue 10/29/19 Tue 12/17/19
9PROJECT MANAGEMENT
Interior and Exterior Works 3 wks Wed 12/18/19 Fri 1/10/20
Installation of Hardware 3 wks Wed 3/18/20 Tue 4/7/20
Installation of Software 2 wks Wed 4/8/20 Thu 4/23/20
IT System Development 6 wks Fri 4/24/20 Thu 6/4/20
System Testing 5 wks Fri 6/5/20 Fri 7/10/20
Handover and Go Live 1 wk Mon 7/13/20 Fri 7/17/20
Interior and Exterior Works 3 wks Wed 12/18/19 Fri 1/10/20
Installation of Hardware 3 wks Wed 3/18/20 Tue 4/7/20
Installation of Software 2 wks Wed 4/8/20 Thu 4/23/20
IT System Development 6 wks Fri 4/24/20 Thu 6/4/20
System Testing 5 wks Fri 6/5/20 Fri 7/10/20
Handover and Go Live 1 wk Mon 7/13/20 Fri 7/17/20
1 out of 10
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.