Fuellies – Project Management
Table of Contents
Introduction...........................................................................................................................................2
Tasks & Activities.................................................................................................................................2
Timelines, Resources, Team, and Roles................................................................................................2
Gantt chart.........................................................................................................................................7
Approaches............................................................................................................................................8
Deliverables...........................................................................................................................................8
References...........................................................................................................................................10
1
Fuellies - Project Management_2
Fuellies – Project Management
Introduction
Fuellies is an Australian Company that is owned by Woolnorth Limited. The company owns
numerous petrol shares in Australia and currently captures only 20% of the market. The
company has decided to carry out the business applications to improve upon its business
performance and have competitive edge in the market.
Tasks & Activities
There will be numerous tasks involved in the project timeline. These tasks have been allotted
in four broad phases (Ibrahim Alzoubi, Qumer Gill and Al-Ani, 2015). Each of these phases
has their own sub-phases and activities as shown in the diagram below.
Timelines, Resources, Team, and Roles
WBS Task Name Duration Start Finish Predecessor
s Resource Roles
1 Fuellies Business Application 296 days
Mon
06-05-
19
Mon
22-06-
20
1.1 Initiation 20 days Mon
06-05-
Fri 31-
05-19
2
Fuellies Business
Application
Initiation
Analysis of the
current business
scenario and
problems
Stakeholder
meeting to discuss
proposed ideas
Finalization of the
business
application for
implementation
Market analysis
and feasibility
analysis
Approval on the
project
Milestone 1:
Project Approval
Planning and
Analysis
Scope
determination and
planning of
market strategy
for suitable
market
positioning
Target audience
identification
Surveys and
interviews with
the intended users
Development of
the application
requirements
Setting up of the
estimates
Planning of
project areas
Milestone 2:
Project Plan
Application
Design &
Development
Sprint 1
Design diagrams
and architecture
UI Design and
wireframes
Review and
customer
feedback
Milestone 3:
Application Design
Sprint 2
Facebook login
functionality -
Secure login
Chat server
functionality
Review and
customer
feedback
Sprint 3
Google map and
location services
Hosted forum
services
Review and
customer
feedback
Sprint 4
Payment gateway
service
Customizable
profile
Review and
customer
feedback
Sprint 5
Push notifactions
and favorites
Information
services and
analytics
Review and
customer
feedback
Sprint 6
Final round of
customer
feedback and
validations
Implementation of
the changes
Milestone 4:
Source code
Control and
Closure
Internal
management
review and
security checks
Marketing of the
app
Deployment and
app release
Performance
evaluation,
reflection, and
documentation
Milestone 5:
Completion report
Fuellies - Project Management_3
Fuellies – Project Management
19
1.1.1 Analysis of the current
business scenario and problems 5 days
Mon
06-05-
19
Fri 10-
05-19
Business
Analyst ,Project
Manager
1.1.2 Stakeholder meeting to
discuss proposed ideas 2 days
Mon
13-05-
19
Tue 14-
05-19 3
Application
Developer
1,Application
Developer
2,Marketing Analyst
,Project Manager,
UI Designer
1.1.3 Finalization of the business
application for implementation 4 days
Wed
15-05-
19
Mon
20-05-
19
4
Business
Analyst ,Project
Manager
1.1.4 Market analysis and
feasibility analysis 6 days Tue 21-
05-19
Tue 28-
05-19 5
Data
Analyst ,Marketing
Analyst
1.1.5 Approval on the project 3 days
Wed
29-05-
19
Fri 31-
05-19 6 Project Manager
1.1.6 Milestone 1: Project
Approval 0 days Fri 31-
05-19
Fri 31-
05-19 7
1.2 Planning and Analysis 78 days
Mon
03-06-
19
Wed
18-09-
19
1.2.1
Scope determination and
planning of market strategy for
suitable market positioning
6 days
Mon
03-06-
19
Mon
10-06-
19
8
Business
Analyst ,Data
Analyst ,Marketing
Analyst
1.2.2 Target audience
identification 12 days Tue 11-
06-19
Wed
26-06-
19
10 Marketing Analyst
1.2.3 Surveys and interviews with 18 days Thu 27- Mon 11 Marketing Associate
3
Fuellies - Project Management_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Developing the MBFSA Application by Globex
|14
|1918
|420

Project Management: Benefits Administration Software
|4
|811
|299

International Journal of Commerce and Management
|7
|652
|11

Cost Management in Sunshine Coast Airport Construction Project
|21
|2825
|158

Project Management: Royale Pizza Shop Renovation
|16
|2463
|4

Development of CRM System for Medium Organization
|5
|596
|58