Schedule Plan. Milestons. Due Dates. 1. Getting approva

   

Added on  2022-11-10

6 Pages408 Words3 Views
Schedule Plan
Milestons Due Dates
1. Getting approval for the design
2. Completion of procurement and delivery phase
3. Completion of construction phase
4. Completion of installation and painting phase
28-03-19
23-05-19
20-06-19
15-08-19
WBS
ID
Activity
description
Precedence Duration
estimate
Resource Cost
estimate
0 Pizza shop
renovation
6 mons AU$ 40,000.00
1 Design phase 1 mon AU$ 5,000.00
1 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_1
1.1 Undertaking
meeting with the
workers of the store
1 day Project management
consultant
AU$ 500.00
1.2 Researching the
problem
2 4 days Project manager AU$ 500.00
1.3 Identifying
solution
3 5 days Project management
consultant, Project manager
AU$ 500.00
1.4 Creating
schematic design
4 10 days Designer AU$ 3,500.00
1.5 Milestone 1:
Getting approval for
the design
5 0 days AU$ 0.00
2 Procurement
and delivery phase
2 mons AU$ 18,000.00
2.1 Determining
products and
5 5 days Procurement manager AU$ 400.00
2 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_2
services
2.2 Hiring suppliers 8 9 days Procurement manager,
Project management
consultant
AU$ 300.00
2.3 Buying different
types of materials
and equipment
9 10 days Supplier AU$ 12,000.00
2.4 Performing
quality assurance
10 8 days Quality analyst AU$ 4,300.00
2.5 Analyzing the
results and margins
11 8 days Procurement manager,
Project management
consultant
AU$ 1,000.00
2.6 Milestone 2:
Completion of
procurement and
delivery phase
12 0 days AU$ 0.00
3 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Renovation of Royale Pizza
|18
|3090
|173

Schedule Plan. Milestons. Due Dates. 1. Proper design f
|6
|451
|11

Schedule Plan. Milestons. Due Dates. 1. Getting approva
|6
|444
|11

Project Management: Royale Pizza
|17
|2562
|331

Project Management: Schedule, Budget, Risk Management
|18
|2574
|78

Schedule Plan. Milestons. Due Dates. Milestone 1: Desig
|5
|343
|2