Schedule Plan. Milestons. Due Dates. 1. Getting approva

Prepare relevant documentation for project schedule, resources, budget, and risk for a case study project.

6 Pages444 Words11 Views
   

Added on  2022-11-11

About This Document

Please go through the following pdfs and present the assignment accordingly. I'm attacting the assignment instructions and reporting forms which you need to use in the assignment and also Case study and marking rubric. please note this is assignment 2 which is based on Assignment 1 which ill provide you the Order ID. Only use the reporting as per requirement......no need to use all!!

Schedule Plan. Milestons. Due Dates. 1. Getting approva

Prepare relevant documentation for project schedule, resources, budget, and risk for a case study project.

   Added on 2022-11-11

ShareRelated Documents
Schedule Plan
Milestons Due Dates
1. Getting approval for the project design that is developed
2. Getting approval for construction phase
3. Completion of construction phase
4. Completion of installation and painting phase
28-03-19
23-05-19
20-06-19
15-08-19
WBS
ID
Activity
description
Precedence Duration
estimate
Resources Cost
Estimate
0 Renovation of
Royale Pizza shop
6 mons AU$
40,000.00
1 Design stage 1 mon AU$ 5,000.00
1.1 Conducting 1 day Project management AU$ 200.00
1 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_1
meeting with the
designer
consultant
1.2 Undertaking
sketch studies
2 4 days Designer, Project
management consultant
AU$ 300.00
1.3 Undertaking
preliminary design for
shop renovation
3 5 days Designer AU$ 1,500.00
1.4 Creating detailed
design
4 10 days Contractor, Designer AU$ 3,000.00
1.5 Milestone 1:
Getting approval for
the project design that
is developed
5 0 days AU$ 0.00
2 Procurement and
delivery phase
2 mons AU$
18,000.00
2.1 Determining 5 8 days Procurement manager, AU$ 200.00
2 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_2
suppliers and other
construction
contractors
Project management
consultant, Project
manager
2.2 Recommending
vendors
8 5 days Procurement manager,
Project management
consultant
AU$ 300.00
2.3 Purchasing orders
and executing
contracts
9 8 days Equipment suppliers AU$ 7,000.00
2.4 Purchasing of deep
fryers, boilers and
dough roller
10 9 days Equipment suppliers AU$ 4,000.00
2.5 Managing and
expediting delivery of
goods
11 10 days Procurement manager,
Supervisor
AU$ 6,500.00
2.6 Milestone 2: 12 0 days AU$ 0.00
3 | P a g e
Schedule Plan. Milestons. Due Dates. 1. Getting approva_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Schedule Plan. Milestons. Due Dates. 1. Proper design f
|6
|451
|11

Project Management: Schedule, Budget, Risk Management
|18
|2574
|78

Project Management: Royale Pizza
|17
|2562
|331

Schedule Plan. Milestons. Due Dates. 1. Getting approva
|6
|408
|3

Budget Estimation.
|4
|483
|2

Project Management for Renovation of Royale Pizza
|18
|3090
|173