logo

BNV6047 Project Management

   

Added on  2021-05-31

19 Pages3818 Words40 Views
BNV6047 Project Management
Academic Year 2018
CWRK001 – Project Stakeholder and Risk Management
Name of the University
Name of Student
ID of Student
Dated: April 26, 2018
Total Word count =
BNV6047 Project Management_1
Contents
Background........................................................................................................... 2
Project Review.................................................................................................... 2
Project Schedule................................................................................................. 2
Project Budget.................................................................................................... 3
Rationale............................................................................................................... 3
Project Organization.............................................................................................. 4
Stakeholder Analysis and Management.................................................................4
Sustainability and Building Performance...............................................................6
Sustinability........................................................................................................ 6
Project performance management plan.............................................................7
Safety & Health Management................................................................................ 8
Risk management.................................................................................................. 8
Communications management............................................................................11
Conclusions.......................................................................................................... 12
References........................................................................................................... 12
BNV6047 Project Management_2
Background
This project is about an early stage residential construction work, which involves
development processes from laying the road for access to the site until the construction of the
Fit gates. The project is expected to take 5 months to complete from June to October 2018.
The project would be completed within the allotted budget of $618,997 and a contingency
amount of $61900 would be kept for handling emergencies.
Project Review
In the proposal stage of the project, a network diagram was prepared and critical paths were
calculated to arrive at two alternative solutions.
Project Schedule
The critical path was A-B-C-E-F-G-H and the project had the following schedule defined:
Task Name Early Start Late Start Early Finish Late Finish
Total
Slack
(Sirees
ha &
Shanka
r, 2010)
Free
Slack
Early stage
residential
construction
project
Mon 02-04-
18
Mon 02-04-
18
Mon 06-08-
18
Mon 06-08-
18 0 days 0 days
A - Lay access
road
Mon 02-04-
18
Mon 02-04-
18
Wed 18-04-
18
Wed 18-04-
18 0 days 0 days
B - Erect fence Thu 19-04-18 Thu 19-04-18 Mon 30-04-
18
Mon 30-04-
18 0 days 0 days
C - Demolition of
existing structure Tue 01-05-18 Tue 01-05-18 Thu 17-05-18 Thu 17-05-18 0 days 0 days
D - Disposal of
demolished
material, off site
Fri 18-05-18 Wed 01-08-
18
Wed 23-05-
18
Mon 06-08-
18 64 days 64 days
E - Top soil
removal Fri 18-05-18 Fri 18-05-18 Thu 07-06-18 Thu 07-06-18 0 days 0 days
F - Hard-core
filling and
compacting
Fri 08-06-18 Fri 08-06-18 Mon 25-06-
18
Mon 25-06-
18 0 days 0 days
BNV6047 Project Management_3
G - Erect site
accommodation Tue 26-06-18 Tue 26-06-18 Thu 12-07-18 Thu 12-07-18 0 days 0 days
H - Fit out Fri 13-07-18 Fri 13-07-18 Mon 06-08-
18
Mon 06-08-
18 0 days 0 days
I - Electrical
services Fri 18-05-18 Fri 06-07-18 Thu 24-05-18 Thu 12-07-18 42 days 42 days
J - Temporary
drain connection Fri 18-05-18 Tue 26-06-18 Mon 04-06-
18 Thu 12-07-18 33 days 33 days
K - Excavate and
lay water service Fri 18-05-18 Mon 02-07-
18 Tue 29-05-18 Thu 12-07-18 38 days 38 days
L - Fit gates Fri 13-07-18 Mon 30-07-
18 Fri 20-07-18 Mon 06-08-
18 14 days 14 days
a) It was found that increasing duration of electrical activity was not going to affect the
overall project schedule s the activity had a 42 days float and thus, its duration was
increased to revise the schedule. An alternative solution was use of this time for
reduction in the project schedule by 40 days, which would change the critical path to
A B C D E F G H and L. However, this would require additional resources to be
recruited. Reduction in time would have major commercial benefits, as site work
would be reduced by 14 days.
Project Budget
Project Budget is $618,997 and a contingency amount of $61900 would be added to it for
approval. The table below shows the distribution of the total funds into each activities of
construction that would be carried out on the project:
BNV6047 Project Management_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BNV6047 Project Management Assignment
|6
|1309
|304

Project Management Techniques
|8
|2107
|64

Project Management Schedule and Cost Estimation for Construction Project
|10
|955
|170

Essendon & Buckley Street Level Crossing Removal Project Scope Statement
|11
|1455
|267

Project Management Isn't Just For Project
|10
|1445
|19

Project Management: Benefits Administration Software
|4
|811
|299