Running head: INFORMATION SYSTEM Information System Name of the Student: Name of the Organization: Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 INFORMATION SYSTEM Executive Summary: The report deals with the case study of the You Can Fit In’ organization who needs a new information system for their business procedures. The details of the implementation of the new information system for the organization has been described in the report. The feasibility study and cost benefit analysis of the development of the system has been described in this report and important illustrations have been included in the report in context of the discussion provided.
2 INFORMATION SYSTEM Table of Contents Part A.................................................................................................................................4 Introduction................................................................................................................................4 Background Information........................................................................................................4 Organizational Chart..............................................................................................................4 Business Functions.................................................................................................................5 System Vision Document...........................................................................................................5 Problem description...............................................................................................................5 System Capabilities................................................................................................................6 Business Benefits...................................................................................................................6 Project Management...................................................................................................................7 Gantt Chart.............................................................................................................................7 CPM Chart.............................................................................................................................8 Project Schedule and budget..................................................................................................8 Cost Benefit Analysis...............................................................................................................10 Feasibility Study.......................................................................................................................12 Part B................................................................................................................................13 Fact Finding.............................................................................................................................13 Interview..............................................................................................................................13 UML Models............................................................................................................................14 Use Case Diagram................................................................................................................14 Use Case Description...........................................................................................................15
3 INFORMATION SYSTEM ER Diagram..........................................................................................................................16 Model Class Diagram...........................................................................................................17 System Sequence Diagram...................................................................................................17 Recommendations....................................................................................................................17 Conclusion................................................................................................................................18 Bibliography.............................................................................................................................19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 INFORMATION SYSTEM Part A Introduction Background Information The report is used for the description of the case study of the ‘You Can Fit In’ organization. The organization owns a number of branches across the whole of Australia and the company is planning for further expansion in the field by deployment of a new Supercentre at Gold Coast in the State of Queensland. There is future planning of deploying the expansion across the other cities such as Brisbane as well. OnAllAccounts, a popular accounting package is currently in use by the organization for the management of the receivables, payables and the general ledger for the company. It is believed that the new supercentre would be requiring a new information system for the development of the newer operations deployed by them. An IT firm named Gates to the job has been hired and Nina Stay has been appointed as the consultant for the organization who would be monitoring the development of the new information system. Organizational Chart Adam Apple is the CEO of the organization, who is assisted by three managers, Donald,thefinancemanager,SallytheSalesandMarketingManagerandChiathe operational manager. In addition to this, there are 13 managers for the each of the centres of the organization. in addition to this there are a number of employees associated with different centres of the company. The organizational chart of the You Can Fit In organization has been described below:
5 INFORMATION SYSTEM Business Functions The main business functions performed in the organization are mainly done in the Microsoft Office package and products such as the Word and Excel are used extensively by theorganizationfortheiroperations.TheMembershiplistsandthewordprocessing procedures are currently performed in the organization. In addition to this, each of the centre of the organization employs a number of employees and the staffs are required to handle a numberofproceduresthatattendingtheshops,cleaningandtheaerobicsandyoga instructions. The company also provides a large exercise area along with the equipment that are state of art along with facilities such as swimming pool, sporting goods shop, health food store and snack bars. System Vision Document Problem description The OnAllAccounts Accounting package is used by the organization currently for the management of all the accounting related processes of the organization. The main problems identified for the current system in the organization, is that there is a considerable amount of increased size in the organization and there has been increased amount of complexity for the new operations. There are basic services provided by the current system, however there is absence of child-fitness programmes as it has been intended here. In addition to this, online access has never been offered to the organization and there is a need for the web-based access which is to be available on 24/7 basis. The basic membership level used in the system also requires proper categorization, such as basic members and full members. In addition to this, there are a number of options that the customers would be able to do but there is currently no facility that would be able to capture the body mass of the people doing certain activities.
6 INFORMATION SYSTEM System Capabilities The new information system developed for the You Can Fit In organization, would provide automated solutions to various processes of the organization. The capabilities of the new information system developed for the organization is described below: ï‚·The system would be able to provide the organization the ability to store all the data at a single datacentre. ï‚·The system would help the organization in mitigating the conflicts that are taking place within the company by providing an excellent mode of communication facility within it. ï‚·The system would be able to measure the Bod mass index of the customers who are enrolled into the system and perform different type of tasks in the gym. ï‚·The system would be able to integrate with the social media and help the organization in spreading their advertisement via the media. ï‚·The system would introduce swipe card into the organization which would help in keeping track of the check in and check out time of the users. Business Benefits The primary benefit that the new information system would provide to the You Can Fit In organization is that they would provide the organization with an opportunity to enhance the process that would assist the user using the system to gain information about any type of task that is to be performed in the system. The system would provide the most appropriate and actual data to the users, and additionally the data to the users would be delivered in the format required by them. There are other benefits such as scalability and ability to expand as the supercentre would be storing data of a larger amount than that of the previous centre that the organization held. In addition to this the implementation of the system would also
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 INFORMATION SYSTEM improve the customer satisfaction level towards the organization and increase the overall reputation of the organization. The system would provide the organization with the ability to classify the different members of the organization into different groups and provide them with facilities accordingly. Project Management Gantt Chart
8 INFORMATION SYSTEM CPM Chart Project Schedule and budget The schedule and the budget for the project which is to be developed is provided below: Task NameDurationStartFinishCost New Information System34 daysMon 14-01-19Thu 28-02-19$7,522.00 Initiation5 daysMon 14-01-19Fri 18-01-19$720.00 Define outcomes1 dayMon 14-01-19Mon 14-01-19$120.00 scope of project1 dayTue 15-01-19Tue 15-01-19$120.00 project vision document2 daysTue 15-01-19Wed 16-01-19$240.00 Gatheraccurate performance data for existing systems and processes 2 daysThu 17-01-19Fri 18-01-19$240.00 Planning6 daysWed 16-01-19Wed 23-01-19$1,032.00
9 INFORMATION SYSTEM Form Project team2 daysWed 16-01-19Thu 17-01-19$240.00 Establish budget2 daysMon 21-01-19Tue 22-01-19$240.00 Develop implementation plan 2 daysMon 21-01-19Tue 22-01-19$432.00 communication plan1 dayWed 23-01-19Wed 23-01-19$120.00 Designing6 daysFri 18-01-19Fri 25-01-19$560.00 Working group meetings2 daysFri 18-01-19Mon 21-01-19$320.00 Governance committee meetings 1 dayThu 24-01-19Thu 24-01-19$120.00 Communicationto organization 1 dayFri 25-01-19Fri 25-01-19$120.00 Development9 daysMon 28-01-19Thu 07-02-19$1,664.00 project kick-off meeting1 dayMon 28-01-19Mon 28-01-19$312.00 gap analysis2 daysTue 29-01-19Wed 30-01-19$240.00 Design training programs1 dayThu 31-01-19Thu 31-01-19$216.00 Design processes and tools for optimization 1 dayThu 31-01-19Thu 31-01-19$216.00 Establish data centre3 daysThu 31-01-19Mon 04-02-19$240.00 Install and configure server environment 2 daysTue 05-02-19Wed 06-02-19$320.00 riskandchange1 dayThu 07-02-19Thu 07-02-19$120.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 INFORMATION SYSTEM management plan Deployment12 daysFri 08-02-19Mon 25-02-19$3,066.00 Procure items2 daysFri 08-02-19Mon 11-02-19$320.00 Install hardware and software 2 daysFri 08-02-19Mon 11-02-19$970.00 Develop User interface6 daysTue 12-02-19Tue 19-02-19$816.00 integrate with data centre10 daysTue 12-02-19Mon 25-02-19$960.00 Maintenance3 daysTue 26-02-19Thu 28-02-19$480.00 Implement monitoring process and tools 1 dayTue 26-02-19Tue 26-02-19$120.00 Monitoruseand maintenance needs 1 dayWed 27-02-19Wed 27-02-19$120.00 Finalize service-level agreements and maintenance contracts 1 dayThu 28-02-19Thu 28-02-19$120.00 Establishbackup procedures 1 dayThu 28-02-19Thu 28-02-19$120.00 Cost Benefit Analysis The cost benefit analysis regarding the development of a new information system for the ‘You Can Fit In’ organization has been described below:
12 INFORMATION SYSTEM Feasibility Study The project to be conducted is used for the development and expansion of the current systems of the You can fit in organization and it can be easily analysed that the system would be increasing the overall reputation of the company and would be enhancing the overall efficiency of the business procedures of the organization. Hence, it system that is to be developed for the company can be termed a feasible one.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 INFORMATION SYSTEM Part B Fact Finding Factfindingistheprocessthatisusedfortheidentificationofthesystem requirements and the preferences of the users who would be using the system. The data collection and information gathering methods are also considered under the fact finding process. For the fact finding procedure interview was chosen as the mode for fact finding for the development of the new information system. Interview One of the main research tools for fact finding technique is interviewing. The process is very important in refining the results of the other procedures such as questionnaires and information review. The process is used in various type of workplace methods. The main stakeholder who would be subjected to the interview are the managers of different centres of the organization and the CEO of the organization.
14 INFORMATION SYSTEM UML Models Use Case Diagram
15 INFORMATION SYSTEM Use Case Description Use CaseDescription Log InThe Staffs, Trainers and the members would be able to log into the system. RegisterThe registration process is used for the registration of the staffs into the system. EnrolmentThe members in the system are to be enrolled in to the system. BMI recordThe BMI of the members are to be recorded in the system. Add InfoThe info about the trainers are to be added to the system by the administrator. Update InfoThe info about the trainers are to be updated to the system by the administrator. Delete InfoThe info about the trainers are to be deleted from the system by the administrator. Handle AccountsTheaccountsdepartmentwouldbelookedoverbythe administrator. Manage MembershipThe memberships would be managed by the administrator. Manage PaymentsThe payments would be managed by the administrator. Log OutThe staffs and the trainers would be able log out from the system when their work is completed.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
17 INFORMATION SYSTEM Model Class Diagram System Sequence Diagram Recommendations For the development of the information system, the following recommendations are directed towards the, CEO of the company:
18 INFORMATION SYSTEM Data integrity: The system should be making sure that no data from the system are leaked out or altered. Any discrepancies would result in widespread deficits for the organization and hence this is to be considered during the development of the system. Access Control: The access control in the system should be defined efficiently so that, any unauthorizeduserssonotgaincontroltoinformationthatisrestricted.Hencethe administrator of the system should be having the control to the accessibility to the functions of the system. Conclusion For conclusion it can be said that the development of a new information system for the You can fit in organization is very feasible and the dev elopement of the system would be very beneficial for the organization. The entire process of development of the system and the analysis of the system have also been described efficiently in this report. Additionally, some illustrations and data has been provided in the report to aid the discussion on the project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19 INFORMATION SYSTEM Bibliography Al Shobaki, M.J. and Naser, S.S.A., 2016. Performance development and its relationship to demographic variables among users of computerized management information systems in Gaza electricity Distribution Company. Dumais, S., Cutrell, E., Cadiz, J.J., Jancke, G., Sarin, R. and Robbins, D.C., 2016, January. Stuff I've seen: a system for personal information retrieval and re-use. InACM SIGIR Forum (Vol. 49, No. 2, pp. 28-35). ACM. Erich, F., Amrit, C. and Daneva, M., 2014, December. A mapping study on cooperation between information system development and operations. InInternational Conference on Product-Focused Software Process Improvement(pp. 277-280). Springer, Cham. Hanseth, O. and Lyytinen, K., 2016. Design theory for dynamic complexity in information infrastructures: the case of building internet. InEnacting Research Methods in Information Systems(pp. 104-142). Palgrave Macmillan, Cham. Horita, F.E., de Albuquerque, J.P., Degrossi, L.C., Mendiondo, E.M. and Ueyama, J., 2015. Development of a spatial decision support system for flood risk management in Brazil that combines volunteered geographic information with wireless sensor networks.Computers & Geosciences,80, pp.84-94. Laudon, K.C. and Laudon, J.P., 2015.Management information systems(Vol. 8). Prentice Hall. Laudon, K.C. and Laudon, J.P., 2016.Management information system. Pearson Education India. Lee, J., Kao, H.A. and Yang, S., 2014. Service innovation and smart analytics for industry 4.0 and big data environment.Procedia Cirp,16, pp.3-8.
20 INFORMATION SYSTEM Liu, Y., Zhan, L., Zhang, Y., Markham, P.N., Zhou, D., Guo, J., Lei, Y., Kou, G., Yao, W., Chai, J. and Liu, Y., 2016. Wide-area-measurement system development at the distribution level: An FNET/GridEye example.IEEE Trans. Power Del,31(2), pp.721-731. Lu, J., Wu, D., Mao, M., Wang, W. and Zhang, G., 2015. Recommender system application developments: a survey.Decision Support Systems,74, pp.12-32. Lu, Y., Nakicenovic, N., Visbeck, M. and Stevance, A.S., 2015. Five priorities for the UN sustainable development goals.Nature,520(7548), pp.432-433. Oinas-Kukkonen, H. and Harjumaa, M., 2018. Persuasive systems design: key issues, process modelandsystemfeatures.InRoutledgeHandbookofPolicyDesign(pp.105-123). Routledge. Stein, E., Taskaeva, N. and Chibisova, E., 2016. Methodological Aspects of the Creation of Information-and-technological Complexes Within the Investment Projects as a Factor of the Urban Territory Development.Procedia Engineering,165, pp.1410-1416. Wiegmann, D.A. and Shappell, S.A., 2017.A human error approach to aviation accident analysis: The human factors analysis and classification system. Routledge. Yuan, X., Roundy, J.K., Wood, E.F. and Sheffield, J., 2015. Seasonal forecasting of global hydrologic extremes: system development and evaluation over GEWEX basins.Bulletin of the American Meteorological Society,96(11), pp.1895-1912.