Change Management in Project Execution and Control
Verified
Added on  2022/11/13
|8
|1517
|133
AI Summary
This report explores the process of project change management with specific reference to the case study provided. It discusses the implementation of the change management concepts in the provided case study in order to enhance the quality of the project by solving the scope, time and budget related problems that have been highlighted.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: PROJ6003 PROJECT EXECUTION AND CONTROL Assessment 1: Change Management (Part B: Change Control) Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJ6003 PROJECT EXECUTION AND CONTROL Executive Summary In this report, the process of project change management has been explored and discussed with specific reference to the case study provided. Project change management process plays an important role in helping project managers to control the progress of the project and ensure it remains within the overall scope that has been defined during planning. However, the change management process must go through detailed review process and change request must be submitted to the authority for approval to go ahead.
2PROJ6003 PROJECT EXECUTION AND CONTROL Table of Contents Introduction......................................................................................................................................3 Processes Involved in Submitting a Request...................................................................................3 Changes Required and Impact on Scope, Time, Cost and Quality..................................................4 Satisfy Change Request and Risks Associated................................................................................5 Change Request Form......................................................................................................................6 Conclusion.......................................................................................................................................6 References........................................................................................................................................7
3PROJ6003 PROJECT EXECUTION AND CONTROL Introduction Change management is defined as a project management process by which some changes are incorporated within a project in order to ensure the project is on track as per the scope and control the budget and schedule to prevent overshoot. Change management is a detailed process in which the existing situation is first analysed, changes are suggested and requested to the project governing body and once the proposed changes are approved, the team moves forward to implement the changes (Kerzner 2018). One of the main requirements of change management is to analyse the feasibility of the proposed changes in the context of the project. If the changes are not feasible for the project, they should not be implemented as they will cause further problems for the project. The analysis of change management process in project management is the primary purpose of this report as it also discusses implementation of the change management concepts in the provided case study in order to enhance the quality of the project by solving the scope, time and budget related problems that have been highlighted. Processes Involved in Submitting a Request From the understanding of the case study provided, it can be said that in order to implement any changes in the project, it is important to submit a change request to the project governing body or the project manager (Heagney 2016). Once the project team members identify that the project requires some changes in scope and other aspects in order to ensure the final milestone of the project is reached, a detailed change request must be created. The change requirement can also be identified by the project manager who can also create the change request
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJ6003 PROJECT EXECUTION AND CONTROL document and then submit the same to the project authority. In large scale projects like the ones mentioned in the case study provided, the changes have significant and long term implications on the overall project and organisational performance and strategic directions (Bresnen 2016). Hence, the change requests are to be developed with every minute details and proper reasoning as to why these changes are necessary and how these changes will benefit the project as a whole. Generally, in order to submit a change request, a change request form (that is already made available to the project teams and managers) is filled with all relevant details before submitting them to the governing body / authority. Changes Required and Impact on Scope, Time, Cost and Quality As per the case study, in spite of successful project planning with all relevant details agreed between the parties, problems have started arising right from the start of the project. The main problem that the project is facing is that it is sensitive in nature and it is not managed efficiently by the project manager (Donovan 2018). There has also been discrepancies in the estimation of work force calculation as due to various delays made by vendors and other external parties, the project work has also been delayed significantly. In this regard, the main change required is to change the vendors and other external parties that are causing delays in the project. It was mentioned on the contract that the external parties must deliver resources or services on time or they will be financially penalised. The same can be imposed and overall, the contracts can be terminated if the external parties still fail to live up to the terms of the initial contract. The proposed change will have some significant impact on scope, time, cost and quality of the project. Already delayed by the external parties, the project will face further delay if the
5PROJ6003 PROJECT EXECUTION AND CONTROL contract changing process is initiated. The penalisation process will help to recover some of the lost expenses of the company but the wasted manual working hours cannot be recovered and the project will be further delayed, resulting in further cost overshoot. In addition, with major changes in the project, the quality can also be hampered and may not be able to fulfil the quality standards as set during the planning of the project. Satisfy Change Request and Risks Associated In order to satisfy change requests, it is important to analyse the feasibility of such changes in the project. Furthermore, it is also essential to determine whether the proposed changes comply with the project management and execution policies that are set by the organisation (Cameron and Green 2015). It has been seen in many cases that the changes in the project, although beneficial to the project and / or requested by the project client, are rejected by the governing body as they do not comply with the standard policies and guidelines of project management of the organisation. Again, in many cases, it has been reported that the project team members undertake the changes without authorisation as they are beneficial to the project but they have been penalised because the changes do not comply with the standards and guidelines. In addition to the penalty from the authority, there are also various risks associated with the change requests. If the changes are not feasible in the project considering the long term strategies of the organisation, then the implementation of these changes will cause major problems for the organisation and the governing person who has approved the changes will face strict actions for failing to understand the long term implications of the changes (Badewi 2016). Another major risk involved includes significant over-expenses as any changes in project require additional investment from the project management body.
6PROJ6003 PROJECT EXECUTION AND CONTROL Change Request Form A change request form from the workplace is shown as follows. Changes Required: Recruitment of 10 new team members in order to manage the extra work load on the current team Reason for Proposed Change: There has been some errors in resource usage estimation and the current team members are facing extra work load everyday Change Request Analysis: To be filled by Supervisor Change Request Approval: To be filled by Authority Member Change Request Tracking: To be filled by Supervisor Change Request Closing: To be filled by Authority Member Conclusion In any project, especially the large scale ones, change managementis a very detailed process that needs to be properly monitored, evaluated and reviewed before approving the changes in the project. Before providing the approval, the governing body has to understand the implications, risks and potential penalties if the changes do not bring success to the project. Furthermore, it is also to be ensured that the changes comply with the organisational policies and guidelines before they are approved or implemented in the project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJ6003 PROJECT EXECUTION AND CONTROL References Badewi, A., 2016. The impact of project management (PM) and benefits management (BM) practicesonprojectsuccess:Towardsdevelopingaprojectbenefitsgovernance framework.International Journal of Project Management,34(4), pp.761-778. Bresnen, M., 2016. Institutional development, divergence and change in the discipline of project management.International journal of project management,34(2), pp.328-338. Cameron, E. and Green, M., 2015.Making sense of change management: A complete guide to the models, tools and techniques of organizational change. Kogan Page Publishers. Donovan, G.O., 2018. Creating a culture of partnership between Project Management and Change Management.Proj. Manag. World J.,7(1), pp.1-11. Heagney, J., 2016.Fundamentals of project management. Amacom. Kerzner, H., 2018.Project management best practices: Achieving global excellence. John Wiley & Sons.