Running head: PROJECT MANAGEMENT
Project Management
Name of Student-
Name of University-
Author’s Note-

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Running head: PROJECT MANAGEMENT
1. WBS Charts
i. Gantt Chart
Task Name Duration Start Finish Predecessors Resource Names Cost
Cloud Implementation 524 days Mon 1/04/19 Thu 1/04/21 $745,200.00
Project Initiation 34 days Mon 1/04/19 Thu 16/05/19 $34,400.00
Research on
Stakeholders
7 days Mon 1/04/19 Tue 9/04/19 $7,840.00
Stakeholder
Interviews
5 days Mon 1/04/19 Fri 5/04/19
Business Analyst, Business
Coordinator, Project Manager
$5,600.00
Stakeholder Analysis 2 days Mon 8/04/19 Tue 9/04/19 3
Business Analyst, Business
Coordinator ,Project Manager
$2,240.00
Implementation Plan 27 days
Wed
10/04/19
Thu 16/05/19 $26,560.00
Selecting the Process 10 days Wed 10/04/19 Tue 23/04/19 4 Business Coordinator, $10,400.00
Document Page
1PROJECT MANAGEMENT
Database Administrator,
Financial manager
Planning Project
Management
9 days Wed 24/04/19 Mon 6/05/19 6,4
Business Analyst, Project
Manager
$7,200.00
Project Sign In 8 days Tue 7/05/19 Thu 16/05/19 7
Business Analyst, Business
Coordinator, Project Manager
$8,960.00
Designing Phase 40 days Fri 17/05/19 Thu 11/07/19 $41,600.00
Modelling the
processes that are
completed
15 days Fri 17/05/19 Thu 6/06/19 8
Business Analyst, Business
Coordinator, Database
Administrator
$14,400.00
Measuring the
performance metrices
15 days Fri 7/06/19 Thu 27/06/19 10
Database Administrator,
Financial manager,
Procurement Manager
$16,800.00
Documenting the
model
10 days Fri 28/06/19 Thu 11/07/19 11 Business Analyst, Database
Administrator, Procurement
$10,400.00
Document Page
2PROJECT MANAGEMENT
Manager
Modelling Phase 185 days Fri 12/07/19 Thu 26/03/20 $245,900.00
Communication plan
for stakeholder
20 days Fri 12/07/19 Thu 8/08/19 12
Business Analyst, Business
Coordinator, Database
Administrator, Financial
manager, Procurement
Manager
$35,200.00
Detailed Execution
plan
20 days Fri 9/08/19 Thu 5/09/19 14,11
Database Administrator,
Financial manager,
Procurement Manager,
Quality analyst, Software
Requirements[1]
$28,700.00
Manufacturing
Resource Layer
15 days Fri 6/09/19 Thu 26/09/19 15 Business Analyst, Business
Coordinator, Database
Administrator, Quality
$19,500.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
3PROJECT MANAGEMENT
analyst, Software
Requirements[1]
Manufacturing
Executing layer
20 days Fri 27/09/19 Thu 24/10/19 16
Business Analyst, Business
Coordinator, Database
Administrator, Procurement
Manager, Software
Requirements[1]
$28,700.00
Manufacturing
Planning Layer
30 days Fri 25/10/19 Thu 5/12/19 17
Business Coordinator,
Database Administrator,
Financial manager, Quality
analyst
$38,400.00
Manufacturing
Management Layer
15 days Fri 6/12/19 Thu 26/12/19 18 Business Analyst, Business
Coordinator, Database
Administrator, Hardware
Requirements[1],Procuremen
t Manager, Quality analyst,
$27,000.00
Document Page
4PROJECT MANAGEMENT
Software Requirements[1]
Redesigning the
process models
25 days Fri 27/12/19 Thu 30/01/20 19
Cables[1],Database
Administrator, Financial
manager, Procurement
Manager, Software
Requirements[1],Tester
$36,000.00
Updated the business
case
30 days Fri 31/01/20 Thu 26/03/20 20
Business Analyst, Database
Administrator, Financial
manager, Procurement
Manager, Project Manager,
Quality analyst
$32,400.00
Developing and
executing phase
245 days Fri 31/01/20 Thu 7/01/21 $363,300.00
Developing overveiw
of the cloud solution
30 days Fri 27/03/20 Thu 7/05/20 21 Business Analyst, Business
Coordinator, Database
$60,000.00
Document Page
5PROJECT MANAGEMENT
Administrator, Financial
manager, Procurement
Manager, Quality analyst
Finalyzing the software
documentation
25 days Fri 31/01/20 Thu 5/03/20 20
Business Coordinator,
Database Administrator,
Financial manager, Hardware
Requirements[1],Quality
analyst, Tester
$39,500.00
Implementing Phase 50 days Fri 8/05/20 Thu 16/07/20 24,23
Business Analyst,
Cables[1],Database
Administrator, Financial
manager, Procurement
Manager, Tester
$84,500.00
Testing of User
acceptance
50 days Fri 17/07/20 Thu 24/09/20 25 Business Analyst, Business
Coordinator, Project
Manager, Software
$69,500.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
6PROJECT MANAGEMENT
Requirements[1],Tester
Training the staffs 35 days Fri 25/09/20 Thu 12/11/20 26
Business Analyst, Hardware
Requirements[1],Project
Manager, Software
Requirements[1],Tester
$39,400.00
Rollout the Cloud in
the organization
40 days Fri 13/11/20 Thu 7/01/21 27
Business Analyst, Database
Administrator, Financial
manager, Project Manager,
Quality analyst
$70,400.00
Monitoring Phase 60 days Fri 8/01/21 Thu 1/04/21 $60,000.00
Monitoring the KPI's 30 days Fri 8/01/21 Thu 18/02/21 28
Procurement Manager,
Project Manager
$26,400.00
Delivery of the service
in time
30 days Fri 19/02/21 Thu 1/04/21 30 Procurement Manager,
Project Manager, Quality
$33,600.00
Document Page
7PROJECT MANAGEMENT
analyst
Project Signoff 0 days Thu 1/04/21 Thu 1/04/21 31
Financial manager,
Procurement Manager,
Project Manager
$0.00
Document Page
8PROJECT MANAGEMENT
ii. Network Diagram

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
9PROJECT MANAGEMENT
iii. Resource Graphs
Document Page
10PROJECT MANAGEMENT
2. The project will take 524 days to complete the implementation of the cloud in MQ manufacturing. The network diagram showing
the critical task is shown below.
Document Page
11PROJECT MANAGEMENT
The critical path indicates the total minimum amount of time that is taken to complete the task. The critical path helps a project
manager to complete the task in the shortest possible way.
To find out the critical path of a network, the early start time and the early finish time is calculated first. The duration of the
task is added to the early start time of an activity. This is known as forward pass calculation. After ending the last activity of the

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
12PROJECT MANAGEMENT
network, there comes a backward pass calculation where the late start and late finish is calculated. Late finish is calculated from the
previous late start and the duration is subtracted from the late finish to get the late start.
There is a slack calculated in the network diagram that states the critical path of the solution. The critical path is taken where
the slack of the activity is 0. The slack is calculated as early start – late start.
3. The cost of the project is determined by allocating resources to all the defined activities. The time frame of the activity is
determined a stated in the project requirement. It takes almost 2 years to implement the project in MQ manufacturing. The staffs were
allocated as per the requirement of the activity that is to be completed for doing the project.
Document Page
13PROJECT MANAGEMENT
Bibliography
[1] S., Tonchia. Project Time Management. In Industrial Project Management (pp. 117-129). Springer, Berlin, Heidelberg, 2018.
[2] D., Lock. The essentials of project management. Routledge, 2017.
[3] K., Schwalbe. Information technology project management. Cengage Learning, 2015.
[4] J., Talman. August. Enhancing Teamwork in Group Projects by Applying Principles of Project Management. In Innovations in
Teaching & Learning Conference Proceedings (Vol. 10, pp. 3-35), 2018.