Running head: PROJECT MANAGEMENT
Project Management
Name of Student-
Name of University-
Author’s Note-
Project Management_1
Running head: PROJECT MANAGEMENT
1. WBS Charts
i. Gantt Chart
Task Name Duration Start Finish Predecessors Resource Names Cost
Cloud Implementation 524 days Mon 1/04/19 Thu 1/04/21 $745,200.00
Project Initiation 34 days Mon 1/04/19 Thu 16/05/19 $34,400.00
Research on
Stakeholders
7 days Mon 1/04/19 Tue 9/04/19 $7,840.00
Stakeholder
Interviews
5 days Mon 1/04/19 Fri 5/04/19
Business Analyst, Business
Coordinator, Project Manager
$5,600.00
Stakeholder Analysis 2 days Mon 8/04/19 Tue 9/04/19 3
Business Analyst, Business
Coordinator ,Project Manager
$2,240.00
Implementation Plan 27 days
Wed
10/04/19
Thu 16/05/19 $26,560.00
Selecting the Process 10 days Wed 10/04/19 Tue 23/04/19 4 Business Coordinator, $10,400.00
Project Management_2
1PROJECT MANAGEMENT
Database Administrator,
Financial manager
Planning Project
Management
9 days Wed 24/04/19 Mon 6/05/19 6,4
Business Analyst, Project
Manager
$7,200.00
Project Sign In 8 days Tue 7/05/19 Thu 16/05/19 7
Business Analyst, Business
Coordinator, Project Manager
$8,960.00
Designing Phase 40 days Fri 17/05/19 Thu 11/07/19 $41,600.00
Modelling the
processes that are
completed
15 days Fri 17/05/19 Thu 6/06/19 8
Business Analyst, Business
Coordinator, Database
Administrator
$14,400.00
Measuring the
performance metrices
15 days Fri 7/06/19 Thu 27/06/19 10
Database Administrator,
Financial manager,
Procurement Manager
$16,800.00
Documenting the
model
10 days Fri 28/06/19 Thu 11/07/19 11 Business Analyst, Database
Administrator, Procurement
$10,400.00
Project Management_3
2PROJECT MANAGEMENT
Manager
Modelling Phase 185 days Fri 12/07/19 Thu 26/03/20 $245,900.00
Communication plan
for stakeholder
20 days Fri 12/07/19 Thu 8/08/19 12
Business Analyst, Business
Coordinator, Database
Administrator, Financial
manager, Procurement
Manager
$35,200.00
Detailed Execution
plan
20 days Fri 9/08/19 Thu 5/09/19 14,11
Database Administrator,
Financial manager,
Procurement Manager,
Quality analyst, Software
Requirements[1]
$28,700.00
Manufacturing
Resource Layer
15 days Fri 6/09/19 Thu 26/09/19 15 Business Analyst, Business
Coordinator, Database
Administrator, Quality
$19,500.00
Project Management_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Business Project Management
|7
|1291
|18

Project Management: Benefits Administration Software
|4
|811
|299

Project Management Isn't Just For Project
|10
|1445
|19

International Journal of Commerce and Management
|7
|652
|11

BSBPMG522 Undertake Project Work - Project Plan
|7
|1370
|59

Assignment (doc) on Project Business Management
|9
|1199
|13