Project Plan: Number Plate Recognition and Facilities Management System

   

Added on  2022-11-26

14 Pages2133 Words137 Views
Running head: PROJECT PLAN
Project Plan: Number Plate Recognition and Facilities Management System
Name of the Student:
Name of the University:

1PROJECT PLAN
3. Project Plan
3.1 Project Schedule
WBS Task Name Duration Start Finish
0 Number Plate Recognition and
Facilities Management System 191 hrs Tue 5/7/19 Fri 6/7/19
1 Project planning phase 53 hrs Tue 5/7/19 Wed 5/15/19
1.1 Identification of the project
requirements 5 hrs Tue 5/7/19 Tue 5/7/19
1.2 Hiring of the project stakeholders 28 hrs Tue 5/7/19 Mon 5/13/19
1.3 Identify the specification of the
system 48 hrs Tue 5/7/19 Wed 5/15/19
1.3.1 Functional specifications 10 hrs Tue 5/7/19 Wed 5/8/19
1.3.2 Non-functional specifications 20 hrs Mon 5/13/19 Wed 5/15/19
1.4 Kick off the project meeting 3 hrs Wed 5/8/19 Thu 5/9/19
1.5 Completion of project planning
phase 0 hrs Thu 5/9/19 Thu 5/9/19
2 Project system design 121 hrs Thu 5/9/19 Thu 5/30/19
2.1 Acquisition of the image 12 hrs Thu 5/9/19 Fri 5/10/19
2.2 Extraction of number plate 15 hrs Fri 5/10/19 Tue 5/14/19
2.3 Character segmentation 60 hrs Wed 5/15/19 Mon 5/27/19
2.3.1 Scaling 18 hrs Wed 5/15/19 Fri 5/17/19
2.3.2 Horizontal projections 20 hrs Fri 5/17/19 Wed 5/22/19
2.3.3 Vertical projections 22 hrs Wed 5/22/19 Mon 5/27/19
2.4 Character recognition 94 hrs Tue 5/14/19 Thu 5/30/19

2PROJECT PLAN
2.4.1 Template matching 12 hrs Mon 5/27/19 Tue 5/28/19
2.4.2 Component labeling 14 hrs Tue 5/28/19 Thu 5/30/19
2.4.3 Vertical projections 16 hrs Tue 5/14/19 Thu 5/16/19
2.5 Completion of system design phase 0 hrs Thu 5/16/19 Thu 5/16/19
3 Project execution phase 85 hrs Thu 5/16/19 Fri 5/31/19
3.1 Building of physical project
deliverables 6 hrs Thu 5/16/19 Fri 5/17/19
3.2 Managing of the project
procurement 9 hrs Fri 5/17/19 Mon 5/20/19
3.3 Acceptance of the client 3 hrs Mon 5/27/19 Mon 5/27/19
3.4 Communication plan 5 hrs Tue 5/28/19 Wed 5/29/19
3.5 Risk management plan 7 hrs Wed 5/29/19 Thu 5/30/19
3.6 Sign off the project client 9 hrs Thu 5/30/19 Fri 5/31/19
3.7 Completion of project execution
phase 0 hrs Fri 5/31/19 Fri 5/31/19
4 Project closure phase 45 hrs Fri 5/31/19 Fri 6/7/19
4.1 Release of the project stakeholders 18 hrs Fri 5/31/19 Tue 6/4/19
4.2 Review the project draft 12 hrs Tue 6/4/19 Wed 6/5/19
4.3 Final project sign off 15 hrs Thu 6/6/19 Fri 6/7/19
4.4 Completion of project closure phase 0 hrs Fri 6/7/19 Fri 6/7/19

3PROJECT PLAN
3.2 Project Phases
Project
Phases
Original
Planned
Completion
Date
Revised
Planned
Completio
n Date
Actual
Completion
Date
Actual
Finish
Original
Planned
Effort
Revised
Planned
Effort Actual Effort
Project
planning
phase
Wed
5/15/19
Wed
5/15/19 Tue 5/7/19 NA 53 hrs 53 hrs 53 hrs
Project
system design Thu 5/30/19 Thu 5/30/19 Thu 5/9/19 NA 121 hrs 121 hrs 118.8 hrs
Project
execution
phase
Mon 6/3/19 Mon 6/3/19 Thu 5/16/19 NA 92 hrs 92 hrs 54 hrs
Project
closure phase
Mon
6/10/19
Mon
6/10/19 NA NA 45 hrs 45 hrs 0 hrs
3.3 Tasks: Dates and effort
Task Name
Original
Planned
Completion
Date
Revised
Planned
Completion
Date
Actual
Completion
Date
Original
Planned
Effort
Revised
Planned
Effort Actual Effort
Project
planning
phase
Wed 5/15/19 Wed
5/15/19 NA 53 hrs 53 hrs 53 hrs
Identification
of the project
requirements
Wed 5/8/19 Wed 5/8/19 Wed 5/8/19 9 hrs 9 hrs 9 hrs
Hiring of
the project
Mon 5/13/19 Mon Mon 5/13/19 28 hrs 28 hrs 28 hrs

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Gantt Chart of Software Training Program_modified | Desklib
|2
|579
|69

Construction Project Management Assignment
|12
|1544
|89

Project Management Isn't Just For Project
|10
|1445
|19

Project Management Assignment 3: Unit Project Part B
|29
|4746
|459

Project Schedule and Cost Estimation
|17
|2907
|394

BSBPMG522 Undertake Project Work - Project Plan
|7
|1370
|59