This article discusses the impact of project scope, peer review, project goals and objectives, project scope statement, WBS, and project schedule in the context of a bungalow construction project. It also highlights the importance of project management knowledge and PMBOK guidelines in ensuring successful project completion. The article provides expert guidance and study material for students and professionals at Desklib.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: SCOPE AND TIME MANAGEMENT PLAN
Scope and Time Management Plan
Name of the Student:
Student ID:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1SCOPE AND TIME MANAGEMENT PLAN
Part A – Module 2 Discussion Activity
1. Impact of Project Scope
The project scope is developed for aligning the integration and developing the
management of the project integration and development. The scope of the project is implied with
the successful management of the improved functional development. The project scope
development would be affected by the utilization and management of the improved
communication. The proper and scope development would be effective with the successful
management of the activities. The number of project scope items would be listed with the
continuation of the improved operations. The change in scope is directly proportional to the
project schedule,
Increase in the scope of the project would result in the increasing the project
duration
Decrease in the scope of the project would result in decreasing the project
duration
The project manager would be responsible for the alignment and developing the
successful management and listing the utilization development. The management of the project
integration has been limited for implying the successful management. The manager of the project
is helpful for listing the utilization management. The managers are responsible for the analysis of
the formation and listing probable management formation. The project manager would be
implied for analysing the successful management and development. The management of the
project activities has been implied with the continuation of the successive project operations. The
progression of the data management is completely dependent on the processing of the business
prosecution and this is the min fact that the data that are generated during the processing of the
Document Page
2SCOPE AND TIME MANAGEMENT PLAN
data prosecution will incur the fact that the project will be performed with better efficiency. This
is the major reason that the completion of the projects are dependent on the project managers in a
huge way. This is the main process that the projection of the data centre requited proper
management steps that are taken by the project managers. The main aspect of the project
managers includes the fact that the project that is to be completed will require better
proclamation of the data that are present in the regression of the business completion.
2. Peer Review
The review of the PMBOK would be developed combining the alignment of the
successful integration and alignment of the improved scope analysis and integration of the
operations and listing proper management of the activities. The inclination of the successful
execution of the project scope has been defined by the student. The listing of the factors for
development and alignment had been implied for forming the successful integration and
development. The proper development had eased the listing of probable management formation.
The implementation has been helpful for aligning the successful integration and development for
forming the effective alignment model. The listing of the proper and effective project
development would be eased with the management of the successful project completion. The
implementation knowledge that are present in the book of project management helps in better
performance of the data proclamation. In case the terminology that is present in the projection of
the data concurrence are stated in the PMBOK. This helps in understanding the basic concepts of
project management and this is the reason that the data terminology that is present in the curse of
the data management will include the fact that the project that is performed is done with
immense integrity. The functioning of models are also stated in the project. This is the main
reason that the project that is performed in the project management can be performed with better
Document Page
3SCOPE AND TIME MANAGEMENT PLAN
understanding of the project. The projection of the entire concept of project management is
reframed with the help of the project managers and this is the sole reason that the projection of
the data centre of the business management can be performed with the help of data prosecution.
PMBOK is used as a reference sett that helps in better completion of the project. The main aspect
that is present in the projection of the data commencement is performed with the help of the
guidelines that are stated in the PMBOK. This is the reason that the prosecution of the projects
are performed with the help of the in depth knowledge that is present in the PMBOK. The main
fact that the data that are present in the PMBOK helps in understanding the entire process with
ease and this is the main reason that the projection of the project manager will not find it
difficulty in the completion of the projects that are stuck in the project are termed to be one of
the complex situation in the project completion.
The project plan had been developed with the consistent management of the activities and
listing probable alignment model. The stakeholders would be implied for listing the formation of
the innovative management formation. The study is helpful for deploying the successful
integration and management of the activities aligning the proper and effective management of
operations. The post had covered the impact of the stakeholders and the listing of the functions
integrating with the utilization of the successful management. The study provided the highlight
of the opportunity analysis for the successful integration. The managers are responsible for the
analysis of the formation and listing probable management formation. The project manager
would be implied for analysing the successful management and development.
Part B – Scope and Time Management Plans
1. Project Goals and Objectives

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4SCOPE AND TIME MANAGEMENT PLAN
The project is developed for integrating the management of the successful integration and
management. The project development would be helpful for integrating the successful
integration and alignment management. The implication of the operations and listing probable
management would be implied for managing the project analysis and forming management of
the successful development. The goals of the bungalow project include,
Deployment of the project plan: Project plan is developed with the consideration of the
alignment model and integrating the listing of the formation development. The project plan
would be developed considering the utilization of the factors for development.
Improvement of Operations: It is important for increasing the construction management
and alignment of improved activities. The analysis would be managed for making sure that the
operations would be effectively implied and deployed for managing operations. The requirement
of improved operational techniques includes the fact that the completion of the project will be
performed with the help of the data commencement and this is the reason that the projection of
the data procurement will be performed with the help of improved alignment.
Construction of the building: The construction of the building would be effectively
constructed with the help of improved functional analysis. The construction of the
The objectives of the bungalow project include,
To construct the bungalow with the help of the construction project management
and imply the management of the successful operations
To complete the project in the estimated time and budget requirements for
ensuring the completion of the project
To improve the management of the operations and align with the successful
integration and development
Document Page
5SCOPE AND TIME MANAGEMENT PLAN
To form the feasible construction management operations for the completion of
the project
2. Project Scope Statement
The scope of the project is implied with the successful management of the improved
functional development. The project scope development would be affected by the utilization and
management of the improved communication1. The proper and scope development would be
effective with the successful management of the activities. The number of project scope items
would be listed with the continuation of the improved operations. The manager of the project is
helpful for listing the utilization management. The managers are responsible for the analysis of
the formation and listing probable management formation. The project manager would be
implied for analysing the successful management and development. The projection of the project
completion requires proper management techniques and this is the main reason that the
proclamation of the data projection will be performed with the help of the data commencement
of the project managers. This is the main reason that the projection that the data prosecution can
be performed with the data management as the prosecution of the project includes proper
definition of the scope that will be performed with the projection of the business management.
3. WBS
1 Oo, S.B., Oo, N.H.M., Chainan, S., Thongniam, A. and Chongdarakul, W., (2018, February). Cloud-based web
application with NFC for employee attendance management system. In 2018 International Conference on Digital
Arts, Media and Technology (ICDAMT) (pp. 162-167). IEEE.
Document Page
6SCOPE AND TIME MANAGEMENT PLAN
The Bungalow Project
Clear Ground
Lay Foundations
Build dwarf walls
Oversite concrete
Floor Joists
Main Walls
Doors and Windows
Frame
Ceiling Joints
Roof Timbers
Tiles
Floorboards
Ceiling boards
Skirtings
Glazing
Plastering
Electrics
Plumbing and
heating
Painting
Figure 1: Work Breakdown Structure of the Bungalow Project
(Source: Created by the author)
WBS Task Name
0 The Bungalow Project
A Clear Ground
B Lay Foundations
C Build dwarf walls
D Oversite concrete
E Floor Joists
F Main Walls
G Doors and Windows Frame
H Ceiling Joints
J Roof Timbers
K Tiles
L Floorboards
M Ceiling boards
N Skirtings

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7SCOPE AND TIME MANAGEMENT PLAN
P Glazing
Q Plastering
R Electrics
S Plumbing and heating
T Painting
4. Project Schedule
WBS Task Name Duratio
n Start Finish Predecessors Resource
Names Cost
0 The Bungalow
Project 34 wks Mon
10/8/18
Fri
5/31/19 $269,040.00
A Clear Ground 2 wks Mon
10/8/18
Fri
10/19/18
Labourer 1,
Labourer 2,
Labourer 3,
Labourer 4,
Labourer 5,
Labourer 6
$14,400.00
B Lay Foundations 3 wks Mon
10/22/18
Fri
11/9/18 1
Labourer 1,
Labourer 2,
Labourer 3,
Labourer 4,
Tradesman 1,
Tradesman 2
$25,200.00
C Build dwarf walls 2 wks Mon
11/12/18
Fri
11/23/18 2
Labourer 1,
Labourer 2,
Tradesman 1,
Tradesman 2,
Tradesman 3,
Tradesman 4
$19,200.00
D Oversite concrete 1 wk Mon
11/12/18
Fri
11/16/18 2
Labourer 1,
Labourer 2,
Labourer 3,
Labourer 4
$4,800.00
E Floor Joists 2 wks Mon
11/26/18
Fri
12/7/18 3,4 Tradesman 3,
Tradesman 4 $7,200.00
F Main Walls 5 wks Mon
12/10/18
Fri
1/11/19 5
Labourer 5,
Labourer 6,
Tradesman 1,
Tradesman 2,
Tradesman 3,
Tradesman 4
$48,000.00
G Doors and 3 wks Mon Fri 5 Tradesman 1, $10,800.00
Document Page
8SCOPE AND TIME MANAGEMENT PLAN
Windows Frame 12/10/18 12/28/18 Tradesman 2
H Ceiling Joints 2 days Mon
1/14/19
Tue
1/15/19 6,7 Tradesman 3,
Tradesman 4 $1,440.00
J Roof Timbers 6 wks Mon
1/14/19
Fri
2/22/19 6,7 Tradesman 1,
Tradesman 2 $21,600.00
K Tiles 2 wks Mon
2/25/19 Fri 3/8/19 8,9
Labourer 1,
Labourer 2,
Tradesman 1,
Tradesman 2,
Tradesman 3
$15,600.00
L Floorboards 3 wks Mon
2/25/19
Fri
3/15/19 8,9 Tradesman 1,
Tradesman 2 $10,800.00
M Ceiling boards 2 wks Mon
3/18/19
Fri
3/29/19 10,11 Tradesman 3,
Tradesman 4 $7,200.00
N Skirtings 1 wk Mon
3/18/19
Fri
3/22/19 10,11 Tradesman 1,
Tradesman 3 $3,600.00
P Glazing 2 wks Mon
4/1/19
Fri
4/12/19 12,13 Tradesman 2,
Tradesman 4 $7,200.00
Q Plastering 2 wks Mon
4/15/19
Fri
4/26/19 14
Labourer 2,
Tradesman 2,
Tradesman 3,
Tradesman 4
$13,200.00
R Electrics 3 wks Mon
4/15/19 Fri 5/3/19 14 Tradesman 1,
Tradesman 4 $10,800.00
S Plumbing and
heating 4 wks Mon
4/15/19
Fri
5/10/19 14
Labourer 3,
Tradesman 2,
Tradesman 3,
Tradesman 4
$26,400.00
T Painting 3 wks Mon
5/13/19
Fri
5/31/19 15,16,17
Tradesman 1,
Tradesman 2,
Tradesman 3,
Tradesman 4
$21,600.00
Document Page
9SCOPE AND TIME MANAGEMENT PLAN
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 The Bungalow Project34 wks Mon 10/8/18 Fri 5/31/19
1 A Clear Ground 2 wks Mon 10/8/18 Fri 10/19/18
2 B Lay Foundations 3 wks Mon 10/22/18 Fri 11/9/18
3 C Build dwarf walls 2 wks Mon 11/12/18 Fri 11/23/18
4 D Oversite concrete 1 wk Mon 11/12/18 Fri 11/16/18
5 E Floor Joists 2 wks Mon 11/26/18 Fri 12/7/18
6 F Main Walls 5 wks Mon 12/10/18 Fri 1/11/19
7 G Doors and
Windows Frame
3 wks Mon 12/10/18 Fri 12/28/18
8 H Ceiling Joints 2 days Mon 1/14/19 Tue 1/15/19
9 J Roof Timbers 6 wks Mon 1/14/19 Fri 2/22/19
10 K Tiles 2 wks Mon 2/25/19 Fri 3/8/19
11 L Floorboards 3 wks Mon 2/25/19 Fri 3/15/19
12 M Ceiling boards 2 wks Mon 3/18/19 Fri 3/29/19
13 N Skirtings 1 wk Mon 3/18/19 Fri 3/22/19
14 P Glazing 2 wks Mon 4/1/19 Fri 4/12/19
15 Q Plastering 2 wks Mon 4/15/19 Fri 4/26/19
16 R Electrics 3 wks Mon 4/15/19 Fri 5/3/19
17 S Plumbing and heating4 wks Mon 4/15/19 Fri 5/10/19
18 T Painting 3 wks Mon 5/13/19 Fri 5/31/19
Labourer 1,Labourer 2,Labourer 3,Labourer 4,Labourer 5,Labourer 6
Labourer 1,Labourer 2,Labourer 3,Labourer 4,Tradesman 1,Tradesman 2
Labourer 1,Labourer 2,Tradesman 1,Tradesman 2,Tradesman 3,Tradesman 4
Labourer 1,Labourer 2,Labourer 3,Labourer 4
Tradesman 3,Tradesman 4
Labourer 5,Labourer 6,Tradesman 1,Tradesman 2,Tradesman 3,Tradesman 4
Tradesman 1,Tradesman 2
Tradesman 3,Tradesman 4
Tradesman 1,Tradesman 2
Labourer 1,Labourer 2,Tradesman 1,Tradesman 2,Tradesman 3
Tradesman 1,Tradesman 2
Tradesman 3,Tradesman 4
Tradesman 1,Tradesman 3
Tradesman 2,Tradesman 4
Labourer 2,Tradesman 2,Tradesman 3,Tradesman 4
Tradesman 1,Tradesman 4
Labourer 3,Tradesman 2,Tradesman 3,Tradesman 4
Tradesman 1,Tradesman 2,Tradesman 3,Tradesman 4
W S T M F T S W S T M F T S W S T M F T S W S T M
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19 Mar 10, '19 Apr 7, '19 May 5, '19 Jun 2, '19 Jun 30, '19
Figure 2: Gantt chart of the Bungalow project
(Source: Created by the author)

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10SCOPE AND TIME MANAGEMENT PLAN
Bibliography
de Reuver, M. and Ondrus, J., (2017). When technological superiority is not enough: The
struggle to impose the SIM card as the NFC Secure Element for mobile payment
platforms. Telecommunications Policy, 41(4), pp.253-262.
Oo, S.B., Oo, N.H.M., Chainan, S., Thongniam, A. and Chongdarakul, W., (2018, February).
Cloud-based web application with NFC for employee attendance management system. In 2018
International Conference on Digital Arts, Media and Technology (ICDAMT) (pp. 162-167).
IEEE.
1 out of 11
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]