Running head: ISY00243 CASE STUDY
ISY00243 Case Study
Name of the Student:
Student ID:
Name of the University:
Author’s notes:
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1ISY00243 CASE STUDY
Table of Contents
1. Summary of “You Can Fit In business”......................................................................................2
2. Organization Chart of “You Can Fit In business”.......................................................................2
3. Business function of “You Can Fit In business”.........................................................................3
4. System Vision Document............................................................................................................4
4.1 Brainstorming functions........................................................................................................4
4.2 System Vision Document......................................................................................................5
5. Project Management....................................................................................................................6
5.1 Table for the activities...........................................................................................................6
5.2 Dependencies in project.........................................................................................................7
5.3 Gantt Chart.............................................................................................................................8
5.4 PERT chart...........................................................................................................................10
5.5 Overall project duration.......................................................................................................12
6. Risk and Cost Benefit Analysis.................................................................................................12
6. Fact Finding techniques.............................................................................................................13
6.1 Fact fining techniques..........................................................................................................13
6.2 Identification of two staff members.....................................................................................14
6.3 List of questionnaires...........................................................................................................14
6.4 Recommendations of fact finding methods.........................................................................14
Bibliography..................................................................................................................................15
Document Page
2ISY00243 CASE STUDY
Part A: Initial Investigation
1. Summary of “You Can Fit In business”
“You Can Fit In business” operates a fitness center with many facilities for the people
such as large exercise area, swimming pool, snack bar, health food store, and sporting goods
shop. The center has also decided to offer child care for various ages with special programs and
computer café. The people can get the benefit of yoga, swimming, exercises at the center along
with the necessary equipment and works. The implication management would be effectively
managed with the consideration of the factors for influencing work and performances of the care
for healthy living. However, Adam who is the owner of organization have decided to start the
online training programs and services. It would allow the people from distant for gaining access
to the program and information about the products and services of the organization.
2. Organization Chart of “You Can Fit In business”
Document Page
3ISY00243 CASE STUDY
Adam Apple
(CEO)
Donald Dollars
(Finance Manager)
Chia Chen
(Operation Manager)
Sally Molly
(Sales Manager)
Center Manager 1
Center Manager 1
………..
Center Manager 13
Shop Attendant
Front Desk
Instructors
Life Guard
3. Business function of “You Can Fit In business”
The new accounting system would support the web based information access for the
organization so that their customers can get access to the information whenever they want. The
new system would help in the following functions,
Integration of the system: The new information system would help in integrating the
information from the various centers of “You Can Fit In business” so that all the centers would
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4ISY00243 CASE STUDY
provide the same basic services like exercise equipment, snack bar, sporting goods, child care
and fitness program, and swimming pool.
Online Service: The new system would be cloud based and it would help in bringing the
concept of 24X7 online services. Customers would be able to use the web based services of
“You Can Fit In business” from wherever they like. It would open the door for online marketing
and gaining more customers.
Better Service Class: the “You Can Fit In business” would get the new feature of
membership levels with the help of new and improved work experience. The improved service
class would be supported by two levels of membership namely basic and full. Apart from this a
pay as you use function would also be available.
4. System Vision Document
4.1 Brainstorming functions
The new system for “You Can Fit In business” would help in integrating the works and
forming the utilization of the smart services for the customers. The new system would be cloud
based focusing on online services like,
Organization information system: The effective management of the information for the
organization would be largely based on the implication of the works and defining the allocation
of the effective processing. The new information system would help “You Can Fit In business”
to integrate information of all its centers and develop improved services.
Customer Attraction: The new information system would help in enabling the
implication of the online web services. The customers from distant locations would get the
benefit of using online services for gaining access to the information management.
More Facilities: The new information system would allow the development of integrated
services at Gold Coast center of “You Can Fit In business”. The improved services would help in
forming the implication management. The services like exercise equipment, snack bar, sporting
goods, child care and fitness program, and swimming pool would be all integrated at the center.
Document Page
5ISY00243 CASE STUDY
Replacement of OnAllAccounts: The accounting software package of OnAllAccounts
of “You Can Fit In business” had been required for managing accounts information like bills
payable, bills receivables, general ledger, and over budget statement. However, the new system
would be able to take care of accounting data and functions effectively. The software package
would be of no use with the help of new information system.
Security of information: The new information system would be aligned with the
formation of the improved analysis and development. The information security would be implied
with the listing of the proper and effective information development. The protection of the
information would help the organization against the cyber criminals for theft and misuse.
4.2 System Vision Document
Introduction: The system vision document is developed for the project of “Developing
new online information system for You Can Fit In business”. The compilation of the effective
information system would provide scope for the improvements of the activities and development
of better services. The new information system would allow the development of integrated
services of equipment, snack bar, sporting goods, child care and fitness program, and swimming
pool at Gold Coast center of “You Can Fit In business”.
The purpose of the document is for providing the effective alignment management of the
operations. The improved work experience would be aligned with the formation of the system
documentation and providing effective alignment.
The aim of the project is to develop the innovative information development and aligning
the management of activities aligning the utilization of the successive information management.
The project would improve the formation of the explicit information limitation for the
operations.
Design Constraints and Considerations: The design of the new information system would
be constrained by the formation of the effective work development consideration. The
constraints and consideration for the design of the system are,
System database must be coherent with the existing database of OnAllAccounts
of “You Can Fit In business”
Document Page
6ISY00243 CASE STUDY
Internet based cloud network must be utilized for improved operations of “You
Can Fit In business”
Compatible design of the activities would be supported by the improved security
for the information and data of the organization
System Usage: The new information system would help in integrating the information
from the various centers of “You Can Fit In business” so that all the centers would provide the
same basic services like exercise equipment, snack bar, sporting goods, child care and fitness
program, and swimming pool. Customers would be able to use the web based services of “You
Can Fit In business” from wherever they like. It would open the door for online marketing and
gaining more customers. The improved service class would be supported by two levels of
membership namely basic and full. Apart from this a pay as you use function would also be
available.
System Requirements: The new information system would include the following
requirements
a) Integrated database
b) Cloud Function Integration
c) Compatible Design
d) Stock Management System
e) Accounts information management
5. Project Management
5.1 Table for the activities
WBS Task Name
0 Developing new online information system for You Can Fit In business
1 Initial Phase
1.1 Requirement Analysis
1.2 Charter Documentation
1.3 Submission of Documents
1.4 Meeting Fitness Center Managers
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7ISY00243 CASE STUDY
1.5 Conducting Interviews
1.6 Kick off
2 Execution Phase
2.1 Reviewing company records
2.2 Analysis of Customer interaction
2.3 Analysis of OnAllAccounts
2.4 Analysis of Sample of bills and sales transaction
2.5 Database Development
2.6 System Designing
2.7 System Programming
2.8 Complete System Development
2.9 Developed
3 Closure Phase
3.1 Final Report is made
3.2 Submission of Documents
3.3 Sign off
3.4 Closed
5.2 Dependencies in project
WBS Task Name Predecessor
s
Dependency
0 Developing new online information system for
You Can Fit In business
1 Initial Phase
1.1 Requirement Analysis First task Dependent on project
start date
1.2 Charter Documentation 2 Finish to start with 1.1
Document Page
8ISY00243 CASE STUDY
1.3 Submission of Documents 3 Finish to start with 1.2
1.4 Meeting Fitness Center Managers 3 Finish to start with 1.2
1.5 Conducting Interviews 2 Finish to start with 1.1
1.6 Kick off 4,5,6 Finish to start with 1.3,
1.4, 1.5
2 Execution Phase
2.1 Reviewing company records 6 Finish to start with 1.5
2.2 Analysis of Customer interaction 9SS Start to start with 2.1
2.3 Analysis of OnAllAccounts 9,10 Finish to start with 2.1,
2.2
2.4 Analysis of Sample of bills and sales transaction 9,10 Finish to start with 2.1,
2.2
2.5 Database Development 11,12 Finish to start with 2.3,
2.4
2.6 System Designing 13 Finish to start with 2.5
2.7 System Programming 14 Finish to start with 2.6
2.8 Complete System Development 15 Finish to start with 2.7
2.9 Developed 16 Finish to start with 2.8
3 Closure Phase
3.1 Final Report is made 17 Finish to start with 2.9
3.2 Submission of Documents 19 Finish to start with 3.1
3.3 Sign off 20 Finish to start with 3.2
3.4 Closed 21 Finish to start with 3.3
5.3 Gantt Chart
Document Page
9ISY00243 CASE STUDY
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Developing new online
information system for You
Can Fit In business
48 days Mon
12/17/18
Wed 2/20/19
1 1 Initial Phase 8 days Mon 12/17/18 Wed 12/26/18
2 1.1 Requirement Analysis 2 days Mon 12/17/18 Tue 12/18/18
3 1.2 Charter Documentation 3 days Wed 12/19/18 Fri 12/21/18
4 1.3 Submission of Documents 1 day Mon 12/24/18 Mon 12/24/18
5 1.4 Meeting Fitness Center Managers3 days Mon 12/24/18 Wed 12/26/18
6 1.5 Conducting Interviews 6 days Wed 12/19/18 Wed 12/26/18
7 1.6 Kick off 0 days Wed 12/26/18 Wed 12/26/18
8 2 Execution Phase 37 days Thu 12/27/18 Fri 2/15/19
9 2.1 Reviewing company records4 days Thu 12/27/18 Tue 1/1/19
10 2.2 Analysis of Customer interaction9 days Thu 12/27/18 Tue 1/8/19
11 2.3 Analysis of OnAllAccounts 3 days Wed 1/9/19 Fri 1/11/19
12 2.4 Analysis of Sample of bills
and sales transaction
3 days Wed 1/9/19 Fri 1/11/19
13 2.5 Database Development 4 days Mon 1/14/19 Thu 1/17/19
14 2.6 System Designing 5 days Fri 1/18/19 Thu 1/24/19
15 2.7 System Programming 10 days Fri 1/25/19 Thu 2/7/19
16 2.8 Complete System Development6 days Fri 2/8/19 Fri 2/15/19
17 2.9 Developed 0 days Fri 2/15/19 Fri 2/15/19
18 3 Closure Phase 3 days Mon 2/18/19 Wed 2/20/19
19 3.1 Final Report is made 1 day Mon 2/18/19 Mon 2/18/19
20 3.2 Submission of Documents 1 day Tue 2/19/19 Tue 2/19/19
21 3.3 Sign off 1 day Wed 2/20/19 Wed 2/20/19
22 3.4 Closed 0 days Wed 2/20/19 Wed 2/20/19
12/26
2/15
2/20
S T M F T S W S T M F T S W S T M F T
Dec 16, '18 Dec 30, '18 Jan 13, '19 Jan 27, '19 Feb 10, '19 Feb 24, '19
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10ISY00243 CASE STUDY
5.4 PERT chart
Critical Path of Project
Document Page
11ISY00243 CASE STUDY
ID Task
Mode
WBS Task Name Duration
2 1.1 Requirement Analysis 2 days
6 1.5 Conducting Interviews 6 days
10 2.2 Analysis of Customer interaction9 days
11 2.3 Analysis of OnAllAccounts 3 days
12 2.4 Analysis of Sample of bills
and sales transaction
3 days
13 2.5 Database Development 4 days
14 2.6 System Designing 5 days
15 2.7 System Programming 10 days
16 2.8 Complete System Development6 days
17 2.9 Developed 0 days
19 3.1 Final Report is made 1 day
20 3.2 Submission of Documents 1 day
21 3.3 Sign off 1 day
22 3.4 Closed 0 days
2/15
2/20
T S W S T M F T S W S T M F T S W S T M F T S W
Dec 2, '18 Dec 16, '18 Dec 30, '18 Jan 13, '19 Jan 27, '19 Feb 10, '19 Feb 24, '19
Document Page
12ISY00243 CASE STUDY
5.5 Overall project duration
The overall project duration is shown below,
WBS Task Name Duration Start Finish
0 Developing new online information system for You
Can Fit In business 48 days Mon
12/17/18
Wed
2/20/19
6. Risk and Cost Benefit Analysis
The following is the cost benefit analysis of the project,
Risk name Probability
(1-5)
Severity
(1-5)
Impact
P*S
Mitigation Responsible
Person
Delay in
Completion
3 4 12 Mitigate Planner
Quality Issues 2 2 4 Exploit Quality Analyst
Over budget 3 1 3 Accept Budgeter
Design Issues 4 1 4 Share Designer
Human Mistake 4 3 12 Avoid HR manager
Contractor
Disagreement
4 3 12 Mitigate Project Manager
Security Issues 4 3 12 Avoid Security
Analyst
Performance
Problems
1 5 5 Share Project Manager
Lack of Information 5 2 10 Transfer Analyst
Change in scope 3 4 12 Transfer Analyst
The following is the cost budget analysis using two methods of NPV and Payback period,
NPV Method
Year 0 Year 1 Year 2 Year 3
Net economic benefit $0 $12,000 $12,000 $12,000
One time cost ($15,000 $0 $0 $0
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13ISY00243 CASE STUDY
)
Recurring cost $0 ($3,600) ($3,600) ($3,600)
Net cash flow ($15,000
) $8,400 $8,400 $8,400
Discount factors
Discount rate 5%
Year Index 0 1 2 3
Discount factor 1 0.95 0.91 0.86
Discounted flows
Cost ($15,000
) ($3,429) ($3,265) ($3,110)
Benefit $0 $11,429 $10,884 $10,366
Net ($15,000
) $8,000 $7,619 $7,256
Cummulative ($15,000
) ($7,000) $619 $7,875
Net present value $7,875
Payback Analysis method
Cost -$15,000.00 -$3,428.57 -$3,265.31 -$3,109.82
Benefit $0.00 $11,428.57 $10,884.35 $10,366.05
Net -$15,000.00 $8,000.00 $7,619.05 $7,256.24
Cummulative -$15,000.00 -$7,000.00 $619.05 $7,875.28
Payback Analysis Years Months
1.00 11.03
Payback Time 1.92
6. Fact Finding techniques
6.1 Fact fining techniques
The most optimum methods of fact finding techniques to be used are brainstorming and
survey questionnaires. The brainstorming would help in easing the process of the information
collection as all the members of the project team would gather and suggest methods of
implementation the new system. The use of the brainstorming methods would be helpful for
ensuring the alignment of the activities facilitation of the information system development. The
questionnaire would be developed with the help of the successive and effective information
management. The brainstorming method would be helpful for collecting all possible methods
and functions of the new information system made for “You Can Fit In business”. The
Document Page
14ISY00243 CASE STUDY
questionnaire developed would help in easing the information development for the operations
and listing probable management methods. For example: the design principles for the new
information system can be decided by using brainstorming method. Apart from it, the application
of the system can be made using the brainstorming method too.
6.2 Identification of two staff members
Risk Analyst: The risk analyst would be responsible for the execution of the risk analysis
and development of methods of mitigation for “You Can Fit In business”
Developer: The developer would program and develop the system with all the functions
required for listing the operations of “You Can Fit In business”
6.3 List of questionnaires
Question Checklist
Do you agree with the need of the new information system for You
Can Fit In business?
Yes
No
Is it possible for managing the work with the new information system
at You Can Fit In business?
Yes
No
Do you think training would be needed by the staffs of You Can Fit
In business for the use of the new information system?
Yes
No
Are you happy with the decision of implementing new information
system?
Yes
No
Provide some changes that you expect with the new technology :____________
Any suggestion for improvement? :____________
6.4 Recommendations of fact finding methods
General Surveys and Questionnaire is helpful for aligning the information regarding the
development of the effective work alignment management. The use of the surveys would help in
integrating the information from various possible personals so that a detail overview of the
project can be completed successfully. The questionnaire developed would help in easing the
information development for the operations and listing probable management methods.
Document Page
15ISY00243 CASE STUDY
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16ISY00243 CASE STUDY
Bibliography
Beringer, C., Jonas, D. and Kock, A., 2013. Behavior of internal stakeholders in project portfolio
management and its impact on success. International Journal of Project Management, 31(6),
pp.830-846.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Goetsch, D.L. and Davis, S.B., 2014. Quality management for organizational excellence. Upper
Saddle River, NJ: pearson.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green
construction: Overcoming challenges. International Journal of Project Management, 31(2),
pp.272-284.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management:
The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Document Page
17ISY00243 CASE STUDY
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Routledge.
Oakland, J.S., 2014. Total quality management and operational excellence: text with cases.
Routledge.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
chevron_up_icon
1 out of 18
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]