Running head: ITC505 ASSIGNMENT 3PROJECT MANAGEMENT
ITC505 Assignment 3: Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:

1ITC505 ASSIGNMENT 3PROJECT MANAGEMENT
1. Part One: MOV - Measurable Organisational Value
The analysis of the areas of comparison for the development of the project in terms of
financial, customer, operational, strategy, and social are given below,,
a) Financial Area: The aspect of financial area is very crucial for the development of the
project and its implication for the management of the functions. The analysis would
show the formation of the figurative development of the finances and their implication
for the development of the final aspects.
b) Customer Area: The customers play a crucial role in aligning the development of the
effective and improved processes. The customer area is a measure of the influence of
the customers on the operations of the project. It would form the prospect of
developing the operations of the organization.
c) Operational Area: The operations of the project would tend to imply the formation of
the sufficient deployment of the project and its functions. The RALS project would
have to ensure that the operations of the project would tend to imply the magnificent
deployment of operations.
d) Strategy Area: Business organizations have been using the business operation
development by the help of smart and effective strategy development. The strategy
area would form the integration of the supportive management of the operations for
forming the analysis of the project.
e) Social Area: Project organizations have been using the formation of the social
upliftment and management for ensuring the support of the government and local
community. The social area helps in forming the management of the operations for
developing the organizational process.

2ITC505 ASSIGNMENT 3PROJECT MANAGEMENT
Better- Ticketing system developed in the project would help in overcoming the
management of the operations for RALS and Globex. The improvement of the
operations would help in critical evaluation of the operations and functions.
Faster- Ticketing system developed in the project would help in improving the
efficiency of operations by critical evaluation of the project integration and
management. The increased pace of operations would help in final management of the
operations.
Cheaper- Ticketing system developed in the project would help in forming the ease of
operations which would involuntarily decrease the overall cost of the functions. The
services of RALS and Globex.
Do more- Ticketing system developed in the project would help in increasing the
functionality and aspect of developing the project operation.
Rank Impact Metrics Timeframe
1 Financial Profit Calculation, Revenue, and NPV 180 days
2 Customer Customer feedback and Suggestions 130 days

3ITC505 ASSIGNMENT 3PROJECT MANAGEMENT
3 Operational Operation Management Plan 240 days
4 Strategy Strategic Analysis Matrix 320 days
5 Social Support from local community and government 100 days
2. Part Two: Define Scope and produce a Scope Management Plan
Define the scope: The extent of the project scope can be realized as the advancement of the
ticketing framework for shaping the viable and enhanced operations of the association for
RALS by dealing with the client's data
Requirements: The human prerequisites of the task are Budgeter, Documenter, IT Engineer,
Planner, Project Manager, System Analyst, Tester, and Contractor. The materialistic
prerequisites of the task are Computer Devices, Network Components, Storage, and Wireless
switches.
In scope-out scope items: The project design, advancement of the framework, change of
operations, and joining of the capacity are in-scope things of the task. The transportation of
the materials, correspondence design, and investigate change administration are of degree for
the undertaking.
Deliverables: The Project Plan, Initiation Documents, Charter Documents, System Design,
and Ticketing System are the expectations for the project deliverables.
Acceptance Criteria: The statement of the acceptance criteria for the project is,

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Assignment on Project Management PDF
|16
|1190
|980

Project Management- RALS
|14
|2243
|44

Project Management Methodologies - Doc
|17
|2715
|55

Impact for the Project of RALS | Assignment
|16
|3384
|46

Project Management Assignment- RALS Ticketing System
|12
|1844
|113

Report on Scope Management Plan
|17
|2241
|31