MANAGING A
SUCCESSFUL BUSINESS
PROJECT
Managing Successful Business Project Assignment - McLaren_1
Table of Contents
TASK 1............................................................................................................................................3
P.1. Device project aims and objectives for McLaren construction...........................................3
P.2. Project management plan.....................................................................................................4
P.3.Gantt Chart to provide time frames......................................................................................6
TASK 2............................................................................................................................................7
P.4. Small-scale research.............................................................................................................7
TASK 3..........................................................................................................................................14
P.5. Analyse research and data using appropriate tools and techniques...................................14
P.6 .Communicating appropriate recommendations.................................................................15
P.7. Reflection...........................................................................................................................15
REFERENCES..............................................................................................................................17
Managing Successful Business Project Assignment - McLaren_2
TASK 1
P.1. Device project aims and objectives for McLaren construction
Topic of research: Impact of on transforming into daily operation of McLaren Construction and
how its competitors are making use of digital technology.
Background of study: Technology is an essential part of each organisation which
assists all business functionalities. In order to completion of each task in easy and smart manner,
digital technology reduces its efforts and save time for business (Bryde, Broquetas and Volm,
2013). Here the following project will be analysed about necessity and impact of digital
technology on McLaren Construction in order to complete its day-to-day operational activities
within a business environment in a relevant form. Beside from it, following study will be
discussed about impact of digital technologies on the organisational operations. The project
management plan in which covers, costs, risk time, communication and quality and resources
will be developed within organisation. The major aims of this project to understanding the
impact of digital technologies on transformation into the daily operations of McLaren
construction organisation and how its competitors making utilisation of digital technologies to
raising their productivity and profitability within industry. Appropriate reflection will be
furnished with the researcher that would help in understanding how researcher attain the aims
and objectives of the study.
The aims and objectives of the research project as below:
Aim:
“To analyse impact of on transforming into daily operation of McLaren Construction and
how its competitors are making use of it”.
Objectives:
To understand meaning of digital technologies within construction industry
To gain the necessity of digital technology to McLaren Construction
To analyse how business can adopt updated and advanced digital technology for
improving its operational functionalities To analyse how its competitors are making use of digital technologies in order to
transform their operational exercises
Research questions:
1. What is the significant of digital technologies?
Managing Successful Business Project Assignment - McLaren_3
2. What are the necessities of digital technologies to McLaren Construction?
P.2. Project management plan
WBS Task Name Durati
on Start Finish Predecess
ors Resource Names Cost level of
risk
1 Recognising the title
of project 5 days
Mon
2/19/
18
Fri
2/23/
18
£0.00 Low-level
2 Creating issues
argument 4 days
Mon
2/26/
18
Thu
3/1/1
8
1 £250.00 Average
3
Background point in
time to apportion
resources
11
days
Fri
3/2/1
8
Fri
3/16/
18
2 £150.00 Average
4 Literature review 5 days
Fri
3/2/1
8
Thu
3/8/1
8
1,2
Books, Journals,
Internet and
articles
£500.00 Advanced
5 Selecting methods
for inquiry 4 days
Mon
3/19/
18
Thu
3/22/
18
3 £100.00 Average
6 Cost computing 5 days
Fri
3/9/1
8
Thu
3/15/
18
4 £300.00 Advanced
7 Data Representation
and investigating 7 days
Fri
3/23/
18
Mon
4/2/1
8
5 Questionnaires £475.00 Advanced
8 Measure outcome
and aggregation 4 days
Fri
3/23/
18
Wed
3/28/
18
4,5 £100.00 Low-level
9 Immediate judgment
and
5 days Fri
3/16/
Thu
3/22/
6 £100.00 Average
Managing Successful Business Project Assignment - McLaren_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Digital Transformation in Business : Assignment
|24
|5324
|426

Digital Technology Transformation on Marketing Activities PDF
|25
|4887
|239

Globalization Benefits PDF
|23
|4183
|393

Report on Management of Project Plan : GLH Hotels
|18
|4052
|52

(Doc)Managing Successful Business Project
|23
|5660
|50

Corinthia Hotel Research-Significance Corporate Social Responsibility
|27
|4894
|45