This article discusses the development of the MBFSA application by Globex, including the milestones, work breakdown structure, activities, and resource assignments.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: DEVELOPING THE MBFSA APPLICATION BY GLOBEX
Developing the MBFSA Application by Globex
Name of the Student
Name of the University
Author note
Developing the MBFSA Application by Globex
Name of the Student
Name of the University
Author note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1DEVELOPING THE MBFSA APPLICATION BY GLOBEX
Table of Contents
1. The Gantt chart............................................................................................................................2
2. The High Level Work Breakdown Structure..............................................................................3
1.1 Milestones..............................................................................................................................0
1.2 Activities or Tasks.................................................................................................................1
1.3 Resource Assignments...........................................................................................................3
1.4 Estimates for each activity or task.........................................................................................5
1.5 Project Budget.......................................................................................................................6
Bibliography....................................................................................................................................8
Table of Contents
1. The Gantt chart............................................................................................................................2
2. The High Level Work Breakdown Structure..............................................................................3
1.1 Milestones..............................................................................................................................0
1.2 Activities or Tasks.................................................................................................................1
1.3 Resource Assignments...........................................................................................................3
1.4 Estimates for each activity or task.........................................................................................5
1.5 Project Budget.......................................................................................................................6
Bibliography....................................................................................................................................8
2DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1. The Gantt chart
ID Task
Mode
Task Name Duration Start Fini sh
0 Developing the MBFSA
Project by Globex
133 days Wed
01-05-19
Fri 01-11-19
1 Phas e 1: Requir em ent Gather ing Phas e29 days Wed 01-05-19 Mon 10-06-19
2 Preparing of Business Case 2 days Wed 01-05-19 Thu 02-05-19
3 Requirement Gathering 4 days Fri 03-05-19 Wed 08-05-19
4 Develop Scope Management Plan 6 days Thu 09-05-19 Thu 16-05-19
5 Develop Project Management Plan 10 days Fri 17-05-19 Thu 30-05-19
6 Perform Initial Risk Assessment 2 days Fri 31-05-19 Mon 03-06-19
7 Initial Application Test Planning 3 days Tue 04-06-19 Thu 06-06-19
8 Develop Quality Plan 2 days Fri 07-06-19 Mon 10-06-19
9 M1: Requirement Complete 0 days Mon 10-06-19 Mon 10-06-19
10 Planning and Des igning 14 days Tue 11-06-19 Fri 28-06-19
11 Creating Conceptual Design 1 day Tue 11-06-19 Tue 11-06-19
12 Cr eate Login Des ign 6 days Wed 12-06-19 Wed 19-06-19
13 LG1 Weather Information System2 days Wed 12-06-19 Thu 13-06-19
14 LG1 Market Inf ormation System1 day Fri 14-06-19 Fri 14-06-19
15 F1 Farmer management System1 day Mon 17-06-19 Mon 17-06-19
16 WM1 Wholesale Management System2 days Tue 18-06-19 Wed 19-06-19
17 Create Implementation Plan 4 days Thu 20-06-19 Tue 25-06-19
18 Create Contengency Plan 3 days Wed 26-06-19 Fri 28-06-19
19 M2: Planning Phase Complete 0 days Fri 28-06-19 Fri 28-06-19
20 Phas e 2: Developm ent of MBFSA 76 days Mon 01-07-19 Mon 14-10-19
21 Create Database 10 days Mon 01-07-19 Fri 12-07-19
22 Make Prototype 19 days Mon 01-07-19 Thu 25-07-19
23 Excute Project Management Plan 20 days Fri 26-07-19 Thu 22-08-19
24 Pr oject Im plem entation 15 days Fri 23-08-19 Thu 12-09-19
25 LG2 Weather Information System6 days Fri 23-08-19 Fri 30-08-19
26 LG2 Market Inf ormation System5 days Fri 23-08-19 Thu 29-08-19
27 F2 Farmer management System4 days Mon 02-09-19 Thu 05-09-19
28 WM2 Wholesale Management System5 days Fri 06-09-19 Thu 12-09-19
29 Data Entry 4 days Fri 13-09-19 Wed 18-09-19
30 Develop Media Content 9 days Fri 23-08-19 Wed 04-09-19
31 Code Review 6 days Thu 19-09-19 Thu 26-09-19
32 Prepare Unit Test 5 days Fri 27-09-19 Thu 03-10-19
33 Developed Application Verification7 days Fri 04-10-19 Mon 14-10-19
34 Create Training Materials 8 days Thu 19-09-19 Mon 30-09-19
35 M3: Development Phase Complete 0 days Mon 30-09-19 Mon 30-09-19
36 Pr oject Deploym ent 5 days Tue 01-10-19 Mon 07-10-19
37 Finalise Implementation Plan 1 day Tue 01-10-19 Tue 01-10-19
38 Finalise Contingency Plan 1 day Wed 02-10-19 Wed 02-10-19
39 Prepare for Deployment 1 day Thu 03-10-19 Thu 03-10-19
40 Deploy Application 2 days Fri 04-10-19 Mon 07-10-19
41 M4: Deploy Phase Complete 0 days Mon 07-10-19 Mon 07-10-19
42 Pr oject Handover 19 days Tue 08-10-19 Fri 01-11-19
43 Conduct-Post Project Review Meeting1 day Tue 08-10-19 Tue 08-10-19
44 Prepare Project Handover Documents7 days Tue 15-10-19 Wed 23-10-19
45 Conduct Performance Recognition 4 days Thu 24-10-19 Tue 29-10-19
46 Prepare Feedback For Team 2 days Wed 30-10-19 Thu 31-10-19
47 Provide Feedback For Team 1 day Fri 01-11-19 Fri 01-11-19
48 Release Team 0 days Fri 01-11-19 Fri 01-11-19
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
10-06
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vinee
Naren Reddy Ennam (Project Manager)[25%],Vine
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
28-06
Karumanchi Vamsi (Database Engi
Revanth Reddy Andru (So
Nare
W T F S S M T W T F S S M T W T
22 Apr '19 13 May '19 03 Jun '19 24 Jun '19 15 Jul '19 05 Aug '19 26 A
(Figure 1: The Gantt chart for the Project)
(Source: Created by author)
1. The Gantt chart
ID Task
Mode
Task Name Duration Start Fini sh
0 Developing the MBFSA
Project by Globex
133 days Wed
01-05-19
Fri 01-11-19
1 Phas e 1: Requir em ent Gather ing Phas e29 days Wed 01-05-19 Mon 10-06-19
2 Preparing of Business Case 2 days Wed 01-05-19 Thu 02-05-19
3 Requirement Gathering 4 days Fri 03-05-19 Wed 08-05-19
4 Develop Scope Management Plan 6 days Thu 09-05-19 Thu 16-05-19
5 Develop Project Management Plan 10 days Fri 17-05-19 Thu 30-05-19
6 Perform Initial Risk Assessment 2 days Fri 31-05-19 Mon 03-06-19
7 Initial Application Test Planning 3 days Tue 04-06-19 Thu 06-06-19
8 Develop Quality Plan 2 days Fri 07-06-19 Mon 10-06-19
9 M1: Requirement Complete 0 days Mon 10-06-19 Mon 10-06-19
10 Planning and Des igning 14 days Tue 11-06-19 Fri 28-06-19
11 Creating Conceptual Design 1 day Tue 11-06-19 Tue 11-06-19
12 Cr eate Login Des ign 6 days Wed 12-06-19 Wed 19-06-19
13 LG1 Weather Information System2 days Wed 12-06-19 Thu 13-06-19
14 LG1 Market Inf ormation System1 day Fri 14-06-19 Fri 14-06-19
15 F1 Farmer management System1 day Mon 17-06-19 Mon 17-06-19
16 WM1 Wholesale Management System2 days Tue 18-06-19 Wed 19-06-19
17 Create Implementation Plan 4 days Thu 20-06-19 Tue 25-06-19
18 Create Contengency Plan 3 days Wed 26-06-19 Fri 28-06-19
19 M2: Planning Phase Complete 0 days Fri 28-06-19 Fri 28-06-19
20 Phas e 2: Developm ent of MBFSA 76 days Mon 01-07-19 Mon 14-10-19
21 Create Database 10 days Mon 01-07-19 Fri 12-07-19
22 Make Prototype 19 days Mon 01-07-19 Thu 25-07-19
23 Excute Project Management Plan 20 days Fri 26-07-19 Thu 22-08-19
24 Pr oject Im plem entation 15 days Fri 23-08-19 Thu 12-09-19
25 LG2 Weather Information System6 days Fri 23-08-19 Fri 30-08-19
26 LG2 Market Inf ormation System5 days Fri 23-08-19 Thu 29-08-19
27 F2 Farmer management System4 days Mon 02-09-19 Thu 05-09-19
28 WM2 Wholesale Management System5 days Fri 06-09-19 Thu 12-09-19
29 Data Entry 4 days Fri 13-09-19 Wed 18-09-19
30 Develop Media Content 9 days Fri 23-08-19 Wed 04-09-19
31 Code Review 6 days Thu 19-09-19 Thu 26-09-19
32 Prepare Unit Test 5 days Fri 27-09-19 Thu 03-10-19
33 Developed Application Verification7 days Fri 04-10-19 Mon 14-10-19
34 Create Training Materials 8 days Thu 19-09-19 Mon 30-09-19
35 M3: Development Phase Complete 0 days Mon 30-09-19 Mon 30-09-19
36 Pr oject Deploym ent 5 days Tue 01-10-19 Mon 07-10-19
37 Finalise Implementation Plan 1 day Tue 01-10-19 Tue 01-10-19
38 Finalise Contingency Plan 1 day Wed 02-10-19 Wed 02-10-19
39 Prepare for Deployment 1 day Thu 03-10-19 Thu 03-10-19
40 Deploy Application 2 days Fri 04-10-19 Mon 07-10-19
41 M4: Deploy Phase Complete 0 days Mon 07-10-19 Mon 07-10-19
42 Pr oject Handover 19 days Tue 08-10-19 Fri 01-11-19
43 Conduct-Post Project Review Meeting1 day Tue 08-10-19 Tue 08-10-19
44 Prepare Project Handover Documents7 days Tue 15-10-19 Wed 23-10-19
45 Conduct Performance Recognition 4 days Thu 24-10-19 Tue 29-10-19
46 Prepare Feedback For Team 2 days Wed 30-10-19 Thu 31-10-19
47 Provide Feedback For Team 1 day Fri 01-11-19 Fri 01-11-19
48 Release Team 0 days Fri 01-11-19 Fri 01-11-19
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
10-06
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vinee
Naren Reddy Ennam (Project Manager)[25%],Vine
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
28-06
Karumanchi Vamsi (Database Engi
Revanth Reddy Andru (So
Nare
W T F S S M T W T F S S M T W T
22 Apr '19 13 May '19 03 Jun '19 24 Jun '19 15 Jul '19 05 Aug '19 26 A
(Figure 1: The Gantt chart for the Project)
(Source: Created by author)
3DEVELOPING THE MBFSA APPLICATION BY GLOBEX
2. The High Level Work Breakdown Structure
(Figure 2: The Work Breakdown Structure for the Project)
(Source: Created by author)
2. The High Level Work Breakdown Structure
(Figure 2: The Work Breakdown Structure for the Project)
(Source: Created by author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1.1 Milestones
The milestones defined for each of the phases of the project could be defined as:
1. M1: Requirement Complete, which is defined under the ‘Phase 1: Requirement
Gathering Phase’
2. M2: Planning Phase Complete, which is defined under the ‘Create Logic Design’
phase.
3. M3: Development Phase Complete, which is defined under the ‘Project
Implementation’ phase.
4. M4: Deploy Phase Complete, which is defined under the ‘Project Deployment’ phase.
5. Release Team, which is defined under the ‘Project Handover’ phase.
The milestones defined for each of the phases of the project could be defined as:
1. M1: Requirement Complete, which is defined under the ‘Phase 1: Requirement
Gathering Phase’
2. M2: Planning Phase Complete, which is defined under the ‘Create Logic Design’
phase.
3. M3: Development Phase Complete, which is defined under the ‘Project
Implementation’ phase.
4. M4: Deploy Phase Complete, which is defined under the ‘Project Deployment’ phase.
5. Release Team, which is defined under the ‘Project Handover’ phase.
1DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1.2 Activities or Tasks
1.2 Activities or Tasks
2DEVELOPING THE MBFSA APPLICATION BY GLOBEX
The different phases or activities defined within the project are described as:
1. Phase 1: Requirement Gathering Phase – In this phase, each of the requirements
would be described for the project. During this phase, each of the requirements would be
collected from the external people and thus a proper form of analysis would be generated for the
development team to develop the application in a planned manner.
2. Planning and Designing – During the phase, a proper analysis would be generated
from the previous phases. This would help the development team to plan and design the aspects
for the MBFSA. During the phase, the design of the application would be done.
3. Phase 2: Development of MBFSA – During this phase, the software developers
would develop the application. The software developers would develop the application by
making use of the proper kind of resources. During the development of the application, the
software developers and other concerned member involved within the project would help in
developing the application. The requirement of the farmers should be taken into wide
consideration. This would also help the teams in bringing the best kind of application for the
farmers.
4. Project Deployment – After the application has been developed, the project would be
deployed for the use of the farmers. The application would be highly helpful for the farmers in
order to measure the different aspects.
5. Project Handover – After a proper kind of feedback from the deployment of the
application, the project would be made handover the entire group of farmers. The farmers would
be provided with reports based on using the application. This would highly help the farmers in
making use of the systems developed by Globex,
The different phases or activities defined within the project are described as:
1. Phase 1: Requirement Gathering Phase – In this phase, each of the requirements
would be described for the project. During this phase, each of the requirements would be
collected from the external people and thus a proper form of analysis would be generated for the
development team to develop the application in a planned manner.
2. Planning and Designing – During the phase, a proper analysis would be generated
from the previous phases. This would help the development team to plan and design the aspects
for the MBFSA. During the phase, the design of the application would be done.
3. Phase 2: Development of MBFSA – During this phase, the software developers
would develop the application. The software developers would develop the application by
making use of the proper kind of resources. During the development of the application, the
software developers and other concerned member involved within the project would help in
developing the application. The requirement of the farmers should be taken into wide
consideration. This would also help the teams in bringing the best kind of application for the
farmers.
4. Project Deployment – After the application has been developed, the project would be
deployed for the use of the farmers. The application would be highly helpful for the farmers in
order to measure the different aspects.
5. Project Handover – After a proper kind of feedback from the deployment of the
application, the project would be made handover the entire group of farmers. The farmers would
be provided with reports based on using the application. This would highly help the farmers in
making use of the systems developed by Globex,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
3DEVELOPING THE MBFSA APPLICATION BY GLOBEX
4DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1.3 Resource Assignments
ID Task
Mode
Task Name
0 Developing the MBFSA
Project by Globex
1 Phas e 1: Requir em ent Gather ing Phas e
2 Preparing of Business Case
3 Requirement Gathering
4 Develop Scope Management Plan
5 Develop Project Management Plan
6 Perform Initial Risk Assessment
7 Initial Application Test Planning
8 Develop Quality Plan
9 M1: Requirement Complete
10 Planning and Des igning
11 Creating Conceptual Design
12 Cr eate Login Des ign
13 LG1 Weather Information System
14 LG1 Market Information System
15 F1 Farmer management System
16 WM1 Wholesale Management System
17 Create Implementation Plan
18 Create Contengency Plan
19 M2: Planning Phase Complete
20 Phas e 2: Developm ent of MBFSA
21 Create Database
22 Make Prototype
23 Excute Project Management Plan
24 Pr oject Im plem entation
25 LG2 Weather Information System
26 LG2 Market Information System
27 F2 Farmer management System
28 WM2 Wholesale Management System
29 Data Entry
30 Develop Media Content
31 Code Review
32 Prepare Unit Test
33 Developed Application Verification
34 Create Training Materials
35 M3: Development Phase Complete
36 Pr oject Deploym ent
37 Finalise Implementation Plan
38 Finalise Contingency Plan
39 Prepare for Deployment
40 Deploy Application
41 M4: Deploy Phase Complete
42 Pr oject Handover
43 Conduct-Post Project Review Meeting
44 Prepare Project Handover Documents
45 Conduct Performance Recognition
46 Prepare Feedback For Team
47 Provide Feedback For Team
48 Release Team
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
10-06
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
28-06
Karumanchi Vamsi (Database Engineer)
Revanth Reddy Andru (Software Engineer)[200%]
Naren Reddy Ennam (Project Manager)
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Bhargav Reddy Ambati (Quality Assurance Engin
Vineeth Reddy Anugu (System Analyst)
Revanth Reddy Andru (Software Engineer
Revanth Reddy Andru (Software Eng
Bhargav Reddy Ambati (Qual
Naren Reddy Ennam (Project Manager)
30-09
Naren Reddy Ennam (Project Manager
Naren Reddy Ennam (Project Manage
Revanth Reddy Andru (Software Eng
Karumanchi Vamsi (Database Engi
07-10
Karumanchi Vamsi (Database Eng
Naren Reddy Ennam (P
Naren Reddy Enna
Naren Reddy Enn
Naren Reddy En
01-11
W T F S S M T W T F S S M T W T F S S M T W T F S S
22 Apr '19 13 May '19 03 Jun '19 24 Jun '19 15 Jul '19 05 Aug '19 26 Aug '19 16 Sep '19 07 Oct '19 28 Oct '19
1.3 Resource Assignments
ID Task
Mode
Task Name
0 Developing the MBFSA
Project by Globex
1 Phas e 1: Requir em ent Gather ing Phas e
2 Preparing of Business Case
3 Requirement Gathering
4 Develop Scope Management Plan
5 Develop Project Management Plan
6 Perform Initial Risk Assessment
7 Initial Application Test Planning
8 Develop Quality Plan
9 M1: Requirement Complete
10 Planning and Des igning
11 Creating Conceptual Design
12 Cr eate Login Des ign
13 LG1 Weather Information System
14 LG1 Market Information System
15 F1 Farmer management System
16 WM1 Wholesale Management System
17 Create Implementation Plan
18 Create Contengency Plan
19 M2: Planning Phase Complete
20 Phas e 2: Developm ent of MBFSA
21 Create Database
22 Make Prototype
23 Excute Project Management Plan
24 Pr oject Im plem entation
25 LG2 Weather Information System
26 LG2 Market Information System
27 F2 Farmer management System
28 WM2 Wholesale Management System
29 Data Entry
30 Develop Media Content
31 Code Review
32 Prepare Unit Test
33 Developed Application Verification
34 Create Training Materials
35 M3: Development Phase Complete
36 Pr oject Deploym ent
37 Finalise Implementation Plan
38 Finalise Contingency Plan
39 Prepare for Deployment
40 Deploy Application
41 M4: Deploy Phase Complete
42 Pr oject Handover
43 Conduct-Post Project Review Meeting
44 Prepare Project Handover Documents
45 Conduct Performance Recognition
46 Prepare Feedback For Team
47 Provide Feedback For Team
48 Release Team
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
10-06
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
28-06
Karumanchi Vamsi (Database Engineer)
Revanth Reddy Andru (Software Engineer)[200%]
Naren Reddy Ennam (Project Manager)
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Revanth Reddy Andru (Software Engineer)[200%]
Bhargav Reddy Ambati (Quality Assurance Engin
Vineeth Reddy Anugu (System Analyst)
Revanth Reddy Andru (Software Engineer
Revanth Reddy Andru (Software Eng
Bhargav Reddy Ambati (Qual
Naren Reddy Ennam (Project Manager)
30-09
Naren Reddy Ennam (Project Manager
Naren Reddy Ennam (Project Manage
Revanth Reddy Andru (Software Eng
Karumanchi Vamsi (Database Engi
07-10
Karumanchi Vamsi (Database Eng
Naren Reddy Ennam (P
Naren Reddy Enna
Naren Reddy Enn
Naren Reddy En
01-11
W T F S S M T W T F S S M T W T F S S M T W T F S S
22 Apr '19 13 May '19 03 Jun '19 24 Jun '19 15 Jul '19 05 Aug '19 26 Aug '19 16 Sep '19 07 Oct '19 28 Oct '19
5DEVELOPING THE MBFSA APPLICATION BY GLOBEX
The different people and resource that would be assigned to each of the phases of the project are
defined as follows:
Name of Resources
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)
Revanth Reddy Andru (Software Engineer)
Karumanchi Vamsi (Database Engineer)
Bhargav Reddy Ambati (Quality Assurance Engineer)
Training
Software
Transport
The different people and resource that would be assigned to each of the phases of the project are
defined as follows:
Name of Resources
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)
Revanth Reddy Andru (Software Engineer)
Karumanchi Vamsi (Database Engineer)
Bhargav Reddy Ambati (Quality Assurance Engineer)
Training
Software
Transport
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1.4 Estimates for each activity or task
1.4 Estimates for each activity or task
7DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1.5 Project Budget
1.5 Project Budget
8DEVELOPING THE MBFSA APPLICATION BY GLOBEX
The entire phase of the project would be completed within an estimated budget of AUD $
480,600. This cost includes each of the costs that have been incurred for the project by making
use of the resources.
The entire phase of the project would be completed within an estimated budget of AUD $
480,600. This cost includes each of the costs that have been incurred for the project by making
use of the resources.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
9DEVELOPING THE MBFSA APPLICATION BY GLOBEX
Bibliography
Baig, M. M., GholamHosseini, H., & Connolly, M. J. (2015). Mobile healthcare applications:
system design review, critical issues and challenges. Australasian physical &
engineering sciences in medicine, 38(1), 23-38.
Sopegno, A., Calvo, A., Berruto, R., Busato, P., & Bocthis, D. (2016). A web mobile application
for agricultural machinery cost analysis. Computers and electronics in agriculture, 130,
158-168.
Williams, V., Price, J., Hardinge, M., Tarassenko, L., & Farmer, A. (2014). Using a mobile
health application to support self-management in COPD: a qualitative study. Br J Gen
Pract, 64(624), e392-e400.
Xin, J., & Zazueta, F. (2016). Technology trends in ICT–towards data-driven, farmer-centered
and knowledge-based hybrid cloud architectures for smart farming. Agricultural
Engineering International: CIGR Journal, 18(4), 275-279.
Bibliography
Baig, M. M., GholamHosseini, H., & Connolly, M. J. (2015). Mobile healthcare applications:
system design review, critical issues and challenges. Australasian physical &
engineering sciences in medicine, 38(1), 23-38.
Sopegno, A., Calvo, A., Berruto, R., Busato, P., & Bocthis, D. (2016). A web mobile application
for agricultural machinery cost analysis. Computers and electronics in agriculture, 130,
158-168.
Williams, V., Price, J., Hardinge, M., Tarassenko, L., & Farmer, A. (2014). Using a mobile
health application to support self-management in COPD: a qualitative study. Br J Gen
Pract, 64(624), e392-e400.
Xin, J., & Zazueta, F. (2016). Technology trends in ICT–towards data-driven, farmer-centered
and knowledge-based hybrid cloud architectures for smart farming. Agricultural
Engineering International: CIGR Journal, 18(4), 275-279.
1 out of 14
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.